Question

You are evaluating the following mutually exclusive projects for your firm, whose cost of capital is...

You are evaluating the following mutually exclusive projects for your firm, whose cost of capital is 14%, and all dollar amounts are in millions.

1. Verify the NPV and IRR of each project.

2. What is your recommendation?

Show how to calculate NPV and IRR

Project

Required Return

Life

IO

NCF1-n

NPV

IRR

Alpha

12%

10 years

$50

$20

Beta

8%

5

$50

$25

0 0
Add a comment Improve this question Transcribed image text
Answer #1

NPV = PV of Cash Inflows - PV of Cash Outflows

Project Alpha:

Year CF PVF @12% Disc CF
0 $ -50.00     1.0000 $ -50.00
1 $   20.00     0.8929 $   17.86
2 $   20.00     0.7972 $   15.94
3 $   20.00     0.7118 $   14.24
4 $   20.00     0.6355 $   12.71
5 $   20.00     0.5674 $   11.35
6 $   20.00     0.5066 $   10.13
7 $   20.00     0.4523 $      9.05
8 $   20.00     0.4039 $      8.08
9 $   20.00     0.3606 $      7.21
10 $   20.00     0.3220 $      6.44
NPV $   63.00

Project Beta:

Year CF PVF @8% Disc CF
0 $ -50.00     1.0000 $ -50.00
1 $   25.00     0.9259 $   23.15
2 $   25.00     0.8573 $   21.43
3 $   25.00     0.7938 $   19.85
4 $   25.00     0.7350 $   18.38
5 $   25.00     0.6806 $   17.01
NPV $   49.82

IRR is the Rate at which PV of Cash Inflows are equal to PV of Cash Outflows.

Project Alpha:

Year CF PVF @38% Disc CF PVF @39% Disc CF
0 $ -50.00     1.0000 $ -50.00     1.0000 $ -50.00
1 $   20.00     0.7246 $   14.49     0.7194 $   14.39
2 $   20.00     0.5251 $   10.50     0.5176 $   10.35
3 $   20.00     0.3805 $      7.61     0.3724 $      7.45
4 $   20.00     0.2757 $      5.51     0.2679 $      5.36
5 $   20.00     0.1998 $      4.00     0.1927 $      3.85
6 $   20.00     0.1448 $      2.90     0.1386 $      2.77
7 $   20.00     0.1049 $      2.10     0.0997 $      1.99
8 $   20.00     0.0760 $      1.52     0.0718 $      1.44
9 $   20.00     0.0551 $      1.10     0.0516 $      1.03
10 $   20.00     0.0399 $      0.80     0.0371 $      0.74
NPV $      0.53 $    -0.62

IRR = Rate at which least +ve NPV + [ NPV at that Rate / Change in NPV due to 1% inc in Disc Rate ] * 1%

= 38% + [ 0.53 / 1.15 ] * 1%

= 38% + 0.46%

= 38.46%

Project Beta:

Year CF PVF @41% Disc CF PVF @42% Disc CF
0 $ -50.00     1.0000 $ -50.00     1.0000 $ -50.00
1 $   25.00     0.7092 $   17.73     0.7042 $   17.61
2 $   25.00     0.5030 $   12.57     0.4959 $   12.40
3 $   25.00     0.3567 $      8.92     0.3492 $      8.73
4 $   25.00     0.2530 $      6.33     0.2459 $      6.15
5 $   25.00     0.1794 $      4.49     0.1732 $      4.33
NPV $      0.03 $    -0.79

IRR = Rate at which least +ve NPV + [ NPV at that Rate / Change in NPV due to 1% inc in Disc Rate ] * 1%

= 41% + [ 0.03 / 0.82 ] * 1%

= 41% + 0.04%%

= 41.04%

Incase of Mutually exclsuive Projects, Seletc the Project with Higher NPV. Hence select Alpha Project.

Add a comment
Know the answer?
Add Answer to:
You are evaluating the following mutually exclusive projects for your firm, whose cost of capital is...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • You are evaluating the following mutually exclusive projects for your firm, whose cost of capital is...

    You are evaluating the following mutually exclusive projects for your firm, whose cost of capital is 14%, and all dollar amounts are in millions. 1. Verify the NPV and IRR of each project. 2. What is your recommendation? Project Required Return Life IO NCF1-n NPV IRR Alpha 12% 10 years $50 $20 $63 38.45% Beta 8% 5 $50 $25 $49.82 41.04% EAABeta = $12.48 million > EAAAlpha = $11.15 million so Accept B and Reject A Is the answer- Please...

  • , A firm is evaluating the following two mutually exclusive, but quite profitable 2-year projects...

    , A firm is evaluating the following two mutually exclusive, but quite profitable 2-year projects I and II, with cash flows at t0,1 and 2 as follows: Year t Project I Project II - $10,000 +20,000 +10,000 $10,000 +$40,000 Compute each project's NPV for r=0% and r=10%, where r= discount rate or required rate Based on the cash flow patterns for the two projects and the answer to part a), can we Using the analytical formulation of the intersection of...

