Question

The management of Xiao Manufacturing Company is trying to decide whether to continue manufacturing a part or to buy it from a

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Cost of the product if manufactured

Units     6,000.00
Variable costs Per Unit
Direct materials 4.75 28,500.00
Direct labour 4.6 27,600.00
Indirect labor 0.45     2,700.00
Utilities 0.35     2,100.00
Varible cost 60,900.00
Direct Fixed Costs     2,500.00
Allocated Fixed Costs     1,700.00
Total Fixed costs     4,200.00
Total cost of manufacturing' 65,100.00
If BIZBE is procured from suppliers
Quotation price 66000
Allocated costs
(relevant costs)
1700
Transportation costs 0.3     1,800.00
receiving costs 750
Total procurement cost 70250
Net increase in Cost     5,150.00

Based on above calculations management should go for own manufacturing.

Currently the company has the benefit of 5,150 from manufacturing rather than procuring, if company has alternative option of manucturing rather than BIZBE which is more than 5,150 than the alternative production is feasible

Other product Net income - 6000

BIZBE net income - 5150

Net surplus - 850

It is advuised to go for other product

4. Non financial factors also management should consider as they are very important while going for the other options

a. Quality

b. Supplier relation

c. process control

d. Trade Secret

Add a comment
Know the answer?
Add Answer to:
The management of Xiao Manufacturing Company is trying to decide whether to continue manufacturing a part...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • The management of Xiao Manufacturing Company is trying to decide whether to continue manufacturing a part...

    The management of Xiao Manufacturing Company is trying to decide whether to continue manufacturing a part or to buy it from an outside supplier. The part, called BIZBE, is a component of the company's finished product The following information was collected from the accounting records and production data for the year ending December 31, 2012. 1. 6,000 units of BIZBE were produced in the Machining Department 2. Variable manufacturing costs applicable to the production of each BIZBE unit were: direct...

  • The management of Shatner Manufacturing Company is trying to decide whetehr to continue manufacturing a part...

    The management of Shatner Manufacturing Company is trying to decide whetehr to continue manufacturing a part or to buy it from an outside supplier. The part, called CISCO. is a component of the company's finished product. The following information was collected from the accounting records and production data for the year ending December 31, 2020. 1. 8000 units of CISCO were produced in the Machining Department 2. Variable manufacturing costs applicable to the production of each CISCO unit were: direct...

  • The management of Concord Manufacturing Company is trying to decide whether to continue manufacturing a part...

    The management of Concord Manufacturing Company is trying to decide whether to continue manufacturing a part or to buy it from an outside supplier. The part, called CISCO, is a component of the company’s finished product. The following information was collected from the accounting records and production data for the year ending December 31, 2017. 1. 8,000 units of CISCO were produced in the Machining Department. 2. Variable manufacturing costs applicable to the production of each CISCO unit were:     direct...

  • The management of Concord Manufacturing Company is trying to decide whether to continue manufacturing a part...

    The management of Concord Manufacturing Company is trying to decide whether to continue manufacturing a part or to buy it from an outside supplier. The part, called CISCO, is a component of the company’s finished product. The following information was collected from the accounting records and production data for the year ending December 31, 2017. 1. 8,000 units of CISCO were produced in the Machining Department. 2. Variable manufacturing costs applicable to the production of each CISCO unit were:     direct...

  • The management of Shatner Manufacturing Company is trying to decide whether to continue manufacturing a part or to...

    The management of Shatner Manufacturing Company is trying to decide whether to continue manufacturing a part or to buy it from an outside supplier. The part, called CISCO, is a component of the company's finished product. The following information was collected from the accounting records and production data for the year ending December 31, 2020. 1.7.900 units of CISCO were produced in the Machining Department. 2. Variable manufacturing costs applicable to the production of each CISCO unit were: direct materials...

  • The management of Shatner Manufacturing Company is trying to decide whether to continue manufacturing a part...

    The management of Shatner Manufacturing Company is trying to decide whether to continue manufacturing a part or to buy it from an outside supplier. The part, called CISCO, is a co The following information was collected from the accounting records and production data for the year ending December 31, 2020. 1.7,900 units of CISCO were produced in the Machining Department. 2. Variable manufacturing costs applicable to the production of each CISCO unit were: direct materials $5.11, direct labor $4.54, indirect...

  • P21-2B The management of Gill Corporation is trying to decide whether to continue manufacturing a part...

    P21-2B The management of Gill Corporation is trying to decide whether to continue manufacturing a part or to buy it from an outside supplier. The part, called FIZBE. is a component of the company's finished product. This information was collected for the year ending December 31, 2017 1. 5,000 units of FIZBE were produced in the Machining Department. 2. Variable manufacturing costs applicable to the production of each FIZBE un direct materials $4.75, direct labor $4.60, indirect labor $0.45, utilities...

  • The management of Shatner Manufacturing Company is trying to decide whether to continue manufactu...

    The management of Shatner Manufacturing Company is trying to decide whether to continue manufacturing a part or to buy it from an outside supplier. The part, called CISCO, is a component of the company’s finished product. The following information was collected from the accounting records and production data for the year ending December 31, 2020. 1. 8,100 units of CISCO were produced in the Machining Department. 2. Variable manufacturing costs applicable to the production of each CISCO unit were:     direct...

  • The management of Shatner Manufacturing Company is trying to decide whether to continue manufacturing a part...

    The management of Shatner Manufacturing Company is trying to decide whether to continue manufacturing a part or to buy it from an outside supplier. The part, called CIsco, is a component of the company's finished product. The following information was collected from the accounting records and production data for the year ending December 31, 2017 1. 8,100 units of CISCO were produced in the Machining Department. 2. Variable manufacturing costs applicable to the production of each CISCO unit were: direct...

  • Current Artempein Progress The management of Ivanhoe Manufacturing Company is trying to decide whether to continue...

    Current Artempein Progress The management of Ivanhoe Manufacturing Company is trying to decide whether to continue manufacturing a part or to buy it from an outside supplier. The part, called CISCO is a component of the company's finished product. The following information was collected from the accounting records and production data for the year ending December 31, 2020 1.8,000 units of CISCO were produced in the Machining Department. 2. Variable manufacturing costs applicable to the production of each CISCO unit...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT