Crane Corp. management is evaluating two mutually exclusive projects. The cost of capital is 15 percent. Costs and cash flows for each project are given in the following table.
Year | Project 1 | Project 2 | ||
0 | -$1,266,858 | -$1,100,968 | ||
1 | 256,000 | 319,000 | ||
2 | 318,000 | 319,000 | ||
3 | 480,000 | 319,000 | ||
4 | 483,000 | 319,000 | ||
5 | 773,000 | 319,000 |
NPV of project 1 is$
NPV of project 2 is$
IRR of project 1 is %
IRR of project 2 is %
Crane Corp should accept:
Crane Corp. management is evaluating two mutually exclusive projects. The cost of capital is 15 percent....
Crane Corp. management is evaluating two mutually exclusive projects. The cost of capital is 15 percent. Costs and cash flows for each project are given in the following table. Year Project 1 Project 2 0 $1,190,556 -$1,107,928 225,000 315,000 315,000 315,000 405,000 315,000 450,000 315,000 675,000 315,000 Calculate NPV and IRR of two projects. (Enter negative amounts using negative sign, e.g. -45.25. Do not round discount factors. Round other intermediate calculations and final answer to O decimal places, e.. 1,525....
Yong Importers, an Asian import company, is evaluating two mutually exclusive projects, A and B. The relevant cash flows for each project are given in the table below. The cost of capital for use in evaluating each of these equally risky projects is 10 percent. initial investment project a project b $350,000 $425,000 year cash inflows (cf) 1 140,000 175,000 2 165,000 150,000 3 190,000 125,000 4 100,000 5 75,000 6 50,000 Which project should be chosen on the basis of...
A firm with a 14% WACC is evaluating two projects for this year's capital budget. After-tax cash flows, including depreciation, are as follows: 0 1 2 3 4 5 Project M -$24,000 $8,000 $8,000 $8,000 $8,000 $8,000 Project N -$72,000 $22,400 $22,400 $22,400 $22,400 $22,400 Assuming the projects are independent, which one(s) would you recommend? -Select-Only Project M would be accepted because NPV(M) > NPV(N).Only Project N would be accepted because NPV(N) > NPV(M).Both projects would be accepted since both...
You are evaluating the following mutually exclusive projects for your firm, whose cost of capital is 14%, and all dollar amounts are in millions. 1. Verify the NPV and IRR of each project. 2. What is your recommendation? Project Required Return Life IO NCF1-n NPV IRR Alpha 12% 10 years $50 $20 $63 38.45% Beta 8% 5 $50 $25 $49.82 41.04% EAABeta = $12.48 million > EAAAlpha = $11.15 million so Accept B and Reject A Is the answer- Please...
(Mutually exclusive projects and NPV) You have been assigned the task of evaluating two mutually exclusive projects with the following projected cash flows: Year Project A Project B Cash Flow Cash Flow $(102,000) $(102,000) 40,000 40.000 40.000 40,000 0 40,000 215,000 If the appropriate discount rate on these projects is 9 percent, which would be chosen and why? The NPV of Project Ass (Round to the nearest cont.)
You are evaluating the following mutually exclusive projects for your firm, whose cost of capital is 14%, and all dollar amounts are in millions. 1. Verify the NPV and IRR of each project. 2. What is your recommendation? Show how to calculate NPV and IRR Project Required Return Life IO NCF1-n NPV IRR Alpha 12% 10 years $50 $20 Beta 8% 5 $50 $25
John is evaluating two mutually exclusive capital budgeting projects that have the following characteristics: 1 Cash Flows Year Project Project R 0 $(10,000) $(10,000) 0 5,000 2 0 5.000 3 0 5,000 4 22,000 5,000 1) Calculate NPV of each project if the firm's required rate of return (1) is 9 percent. 2) which project should be purchased? >
11.07 CAPITAL BUDGETING CRITERIA A firm with a 13% WACC is evaluating two projects for this year's capital budget. After-tax cash flows, including depreciation, are as follows: 0 1 2 3 4 5 Project M -$6,000 $2,000 $2,000 $2,000 $2,000 $2,000 Project N -$18,000 $5,600 $5,600 $5,600 $5,600 $5,600 Calculate NPV for each project. Round your answers to the nearest cent. Do not round your intermediate calculations. Project M $ Project N $ Calculate IRR for each project. Round your answers...
CAPITAL BUDGETING CRITERIA A firm with a 14% WACC is evaluating two projects for this year's capital budget. After-tax cash flows, including depreciation, are as follows: 0 1 2 5 Project M Project N - $30,000 $10,000 $10,000 $10,000 $10,000 $10,000 $90,000 $28,000 $28,000 $28,000 $28,000 $28,000 a. Calculate NPV for each project. Round your answers to the nearest cent. Do not round your intermediate calculations. Project M $ Project N $ Calculate IRR for each project. Round your answers...
If mutually exclusive projects with normal cash flows are being analyzed, the net present value (NPV) and internal rate of return (IRR) methods agree. Projects Y and Z are mutually exclusive projects. Their cash flows and NPV profiles are shown as follows. NPV (Dollars) 800 Year Project Y Project Z 0 -$1,500 -$1,500 1 $200 $900 2 $400 $600 $600 $300 4 $1,000 $200 Project Y Project 2 If the weighted average cost of capital (WACC) for each project is...