Provide round off information if any available in comment or any query for this question.
Solution
Reconciliation of Units | ||
A | Beginning WIP | 44,000 |
B | Introduced | 150,000 |
C=A+B | TOTAL | 194,000 |
D | Transferred out | 118,000 |
E=C-D | Ending WIP | 76,000 |
.
Material | Conversion | |
Equivalent Units of Production | 194,000 | 133,200 |
.
Material | Conversion | |
Cost per equivalent Unit | $ 1.49 | $ 3.23 |
.
Cost Reconciliation | |
Costs to be accounted for: | |
Beginning Wip cost | $ 174,000 |
Cost incurred during period | $ 546,000 |
Total cost to be accounted for | $ 720,000 |
Costs accounted for as follows: | |
Cost of Units Transferred Out | $ 557,323 |
Cost of Ending Wip | $ 162,677 |
Total cost accounted for | $ 720,000 |
Working
Statement of Equivalent Units(Weighted average) | |||||||
Material | Conversion cost | ||||||
Units | Complete % | Equivalent units | Complete % | Equivalent units | |||
Transferred out | 118,000 | 100% | 118,000 | 100% | 118,000 | ||
Ending WIP | 76,000 | 100% | 76,000 | 20% | 15,200 | ||
Total | 194,000 | Total | 194,000 | Total | 133,200 |
.
Cost per Equivalent Units (Weighted average) | ||||
COST | Material | Conversion cost | TOTAL | |
Beginning WIP Inventory Cost | $ 72,000 | $ 102,000 | $ 174,000 | |
Cost incurred during period | $ 218,000 | $ 328,000 | $ 546,000 | |
Total Cost to be accounted for | $ 290,000 | $ 430,000 | $ 720,000 | |
Total Equivalent Units | 194,000 | 133,200 | ||
Cost per Equivalent Units | $ 1.49 | $ 3.23 | $ 4.72 |
.
Statement of cost (Weighted average) | |||||
Cost | Equivalent Cost/unit | Ending WIP | Transferred | ||
Units | Cost Allocated | Units | Cost Allocated | ||
Material | $ 1.49 | 76,000 | $ 113,608.25 | 118,000 | $ 176,391.75 |
Conversion cost | $ 3.23 | 15,200 | $ 49,069.07 | 118,000 | $ 380,930.93 |
TOTAL | $ 720,000 | TOTAL | $ 162,677 | TOTAL | $ 557,323 |
.
Reconciliation and Cost report (weighted average) | ||||
Cost to be accounted for | ||||
Beginning Work In Progress: | ||||
Material | $ 72,000 | |||
Conversion cost | $ 102,000 | $ 174,000 | ||
Cost incurred during period: | ||||
Material | $ 218,000 | |||
Conversion cost | $ 328,000 | $ 546,000 | ||
Total Cost to be accounted for | $ 720,000 | |||
Cost accounted for | ||||
Cost of Units transferred | Equivalent Units | Cost per Equivalent Units | Cost accounted for | |
Material | 118,000 | $ 1.49 | $ 176,392 | |
Conversion cost | 118,000 | $ 3.23 | $ 380,931 | |
$ 557,323 | ||||
Cost of ending WIP | Equivalent Units | Cost per Equivalent Units | Cost accounted for | |
Material | 76,000 | $ 1.49 | $ 113,608 | |
Conversion cost | 15,200 | $ 3.23 | $ 49,069 | |
$ 162,677 | ||||
Total Cost accounted for | $ 720,000 |
Silver Company manufactures kites and has the following information available for the month of April: Work...
Silver Company manufactures kites and has the following information available for the month of April: Work in process, April 1 (100% complete for materials, 40% for conversion) 44,000 units Direct materials $ 72,000 Conversion cost $ 102,000 Number of units started 150,000 units April costs Direct materials $ 218,000 Conversion cost $ 328,000 Work in process, April 30 (100% complete for materials, 20% for conversion) 76,000 units Required: Using the weighted-average method, complete each of the following steps: 2. Calculate...
Silver Company manufactures kites and has the following information available for the month of April: Work in process, April 1 (100% complete for materials, 43% for conversion) 35,000 units Direct materials $ 47,000 Conversion cost $ 52,000 Number of units started 87,000 units April costs Direct materials $ 107,000 Conversion cost $ 166,000 Work in process, April 30 (100% complete for materials, 26% for conversion) 34,000 units Required: Using the weighted-average method, complete each of the following steps: 1. Reconcile...
Silver Company manufactures kites and has the following information available for the month of April: Work in process, April 1 (100% complete for materials, 43% for conversion) 35,000 units Direct materials $ 47,000 Conversion cost $ 52,000 Number of units started 87,000 units April costs Direct materials $ 107,000 Conversion cost $ 166,000 Work in process, April 30 (100% complete for materials, 26% for conversion) 34,000 units Required: Using the weighted-average method, complete each of the following steps: 1. Reconcile...
Silver Company manufactures kites and has the following information available for the month of April: 52,000 units $ 80,000 $ 110,000 Work in process, April 1 (188% complete for materials, 40% for conversion) Direct materials Conversion cost Number of units started April costs Direct materials Conversion cost 158,000 units $ 226,000 $ 336,000 Work in process, April 30 (100% complete for materials, 20% for conversion) 80,000 units Required: Using the weighted-average method, complete each of the following steps: 1. Reconcile...
[The following information applies to the questions displayed below.] Silver Company manufactures kites and has the following information available for the month of April: Work in process, April 1 (100% complete for materials, 40% for conversion) 58,000 units Direct materials $ 86,000 Conversion cost $ 116,000 Number of units started 164,000 units April costs Direct materials $ 232,000 Conversion cost $ 342,000 Work in process, April 30 (100% complete for materials, 20% for conversion) 83,000 units Required: Using the weighted-average...
Legacy Company manufactures umbrellas and has the following information available for the month of May Work in process, May 1 (100% complete for materials, 86% for conversion) Direct materials Conversion cost 78,000 units $131,000 $176,000 Number of units started 183,000 units May costs Direct materials Conversion cost $200,000 $377,000 Work in process, May 31 (100% complete for materials, 22% for conversion) 57,000 units Required: Using the weighted-average method of process costing, complete each the following steps: 1. Reconcile the number...
Mirada Company manufactures handheld calculators and has the following information available for the month of July: Work in process, May 1 (100% complete for July, 25% for conversion) Direct materials Conversion cost $ $ 126,000 units 240,000 394,000 Number of units started 220,000 units July costs Direct materials Conversion cost $ $ 426,000 484,000 Work in process, July 31 (100% complete for materials, 10% for conversion) 144,000 units Required: Using the weighted average method of process costing, complete each of...
Mirada Company manufactures handheld calculators and has the following information available for the month of July: Work in process, July 1 (100% complete for materials, 25% for conversion) Direct materials Conversion cost 134,000 units $ 248,000 $ 402,000 Number of units started 228,000 units July costs Direct materials Conversion cost $ 434,000 $ 492,000 Work in process, July 31 (100% complete for materials, 10% for conversion) 152,000 units Required: Using the FIFO method of process costing, complete each of the...
Mirada Company manufactures handheld calculators and has the following information available for the month of July: Work in process, May 1 (100% complete for July, 25% for conversion) Direct materials Conversion cost $ $ 126,000 units 240,000 394,000 Number of units started 220,000 units July costs Direct materials Conversion cost $ $ 426,000 484,000 Work in process, July 31 (100% complete for materials, 10% for conversion) 144,000 units Required: Using the weighted average method of process costing, complete each of...
e-Built Problems Required information (The following information applies to the questions displayed below) Mirada Company manufactures handheld calculators and has the following information available for the month of July. Work in process, July 1 (100% complete for materials, 25% for conversion) Direct materials Conversion cost 124,000 units $ 238,000 $ 392,000 Number of units started 218,000 units July costs Direct materials Conversion cost $ 424,000 $ 482,000 Work in process, July 31 (100% complete for materials, 10% for conversion) 142,000...