11.07
CAPITAL BUDGETING CRITERIA
A firm with a 13% WACC is evaluating two projects for this year's capital budget. After-tax cash flows, including depreciation, are as follows:
0 | 1 | 2 | 3 | 4 | 5 |
Project M | -$6,000 | $2,000 | $2,000 | $2,000 | $2,000 | $2,000 |
Project N | -$18,000 | $5,600 | $5,600 | $5,600 | $5,600 | $5,600 |
Calculate NPV for each project. Round your answers to the
nearest cent. Do not round your intermediate calculations.
Project M $
Project N $
Calculate IRR for each project. Round your answers to two
decimal places. Do not round your intermediate calculations.
Project M %
Project N %
Calculate MIRR for each project. Round your answers to two
decimal places. Do not round your intermediate calculations.
Project M %
Project N %
Calculate payback for each project. Round your answers to two
decimal places. Do not round your intermediate calculations.
Project M years
Project N years
Calculate discounted payback for each project. Round your
answers to two decimal places. Do not round your intermediate
calculations.
Project M years
Project N years
SEE THE IMAGE. ANY DOUBTS, FEEL FREE TO ASK. THUMBS UP PLEASE
FOR b : E :
FOR c : B
FOR d : B
11.07 CAPITAL BUDGETING CRITERIA A firm with a 13% WACC is evaluating two projects for this...
CAPITAL BUDGETING CRITERIA A firm with a 14% WACC is evaluating two projects for this year's capital budget. After-tax cash flows, including depreciation, are as follows: 0 1 2 5 Project M Project N - $30,000 $10,000 $10,000 $10,000 $10,000 $10,000 $90,000 $28,000 $28,000 $28,000 $28,000 $28,000 a. Calculate NPV for each project. Round your answers to the nearest cent. Do not round your intermediate calculations. Project M $ Project N $ Calculate IRR for each project. Round your answers...
CAPITAL BUDGETING CRITERIA A firm with a 13% WACC is evaluating two projects for this year's capital budget. After-tax cash flows, including depreciation are as follows 0 1 2 3 4 5 Project -$27.000 $9.000 59.000 9,000 $9.000 $9,000 Project-581,000 $25,200 $25,200 $25,200 $25,200 $25.200 - Calculate NPV for each project. Round your answers to the nearest cent. Do not round your intermediate calculations. Projects Proiect N $ Calculate IRR for each project. Round your answers to two decimal places....
CAPITAL BUDGETING CRITERIA 1. A firm with a 13% WACC is evaluating two projects for this year's capital budget. After-tax cash flows, including depreciation, are as follows: 0 1 2 3 4 5 Project M -$18,000 $6,000 $6,000 $6,000 $6,000 $6,000 Project N -$54,000 $16,800 $16,800 $16,800 $16,800 $16,800 Calculate NPV for each project. Round your answers to the nearest cent. Do not round your intermediate calculations. Project M $ Project N $ Calculate IRR for each project. Round your answers to...
A firm with a 13% WACC is evaluating two projects for this year's capital budget. After-tax cash flows, including depreciation, are as follows: 0 1 2 3 4 5 Project M -$21,000 $7,000 $7,000 $7,000 $7,000 $7,000 Project N -$63,000 $19,600 $19,600 $19,600 $19,600 $19,600 Calculate NPV for each project. Round your answers to the nearest cent. Do not round your intermediate calculations. Project M $ Project N $ Calculate IRR for each project. Round your answers to two decimal places. Do...
A firm with a 13% WACC is evaluating two projects for this year's capital budget. After-tax cash flows, including depreciation, are as follows: 0 1 2 3 4 5 Project M $(21,000) $7,000 $7,000 $7,000 $7,000 $7,000 Project N $(63,000) $19,600 $19,600 $19,600 $19,600 $19,600 Calculate NPV for each project. Round your answers to the nearest cent. Do not round your intermediate calculations. Project M $ Project N $ Calculate IRR for each project. Round your answers to two decimal places. Do...
A firm with a 14% WACC is evaluating two projects for this year's capital budget. After-tax cash flows, including depreciation, are as follows: 0 1 2 3 4 5 Project M -$24,000 $8,000 $8,000 $8,000 $8,000 $8,000 Project N -$72,000 $22,400 $22,400 $22,400 $22,400 $22,400 Calculate NPV for each project. Round your answers to the nearest cent. Do not round your intermediate calculations. Project M $ Project N $ Calculate IRR for each project. Round your answers to two decimal places. Do...
A firm with a 14% WACC is evaluating two projects for this year's capital budget. After-tax cash flows, including depreciation, are as follows: 0 1 2 3 4 5 Project M -$24,000 $8,000 $8,000 $8,000 $8,000 $8,000 Project N -$72,000 $22,400 $22,400 $22,400 $22,400 $22,400 Assuming the projects are independent, which one(s) would you recommend? -Select-Only Project M would be accepted because NPV(M) > NPV(N).Only Project N would be accepted because NPV(N) > NPV(M).Both projects would be accepted since both...
CAPITAL BUDGETING CRITERIA A firm with a 13% WACC is evaluating two projects for this year's capital budget. After-tax cash flows, including depreciation, are as follows: Project M Project N - $15,000 $5,000 $5,000 $5,000 $5,000 $5,000 -$45,000 $14,000 $14,000 $14,000 $14,000 $14,000 a. Calculate NPV for each project. Round your answers to the nearest cent. Do not round your intermediate calculations. Project M $ Project N $ Calculate IRR for each project. Round your answers to two decimal places....
CAPITAL BUDGETING CRITERIA A firm with a 14% WACC is evaluating two projects for this year's capital budget. After-tax cash flows, including depreciation, are as follows: 0 1 2 3 4 5 Project M Project N - $9,000 $3,000 $27,000 $8,400 $3,000 $8,400 $3,000 $8,400 $3,000 $8,400 $3,000 $8,400 a. Calculate NPV for each project. Round your answers to the nearest cent. Do not round your intermediate calculations. Project M $ Project N $ Calculate IRR for each project. Round...
CAPITAL BUDGETING CRITERIA A firm with a 14% WACC is evaluating two projects for this year's capital budget. After-tax cash flows, including depreciation, are as follows: Project M $3,000 $1,000 $1,000 $1,000 $1,000 $1,000 Project N $9,000 $2,800 $2,800 $2,800 $2,800 $2,800 a. Calculate NPV for each project. Round your answers to the nearest cent. Do not round your intermediate calculations. Project M $ Project N $ Calculate IRR for each project. Round your answers to two decimal places. Do...