Question

John is evaluating two mutually exclusive capital budgeting projects that have the following characteristics: 1 Cash Flows Ye
0 0
Add a comment Improve this question Transcribed image text
Answer #1

NPV = Present value of all the future cash inflow discounted at required rate of return - initial outlay

1)

Project Q:

NPV = 22000/(1+ 0.09)^4 - 10000

= $5585.35 Answer

Project R:

NPV = 5000/(1+ 0.09)^1 + 5000/(1+ 0.09)^2 + 5000/(1+ 0.09)^3 + 5000/(1+ 0.09)^4 - 10000

= $6198.60 Answer

2)

Since NPV of project R is higher than project Q, we should purchase project R.

Please let me know in case you have any queries and I will be happy to assist you.

Add a comment
Know the answer?
Add Answer to:
John is evaluating two mutually exclusive capital budgeting projects that have the following characteristics: 1 Cash...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • As the director of capital budgeting for Denver Corporation, you are evaluating two mutually exclusive projects...

    As the director of capital budgeting for Denver Corporation, you are evaluating two mutually exclusive projects with the following net cash flows. Project X has cash flows of -100,000 in year 0, 50,000 in year 1, 40,000 in year 2, 30,000 in year 3 and 10,000 in year 4. Project Z has cash flows of -100,000 in year 0, 10,000 in year 1, 30,000 in year 2, 40,000 in year 3 and 60,000 in year 4. If Denver's cost of...

  • As the director of capital budgeting for KU dairy, you are evaluating two mutually exclusive projects...

    As the director of capital budgeting for KU dairy, you are evaluating two mutually exclusive projects with the following net cash flows: Year Project A Cash Flow Project B Cash Flow 0 -100,000 -100,000 1 50,000 10,000 2 40,000 30,000 3 30,000 40,000 4 10,000 60,000 If KU’s cost of capital is 15%, examine which project you would choose?

  • (Mutually exclusive projects and NPV) You have been assigned the task of evaluating two mutually exclusive...

    (Mutually exclusive projects and NPV) You have been assigned the task of evaluating two mutually exclusive projects with the following projected cash flows: Year Project A Project B Cash Flow Cash Flow $(102,000) $(102,000) 40,000 40.000 40.000 40,000 0 40,000 215,000 If the appropriate discount rate on these projects is 9 percent, which would be chosen and why? The NPV of Project Ass (Round to the nearest cont.)

  • 6) A firm is evaluating three mutually exclusive capital budgeting projects. The net present value of...

    6) A firm is evaluating three mutually exclusive capital budgeting projects. The net present value of each project is shown below. Given this information, which project() should the firm accept? Project 1 100,000 NPV, S Project 2 10,000 Project 3 - 100,000 a) accept Projects 1 and 2, and reject Project 3 b) accept Projects 1 and 3, and reject Project 2 c) accept Project 3, and reject Projects 1 and 2 d) accept Project 1, and reject Projects 2...

  • Crane Corp. management is evaluating two mutually exclusive projects. The cost of capital is 15 percent....

    Crane Corp. management is evaluating two mutually exclusive projects. The cost of capital is 15 percent. Costs and cash flows for each project are given in the following table. Year Project 1 Project 2 0 -$1,266,858 -$1,100,968 1 256,000 319,000 2 318,000 319,000 3 480,000 319,000 4 483,000 319,000 5 773,000 319,000 NPV of project 1 is$ NPV of project 2 is$ IRR of project 1 is % IRR of project 2 is % Crane Corp should accept:

  • ON EXCEL The director of capital budgeting for Giant Inc. has identified two mutually exclusive projects,...

    ON EXCEL The director of capital budgeting for Giant Inc. has identified two mutually exclusive projects, L and S, with the following expected net cash flows and a required rate of return of 10 percent: Expected Net Cash Flows Year Project S Project L ($210,000) 0 ($161,000) 90,000 10,000 - 0 20,000 60,000 80,000 20,000 60,000 + 90,000 90,000 10,000 Build an automatic spread sheet that calculates: 1. the NPV of both projects with 2 different methods (NPV of excel...

  • Question :1 (40%, 8% per sub question) A firm is evaluating two mutually exclusive projects that...

    Question :1 (40%, 8% per sub question) A firm is evaluating two mutually exclusive projects that have unequal lives. The firm must evaluate the projects using the annualized net present value approach and recommend which project they should select. The firm's cost of capital has been determined to be 14 percent, and the projects have the following initial investments and cash flows: The NPVs of Projects R and S are The annualized NPV of Project R is The annualized NPV...

  • , A firm is evaluating the following two mutually exclusive, but quite profitable 2-year projects...

    , A firm is evaluating the following two mutually exclusive, but quite profitable 2-year projects I and II, with cash flows at t0,1 and 2 as follows: Year t Project I Project II - $10,000 +20,000 +10,000 $10,000 +$40,000 Compute each project's NPV for r=0% and r=10%, where r= discount rate or required rate Based on the cash flow patterns for the two projects and the answer to part a), can we Using the analytical formulation of the intersection of...

  • 11-7 CAPITAL BUDGETING CRITERIA A firm with a 14% WACC is evaluating two projects for this...

    11-7 CAPITAL BUDGETING CRITERIA A firm with a 14% WACC is evaluating two projects for this year's capital budget. After-tax cash flows, including depreciation, are as follows: 3 Project M Project N - $30,000 - $90,000 $10,000 $28,000 $10,000 $28,000 $10,000 $28,000 $10,000 $28,000 $10,000 $28,000 a. Calculate NPV, IRR, MIRR, payback, and discounted payback for each project. b. Assuming the projects are independent, which one(s) would you recommend? c. If the projects are mutually exclusive, which would you recommend?...

  • If mutually exclusive projects with normal cash flows are being analyzed, the net present value (NPV)...

    If mutually exclusive projects with normal cash flows are being analyzed, the net present value (NPV) and internal rate of return (IRR) methods agree. Projects Y and Z are mutually exclusive projects. Their cash flows and NPV profiles are shown as follows. NPV (Dollars) 800 Year Project Y Project Z 0 -$1,500 -$1,500 1 $200 $900 2 $400 $600 $600 $300 4 $1,000 $200 Project Y Project 2 If the weighted average cost of capital (WACC) for each project is...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT