You have been given the following information about the production of Usher Co., and are asked to provide the plant manager with information for a meeting with the vice president of operations.


Standard Cost Card

Direct materials (7 pounds at $5 per pound) $35.00

Direct labor (0.80 hours at $10) 8.00

Variable overhead (0.80 hours at $5 per hour) 4.00

Fixed overhead (0.80 hours at $7 per hour) 5.60

$52.60


The following is a variance report for the most recent period of operations.


Variances

Costs

Total Standard Cost

Price

Quantity

Direct materials $406,000 $4,154 F $9,400 U

Direct labor 92,800 4,008 U 7,400 U




Correct answer. Your answer is correct.

   

How many units were produced during the period?


Number of units


11600


Incorrect answer. Your answer is incorrect.  Try again.

   

How many pounds of raw materials were purchased and used during the period?


Raw material

Entry field with incorrect answer

11481.31 pounds


Incorrect answer. Your answer is incorrect.  Try again.

   

What was the actual cost per pound of raw materials? (Round answer to 2 decimal places, e.g. 1.25.)


Actual cost per pound of raw materials

$Entry field with incorrect answer

35 /lb


Incorrect answer. Your answer is incorrect.  Try again.

   

How many actual direct labor hours were worked during the period?


Actual direct labor hours

Entry field with incorrect answer

11600

 hours




Incorrect answer. Your answer is incorrect.  Try again.

   

What was the actual rate paid per direct labor hour? (Round answer to 2 decimal places, e.g. 1.25.)


Actual rate paid per direct labor hour

$Entry field with incorrect answer

83.45/hr

Click if you would like to Show Work for this question:

Open Show Work


0 0
Add a comment Improve this question Transcribed image text
Answer #1

The answer has been presented in the supporting sheet. All the parts has been soled with detailed explanation and format. For detailed explanation refer to the supporting sheet.

A B E F G H I J K L C D Answer 3 Part 1) 4 Units produced during the period = Standard cost of material for the period / stan26 Part 4) 27 Direct labour effeciency variance = (actual hours-standard hours)standard price 28 7700 = (actual hours - (112


answered by: ANURANJAN SARSAM
Add a comment
Know the answer?
Add Answer to:
Exercise 24-09
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Exercise 24-09 a-e (Part Level Submission) You have been given the following information about the production...

    Exercise 24-09 a-e (Part Level Submission) You have been given the following information about the production of Usher Co., and are asked to provide the plant manager with information for a meeting with the vice president of operations. Standard Cost Card $20.00 Direct materials (5 pounds at $4 per pound) Direct labor (0.80 hours at $10) Variable overhead (0.80 hours at $3 per hour) Fixed overhead (0.80 hours at $7 per hour) 8.00 2.40 5.60 $36.00 The following is a...

  • You have been given the following information about the production of Usher Co., and are asked...

    You have been given the following information about the production of Usher Co., and are asked to provide the plant manager with information for a meeting with the vice president of operations. Standard Cost Card Direct materials (5 pounds at $4 per pound) $20.00 Direct labor (0.80 hours at $10) 8.00 Variable overhead (0.80 hours at $3 per hour) 2.40 Fixed overhead (0.80 hours at $7 per hour) 5.60 $36.00 The following is a variance report for the most recent...

  • You have been given the following information about the production of Usher Co., and are asked...

    You have been given the following information about the production of Usher Co., and are asked to provide the plant manager with information for a meeting with the vice president of operations. Standard Cost Card Direct materials (8 pounds at $5 per pound) $40.00 Direct labor (0.70 hours at $10) 7.00 Variable overhead (0.70 hours at $3 per hour) 2.10 Fixed overhead (0.70 hours at $7 per hour) 4.90 $54.00 The following is a variance report for the most recent...

  • You have been given the following information about the production of Usher Co., and are asked to provide the plant man...

    You have been given the following information about the production of Usher Co., and are asked to provide the plant manager with information for a meeting with the vice president of operations. Direct materials (8 pounds at $4 per pound) Direct labor (0.70 hours at $10) Variable overhead (0.70 hours at $5 per hour) Fixed overhead (0.70 hours at $7 per hour) Standard Cost Card $32.00 7.00 3.50 4.90 $47.40 The following is a variance report for the most recent...

  • You have been given the following information about the production of Usher Co., and are asked to provide the plant mana...

    You have been given the following information about the production of Usher Co., and are asked to provide the plant manager with information for a meeting with the vice president of operations. Standard Cost Card Direct materials (6 pounds at $5 per pound) $30.00 Direct labor (0.70 hours at $10) 7.00 Variable overhead (0.70 hours at $4 per hour) 2.80 Fixed overhead (0.70 hours at $9 per hour) 6.30 $46.10 The following is a variance report for the most recent...

  • Exercise 24-03 (Video) X Your answer is incorrect. Try again. Stefani Company has gathered the following...

    Exercise 24-03 (Video) X Your answer is incorrect. Try again. Stefani Company has gathered the following information about its product. Direct materials: Each unit of product contains 4.50 pounds of materials. The average waste and spoilage per unit produced under normal conditions is 0.50 pounds. Materials cost $5 per pound, but Stefani always takes the 2.00% cash discount all of its suppliers offer. Freight costs average $0.25 per pound. Direct labor. Each unit requires 2.00 hours of labor. Setup, cleanup,...

  • Standard Standard Price (1) Standard Quantity or Hours 2.30 pounds 1.ee hours 1.00 hours or Rate...

    Standard Standard Price (1) Standard Quantity or Hours 2.30 pounds 1.ee hours 1.00 hours or Rate Inputs Direct materials Direct labor Variable manufacturing overhead (1) X (2) $39.10 $17.00 per pound $16.10 per hour $ 9.20 per hour Total standard cost per unit Direct materials Direct labor Variable manufacturing overhead Total Variance Reported Standard Price Quantity or Cost or Rate Efficiency 5782,000 $ 13,920 F $ 34,000 U $322,000 $ 4,200 $ 16,100 U $184,000 $4,700 F S "Applied to...

  • Vitex, Inc. manufactures a popular consumer product and it has provided the following data excerpts from...

    Vitex, Inc. manufactures a popular consumer product and it has provided the following data excerpts from its standard cost system: Inputs Direct materials Direct labor Variable manufacturing overhead Total standard cost per unit Quantity or Hours 2.20 pounds 1.00 hours 1.00 hours Price Or Rate $16.70 per pound $15.90 per hour $ 9.20 per hour Cost (1) (2) $36.74 $15.90 $ 9.20 $61.84 Direct materials Direct labor Variable manufacturing overhead Total Variances Reported Standard Price Quantity or Cost. Or Rate...

  • (1) Standard Quantity or Standard Standard Cost Price (1) (2) $41.75 $15.40 9.20 Inputs Direct materials...

    (1) Standard Quantity or Standard Standard Cost Price (1) (2) $41.75 $15.40 9.20 Inputs Direct materials Hours or Rate 2.50 pounds 1.00 hours $16.70 per pound Direct labor $15.40 per hour $ 9.20 per hour Variable manufacturing overhead 1.00 hours $66.35 Total standard cost per unit Variances Reported Quantity or Efficiency $33,400 U $15,400 U Total Standard Price Cost $668,000 $ 12,180 F $246,400 3,400 U $147,200 $ 4,900 F or Rate Direct materials Direct labor Variable manufacturing overhead $...

  • Problem 23-4A (Part Level Submission) Kansas Company uses a standard cost accounting system. In 2017, the...

    Problem 23-4A (Part Level Submission) Kansas Company uses a standard cost accounting system. In 2017, the company produced 28,400 units. Each unit took several pounds of direct materials and 1.6 standard hours of direct labor at a standard hourly rate of $11.00. Normal capacity was 50,300 direct labor hours. During the year, 130,700 pounds of raw materials were purchased at $0.95 per pound. All materials purchased were used during the year. (d) X Your answer is incorrect. Try again. If...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT