Question

32. Calculating a Bid Price Guthrie Enterprises needs someone to supply it with 175,000 cartons of...

32. Calculating a Bid Price Guthrie Enterprises needs someone to supply it with 175,000 cartons of machine screws per year to support its manufacturing needs over the next five years, and you’ve decided to bid on the contract. It will cost you $1,800,000 to install the equipment necessary to start production; you’ll depreciate this cost straight-line to zero over the project’s life. You estimate that in five years, this equipment can be salvaged for $160,000. Your fixed production costs will be $265,000 per year, and your variable production costs should be $13.25 per carton. You also need an initial investment in net working capital of $175,000. If your tax rate is 35 percent and you require a return of 13 percent on your investment, what bid price should you submit?

0 0
Add a comment Improve this question Transcribed image text
Answer #1


Solution: units 175000 Project life 5 Years 1800000 360000 160000 Equipment cost Depreciation 1800000/5 Sale value FC 265000

Add a comment
Know the answer?
Add Answer to:
32. Calculating a Bid Price Guthrie Enterprises needs someone to supply it with 175,000 cartons of...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Problem 8-32 Calculating a Bid Price Guthrie Enterprises needs someone to supply it with 158,000 cartons...

    Problem 8-32 Calculating a Bid Price Guthrie Enterprises needs someone to supply it with 158,000 cartons of machine screws per year to support its manufacturing needs over the next five years, and you've decided to bid on the contract. It will cost you $1,980,000 to install the equipment necessary to start production, you'll depreciate this cost straight-line to zero over the project's life. You estimate that in five years, this equipment can be salvaged for $168,000. Your fixed production costs...

  • Guthrie Enterprises

    Guthrie Enterprises needs someone to supply it with 205,000 cartons of machine screws per year to support its manufacturing needs over the next five years, and you’ve decided to bid on the contract. It will cost $2,600,000 to install the equipment necessary to start production; you’ll depreciate this cost straight-line to zero over the project’s life. You estimate that in five years this equipment can be salvaged for $215,000. Your fixed production costs will be $700,000 per year, and your variable...

  • Martin Enterprises needs someone to supply it with 119,000 cartons of machine screws per year to...

    Martin Enterprises needs someone to supply it with 119,000 cartons of machine screws per year to support its manufacturing needs over the next five years, and you’ve decided to bid on the contract. It will cost you $790,000 to install the equipment necessary to start production; you’ll depreciate this cost straight-line to zero over the project’s life. You estimate that, in five years, this equipment can be salvaged for $138,000. Your fixed production costs will be $425,000 per year, and...

  • Guthrie Enterprises needs someone to supply it with 145,000 cartons of machine screws per year to...

    Guthrie Enterprises needs someone to supply it with 145,000 cartons of machine screws per year to support its manufacturing needs over the next five years, and you've decided to bid on the contract. It will cost $2,000,000 to install the equipment necessary to start production; you'll depreciate this cost straight-line to zero over the project's life. You estimate that in five years this equipment can be salvaged for $155,000. Your fixed production costs will be $640,000 per year, and your...

  • Romo Enterprises needs someone to supply it with 113,000 cartons of machine screws per year to...

    Romo Enterprises needs someone to supply it with 113,000 cartons of machine screws per year to support its manufacturing needs over the next five years, and you’ve decided to bid on the contract. It will cost you $800,000 to install the equipment necessary to start production; you’ll depreciate this cost straight-line to zero over the project’s life. You estimate that, in five years, this equipment can be salvaged for $63,000. Your fixed production costs will be $318,000 per year, and...

  • Guthrie Enterprises needs someone to supply it with 142,000 cartons of machine screws per year to...

    Guthrie Enterprises needs someone to supply it with 142,000 cartons of machine screws per year to support its manufacturing needs over the next five years. It will cost $1,820,000 to install the equipment necessary to start production; you’ll depreciate this cost straight-line to zero over the project’s life. You estimate that in five years this equipment can be salvaged for $152,000. Your fixed production costs will be $267,000 per year, and your variable production costs should be $9.60 per carton....

  • The technique for calculating a bid price can be extended to many other types of problems....

    The technique for calculating a bid price can be extended to many other types of problems. Answer the following questions using the same technique as setting a bid price; that is, set the project NPV to zero and solve for the variable in question. Guthrie Enterprises needs someone to supply it with 145,000 cartons of machine screws per year to support its manufacturing needs over the next five years, and you’ve decided to bid on the contract. It will cost...

  • The technique for calculating a bid price can be extended to many other types of problems....

    The technique for calculating a bid price can be extended to many other types of problems. Answer the following questions using the same technique as setting a bid price; that is, set the project NPV to zero and solve for the variable in question. Guthrie Enterprises needs someone to supply it with 154,000 cartons of machine screws per year to support its manufacturing needs over the next five years, and you’ve decided to bid on the contract. It will cost...

  • The technique for calculating a bid price can be extended to many other types of problems....

    The technique for calculating a bid price can be extended to many other types of problems. Answer the following questions using the same technique as setting a bid price; that is, set the project NPV to zero and solve for the variable in question. Guthrie Enterprises needs someone to supply it with 150,000 cartons of machine screws per year to support its manufacturing needs over the next five years, and you’ve decided to bid on the contract. It will cost...

  • Martin Enterprises needs someone to supply it with 131,000 cartons of machine screws per year to...

    Martin Enterprises needs someone to supply it with 131,000 cartons of machine screws per year to support its manufacturing needs over the next five years, and you've decided to bid on the contractIt will cost you $940,000 to install the equipment necessary to start production, you'll depreciate this cost straight line to zero over the project's lifeYou estimate that, in five years, this equipment can be salvaged for $103,000. Your fixed production costs will be $515,000 per year, and your...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT