Information is given in the Question
Machine hours | 158000 |
Fixed manufacturing | $ 653,000.00 |
Variable manufacturing overhead cost per machine hour | $ 5.00 |
1. Calculate predetermine overhead rate
Fixed manufacturing overhead | $ 653,000.00 |
Variable manufacturing overhead ($5*158000 machine hours) | $ 790,000.00 |
Total manufacturing costs | $ 1,443,000.00 |
Plantwide predetermined overhead is given below: | |
Total manufacturing overhead | $ 1,443,000.00 |
Total machine hours | 158000 |
Pre-determine overhead rate(total manufacturing overhead/total machine hours) | $ 9.13 |
2. Total manufacturing cost applied to Job 400
Direct Materials | $ 400.00 |
Direct Labor | $ 260.00 |
Manufacturing overhead ($9.13*30(direct labor hours) | $ 273.90 |
Total manufacturing cost assigned to job 400 | $ 933.90 |
3. Calculate the unit of production cost
Total manufacturing cost | $ 933.90 |
No. of units in the job (60 Units) | 60 |
Unit of production cost | 15.57 |
4. Calculate the selling price per unit with 120% markup
Total manufacturing cost | $ 933.90 |
Markup (130% of manufacturing cost) | $ 1,214.07 |
Selling price for job 400 | $ 2,147.97 |
No. of units in job 400 | 60 |
Selling price per unit | $ 35.80 |
Moody Corporation uses a job-order costing system with a plantwide predetermined overhead rate based on machine-hours....
Moody Corporation uses a job-order costing system with a plantwide predetermined overhead rate based on machine-hours. At the beginning of the year, the company made the following estimates: Machine-hours required to support estimated production Fixed manufacturing overhead cost Variable manufacturing overhead cost per machine-hour 151,000 $ 650,000 $ 4.10 Required: 1. Compute the plantwide predetermined overhead rate. 2. During the year, Job 400 was started and completed. The following information was available with respect to this job: Direct materials Direct...
Moody Corporation uses a job-order costing system with a plantwide predetermined overhead rate based on machine-hours. At the beginning of the year, the company made the following estimates: ots Machine-hours required to support estimated production 152, eee Fixed manufacturing overhead cost $659,800 Variable manufacturing overhead cost per machine-hour $ 4.30 - eBook Required: 1. Compute the plantwide predetermined overhead rate. 2. During the year, Job 400 was started and completed. The following information was available with respect to this job!...
Moody Corporation uses a job-order costing system with a plantwide predetermined overhead rate based on machine-hours. At the beginning of the year, the company made the following estimates: Machine-hours required to support estimated production 100,000 Fixed manufacturing overhead cost $ 650,000 Variable manufacturing overhead cost per machine-hour $ 3.00 Required: 1. Compute the plantwide predetermined overhead rate. 2. During the year, Job 400 was started and completed. The following information was available with respect to this job: Direct materials $...
Moody Corporation uses a job-order costing system with a plantwide predetermined overhead rate based on machine-hours. At the beginning of the year, the company made the following estimates: Machine-hours required to support estimated production Fixed manufacturing overhead cost Variable manufacturing overhead cost per machine-hour 151,000 $653,000 $ 5.00 Required: 1. Compute the plantwide predetermined overhead rate. 2. During the year, Job 400 was started and completed. The following information was available with respect to this job: Direct materials Direct labor...
Moody Corporation uses a job-order costing system with a plantwide predetermined overhead rate based on machine-hours. At the beginning of the year, the company made the following estimates: Machine-hours required to support estimated production 100,000 Fixed manufacturing overhead cost Variable manufacturing overhead cost per machine-hour $3.ee $650,0e0 Required 1. Compute the plantwide predetermined overhead rate. 2. During the year, Job 400 was started and completed. The following information was available with respect to this job: Direct materials Direct labor cost...
Moody Corporation uses a job-order costing system with a plantwide predetermined overhead rate based on machine-hours. At the beginning of the year, the company made the following estimates: Machine-hours required to support estimated production 154,000 Fixed manufacturing overhead cost $ 652,000 Variable manufacturing overhead cost per machine-hour $ 4.20 Required: 1. Compute the plantwide predetermined overhead rate. 2. During the year, Job 400 was started and completed. The following information was available with respect to this job: Direct materials $...
Moody Corporation uses a job-order costing system with a plantwide predetermined overhead rate based on machine-hours. At the beginning of the year, the company made the following estimates: Machine-hours required to support estimated production 153,000 Fixed manufacturing overhead cost $ 659,000 Variable manufacturing overhead cost per machine-hour $ 4.90 Required: 1. Compute the plantwide predetermined overhead rate. 2. During the year, Job 400 was started and completed. The following information was available with respect to this job: Direct materials $...
Moody Corporation uses a job-order costing system with a plantwide predetermined overhead rate based on machine-hours. At the beginning of the year, the company made the following estimates: Machine-hours required to support estimated production 156,000 Fixed manufacturing overhead cost $ 658,000 Variable manufacturing overhead cost per machine-hour $ 4.60 Required: 1. Compute the plantwide predetermined overhead rate. 2. During the year, Job 400 was started and completed. The following information was available with respect to this job: Direct materials $...
Moody Corporation uses a job-order costing system with a plantwide predetermined overhead rate based on machine-hours. At the beginning of the year, the company made the following estimates: Machine-hours required to support estimated production 154,000 Fixed manufacturing overhead cost $ 655,000 Variable manufacturing overhead cost per machine-hour $ 4.50 Required: 1. Compute the plantwide predetermined overhead rate. 2. During the year, Job 400 was started and completed. The following information was available with respect to this job: Direct materials $...
Moody Corporation uses a job-order costing system with a plantwide predetermined overhead rate based on machine-hours. At the beginning of the year, the company made the following estimates: Machine-hours required to support estimated production 157,000 Fixed manufacturing overhead cost $ 651,000 Variable manufacturing overhead cost per machine-hour $ 4.50 Required: 1. Compute the plantwide predetermined overhead rate. 2. During the year, Job 400 was started and completed. The following information was available with respect to this job: Direct materials $...