You have the following information on a project's cash flows. The cost of capital is 11.0% Year Cash flows 0 -$106,000 1 23,000 2 23,000 3 24,000 4 32,000 5 45,000 The NPV of the project is $____. Round to two decimal places. Your Answer:
Present value of inflows=cash inflow*Present value of discounting factor(rate%,time period)
=23,000/1.11+23,000/1.11^2+24,000/1.11^3+32,000 /1.11^4+45,000/1.11^5
=104721.33
NPV=Present value of inflows-Present value of outflows
=104721.33-106,000
=($1278.67)(Approx)(Negative).
You have the following information on a project's cash flows. The cost of capital is 11.0%...
You have the following information on a project's cash flows. The cost of capital is 7.7% Year Cash flows 0 -$ 110 ,000 1 23,000 2 28,000 3 34,000 4 32,000 5 64,000 The NPV of the project is $____. Round to two decimal places.
Question 4 options: You have the following information on a project's cash flows. The cost of capital is 12.5%. Year Cash flows 0 -$123,000 1 28,000 2 31,000 3 36,000 4 41,000 5 49,000 The NPV of the project is $______ (round it two decimal places); the IRR is percent (round it to two decimal places); the payback is years (round it to two decimal places).
You have the following information on a project's cash flows. Year Cash flows 0 -$111,000 1 24,000 2 31,000 3 36,000 4 50,000 5 55,000 The project's payback is ____ years. Round it to two decimal places.
You have the following information on a project's cash flows. The project's required rate is 12%. Year Cash flows 0 -$ 80 ,000 1 23,000 2 28,000 3 38 ,000 4 92 ,000 The project's profitablity index is ____ . Round it to two decimal places.
Question 2 (2 points) You have the following information on a project's cash flows. Year Cash flows. -$116,000 0 24,000 2 31,000 38,000 4 72,000 5 55,000 The project's payback is _years. Round it to two decimal places. Your Answer:
You have the following information on a project's cash flows. Year Cash flows 0 -$108,000 1 33,000 2 33,000 3 38,000 4 92,000 5 55,000 The project's payback is ____ years. Round it to two decimal places. Your Answer:
You have the following information on a project's cash flows. Year Cash flows -$108,000 33,000 33,000 36,000 84,000 55,000 The project's payback is l years. Round it to two decimal places. Your Answer: Answer
A project's NPV profile graph intersects the Y-axis at 0% cost of capital and intersects the X-axis at the project's Select (where NPV = 0). The Y-axis intersection point represents the project's undiscounted NPV. The point at which 2 projects' profiles cross one another is the crossover rate. The crossover rate can be found by calculating the Select of the differences in the projects' cash flows (Project Delta). A Select NPV profile indicates that increases in the cost of capital...
1. You have the chance to participate in a project that produces the following cash flows: Cash Flows ($) C0 C1 C2 4,600 4,400 –10,800 a. The internal rate of return is 12.69%. If the opportunity cost of capital is 12%, what is the NPV of the project? (A negative answer should be indicated by a minus sign. Do not round intermediate calculations. Round your answer to 2 decimal places.) NPV $ __________. 2. Consider the following projects: Cash Flows...
You are considering the following two projects and can only take one. Your cost of capital is 11.4 %. The cash flows for the two projects are as follows ($ million): Project Year 0 Year 1 Year 2 Year 3 Year 4 A −$102 $27 $31 $39 $49 B −$102 $49 $39 $31 $20 a. What is the IRR of each project? b. What is the NPV of each project at your cost of capital? c. At what cost of...