  • Crane Corp. management is evaluating two mutually exclusive projects. The cost of capital is 15 percent....

    Crane Corp. management is evaluating two mutually exclusive projects. The cost of capital is 15 percent. Costs and cash flows for each project are given in the following table. Year Project 1 Project 2 0 $1,190,556 -$1,107,928 225,000 315,000 315,000 315,000 405,000 315,000 450,000 315,000 675,000 315,000 Calculate NPV and IRR of two projects. (Enter negative amounts using negative sign, e.g. -45.25. Do not round discount factors. Round other intermediate calculations and final answer to O decimal places, e.. 1,525....

  • Crane Corp. management is evaluating two mutually exclusive projects. The cost of capital is 15 percent....

    Crane Corp. management is evaluating two mutually exclusive projects. The cost of capital is 15 percent. Costs and cash flows for each project are given in the following table. Year Project 1 Project 2 0 -$1,266,858 -$1,100,968 1 256,000 319,000 2 318,000 319,000 3 480,000 319,000 4 483,000 319,000 5 773,000 319,000 NPV of project 1 is$ NPV of project 2 is$ IRR of project 1 is % IRR of project 2 is % Crane Corp should accept:

  • 6) A firm is evaluating three mutually exclusive capital budgeting projects. The net present value of...

    6) A firm is evaluating three mutually exclusive capital budgeting projects. The net present value of each project is shown below. Given this information, which project() should the firm accept? Project 1 100,000 NPV, S Project 2 10,000 Project 3 - 100,000 a) accept Projects 1 and 2, and reject Project 3 b) accept Projects 1 and 3, and reject Project 2 c) accept Project 3, and reject Projects 1 and 2 d) accept Project 1, and reject Projects 2...

  • A firm with a 14% WACC is evaluating two projects for this year's capital budget. After-tax...

    A firm with a 14% WACC is evaluating two projects for this year's capital budget. After-tax cash flows, including depreciation, are as follows: 0 1 2 3 4 5 Project M -$24,000 $8,000 $8,000 $8,000 $8,000 $8,000 Project N -$72,000 $22,400 $22,400 $22,400 $22,400 $22,400 Assuming the projects are independent, which one(s) would you recommend? -Select-Only Project M would be accepted because NPV(M) > NPV(N).Only Project N would be accepted because NPV(N) > NPV(M).Both projects would be accepted since both...

  • MIRR and NPV Your company is considering two mutually exclusive projects, X and Y, whose costs...

    MIRR and NPV Your company is considering two mutually exclusive projects, X and Y, whose costs and cash flows are shown below: Year X Y 0 -$5,000 -$5,000 1 1,000 4,500 2 1,500 1,500 3 2,000 1,000 4 4,000 500 The projects are equally risky, and their cost of capital is 14%. You must make a recommendation, and you must base it on the modified IRR (MIRR). Calculate the two projects' MIRRs. Do not round intermediate calculations. Round your answers...

  • CAPITAL BUDGETING CRITERIA 1. A firm with a 13% WACC is evaluating two projects for this...

    CAPITAL BUDGETING CRITERIA 1. A firm with a 13% WACC is evaluating two projects for this year's capital budget. After-tax cash flows, including depreciation, are as follows: 0 1 2 3 4 5 Project M -$18,000 $6,000 $6,000 $6,000 $6,000 $6,000 Project N -$54,000 $16,800 $16,800 $16,800 $16,800 $16,800 Calculate NPV for each project. Round your answers to the nearest cent. Do not round your intermediate calculations. Project M    $ Project N    $ Calculate IRR for each project. Round your answers to...

  • CAPITAL BUDGETING CRITERIA A firm with a 14% WACC is evaluating two projects for this year's...

    CAPITAL BUDGETING CRITERIA A firm with a 14% WACC is evaluating two projects for this year's capital budget. After-tax cash flows, including depreciation, are as follows: 0 1 2 5 Project M Project N - $30,000 $10,000 $10,000 $10,000 $10,000 $10,000 $90,000 $28,000 $28,000 $28,000 $28,000 $28,000 a. Calculate NPV for each project. Round your answers to the nearest cent. Do not round your intermediate calculations. Project M $ Project N $ Calculate IRR for each project. Round your answers...

  • Thomas Company is considering two mutually exclusive projects. The firm has a 12% cost of capital....

    Thomas Company is considering two mutually exclusive projects. The firm has a 12% cost of capital. Cash inflows Initial investment Year 1 Year 2 Year 3 Year 4 Year 5 Project A Project B $130000 $85000 $25000 $35000 $45000 $50000 $55000 $40000 $35000 $30000 $10000 $5000 Evaluate and discuss the rankings of NPV and IRR of the two projects on the basis of your finding. O A Project B should be chosen because it has a higher IRR than Project...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT