Question

The formula for computing the predetermined overhead rate is: Predetermined overhead rate = Estimated total manufacturing ove
Thach Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on machine-hours
0 0
Add a comment Improve this question Transcribed image text
Answer #1
1
TRUE
Predetermined overhead rate = Estimated total manufacturing overhead cost/ Estimated total amount of the allocation base
Allocation base may include activity measure such as direct labor hours or machine hours.
2
Predetermined overhead rate 12.50 =3+(665000/70000)
Direct materials 630
Direct labor cost 2880
Overhead applied 1125 =90*12.50
Total manufacturing cost 4635
Divide by Units 30
Unit product cost for Job T321 154.50
Option C $154.50 is correct
Add a comment
Know the answer?
Add Answer to:
The formula for computing the predetermined overhead rate is: Predetermined overhead rate = Estimated total manufacturing...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT