You have the following information on a project's cash flows. Year Cash flows 0 -$111,000 1 24,000 2 31,000 3 36,000 4 50,000 5 55,000 The project's payback is ____ years. Round it to two decimal places.
Year | Cash flows | Cumulative Cash flows |
0 | (111,000) | (111,000) |
1 | 24,000 | (87000) |
2 | 31,000 | (56,000) |
3 | 36,000 | (20,000) |
4 | 50,000 | 30,000 |
5 | 55,000 | 85,000 |
Payback period=Last period with a negative cumulative cash flow+(Absolute value of cumulative cash flows at that period/Cash flow after that period).
=3+(20,000/50,000)
=3.4 years.
You have the following information on a project's cash flows. Year Cash flows 0 -$111,000 1...
Question 2 (2 points) You have the following information on a project's cash flows. Year Cash flows. -$116,000 0 24,000 2 31,000 38,000 4 72,000 5 55,000 The project's payback is _years. Round it to two decimal places. Your Answer:
You have the following information on a project's cash flows. Year Cash flows 0 -$108,000 1 33,000 2 33,000 3 38,000 4 92,000 5 55,000 The project's payback is ____ years. Round it to two decimal places. Your Answer:
Question 4 options: You have the following information on a project's cash flows. The cost of capital is 12.5%. Year Cash flows 0 -$123,000 1 28,000 2 31,000 3 36,000 4 41,000 5 49,000 The NPV of the project is $______ (round it two decimal places); the IRR is percent (round it to two decimal places); the payback is years (round it to two decimal places).
You have the following information on a project's cash flows. Year Cash flows -$108,000 33,000 33,000 36,000 84,000 55,000 The project's payback is l years. Round it to two decimal places. Your Answer: Answer
You have the following information on a project's cash flows. The cost of capital is 11.0% Year Cash flows 0 -$106,000 1 23,000 2 23,000 3 24,000 4 32,000 5 45,000 The NPV of the project is $____. Round to two decimal places. Your Answer:
You have the following information on a project's cash flows. The project's required rate is 12%. Year Cash flows 0 -$ 80 ,000 1 23,000 2 28,000 3 38 ,000 4 92 ,000 The project's profitablity index is ____ . Round it to two decimal places.
You have the following information on a project's cash flows. The cost of capital is 7.7% Year Cash flows 0 -$ 110 ,000 1 23,000 2 28,000 3 34,000 4 32,000 5 64,000 The NPV of the project is $____. Round to two decimal places.
Nano Specialist is considering an upgrade project. The estimated cash flows from the upgrade project appear below. What is the project's payback period? Note that year 0 and year 1 cash flows are negative. (Answer in years, round to 2 places) Year 0 cash flow = -79,000 Year 1 cash flow = -36,000 Year 2 cash flow = 24,000 Year 3 cash flow = 31,000 Year 4 cash flow = 27,000 Year 5 cash flow = 27,000 Year 6 cash...
1. Sanders Inc., is considering a project with the following cash flows. Year Cash Flows 0 -$50,000 1 $10,659 2 $15,437 3 $45,103 4 $75,074 5 $250,682 What is the regular payback period for this project? [Enter the final answer in as a decimal (e.g. 5.55) - not a percent] 2. Sanders Inc., is considering a project with the following cash flows. Year Cash Flows 0 -$50,000 1 $10,988 2 $15,644 3 $20,216 4 $40,031 5 $133,490 What is the...
(Discounted payback period) Gio's Restaurants is considering a project with the following expected cash flows: Year Project Cash Flow (millions) 0 $(180) 1 100 2 65 3 100 4 110 If the project's appropriate discount rate is 13 percent, what is the project's discounted payback period? The project's discounted payback period is _____ years. (Round to two decimal places.)