Wolk Corporation is a highly automated manufacturing firm. The vice president of finance has decided that traditional standar
0 0
Add a comment Improve this question Transcribed image text
Answer #1

The correct answer is option B

Process Cycle Efficiency = Value-Added Time / Cycle Time

Value added time = Process (manufacturing time) = 16 days

Cycle time = Lead time + Inspection time + Process time + Move time

= (36 + 18) + 8 + 16 + 5

= 83 days

Thus, Process Cycle Efficiency = 16 / 83

= 19.277 i.e. 19.3%

Add a comment
Know the answer?
Add Answer to:
Wolk Corporation is a highly automated manufacturing firm. The vice president of finance has decided that...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Wolk Corporation is a highly automated manufacturing firm. The vice president of finance has decided that...

    Wolk Corporation is a highly automated manufacturing firm. The vice president of finance has decided that traditional standards are inappropriate for performance measures in an automated environment. Labor for this company is insignificant in terms of the total cost of production and tends to be fixed, material quality is considered more important than minimizing material cost, and customer satisfaction is the number one priority. As a result, delivery performance measures have been chosen to evaluate performance. The following information is...

  • DataSpan, Inc., automated its plant at the start of the current year and installed a flexible manufacturing system. The...

    DataSpan, Inc., automated its plant at the start of the current year and installed a flexible manufacturing system. The company is also evaluating its suppliers and moving toward Lean Production. Many adjustment problems have been encountered, including problems relating to performance measurement. After much study, the company has decided to use the performance measures below, and it has gathered data relating to these measures for the first four months of operations. Month 1 2 3 4 Throughput time (days) ?...

  • DataSpan, Inc, automated its plant at the start of the current year and installed a flexible manufacturing system....

    DataSpan, Inc, automated its plant at the start of the current year and installed a flexible manufacturing system. The company is also evaluating its suppliers and moving toward Lean Production. Many adjustment problems have been encountered, including problems relating to performance measurement. After much study, the company has decided to use the performance measures below, and it has gathered data relating to these measures for the first four months of operations. Month 2 3 4 Throughput time (days) Delivery cycle...

  • Case Studies Jackson Manufacturing Company Kathleen McFadden, vice president of operations at Jackson Manufacturing Company, has...

    Case Studies Jackson Manufacturing Company Kathleen McFadden, vice president of operations at Jackson Manufacturing Company, has just received a request for quote (RFQ) from DeKalb Electric Supply for 400 units per week of a motor armature. The components are standard and either easy to work into the existing production schedule or readily available from established suppliers on a JIT basis. But there is some difference in assembly. Ms. McFadden has identified eight tasks that Jackson must perform to assemble the...

  • MANAGERIAL ACCOUNTING CASE STUDY.CASE ASSIGNMENT #1: Cortland Manufacturing, Inc.

    MANAGERIAL ACCOUNTING CASE STUDY.CASE ASSIGNMENT #1: Cortland Manufacturing, Inc.We constantly seem to be pricing ourselves out of some markets and not charging enough in others. Our pricing policy is pretty simple: we mark up our full manufacturing cost by 50%. That means a computer that costs us $2,000 to manufacture will sell for $3,000. Until now I thought this was a workable approach, but now I’m not so sure.Steve Works, CEO, Cortland Manufacturing, Inc. (CMI)Steve’s Controller, Sally Nomer, had just...

  • Your Assignment ·     You are an outside consulting organization who has been retained by the CEO to...

    Your Assignment ·     You are an outside consulting organization who has been retained by the CEO to fix the problems and make sure the mandate is driven throughout the organization. identify what strategic initiatives and changes you will recommend and the tactics to implement those strategies and changes based on this case study New Product Development Process Improvement Case Study Background:          Horizon Giftables, Inc. is a 35-year-old consumer products company that manufactures and distributes home accessory products and décor items through...

  • ask back to top Background You are a manager in the audit division at Miller Yates...

    ask back to top Background You are a manager in the audit division at Miller Yates Howarth (MYH), an accounting firm with offices throughout the major regional centres of NSW and Queensland. Although a medium sized firm by national standards, MYH is the second largest regional accounting firm in Australia. Most of MYH’s audit clients are in the agriculture, mining, manufacturing and property industries. All those industries are currently under pressure, either from a downturn in commodity prices or fierce...

  • Identify the cost issues facing the firm in this case. Chrystal Moulding and Repairs Works (CMRW)...

    Identify the cost issues facing the firm in this case. Chrystal Moulding and Repairs Works (CMRW) is a successful SME based in Ashhurst, a small rural town close to Palmerston North. CMRW manufactures a variety of products and provides a range of services to clients. Work involves (a) moulding of plastics and other materials, (b) custom builds using plastic, fibreglass, kevlar, carbon fibre and other new age materials and (c) the repair of anything using these materials. George Hood, one...

  • How can we assess whether a project is a success or a failure? This case presents...

    How can we assess whether a project is a success or a failure? This case presents two phases of a large business transformation project involving the implementation of an ERP system with the aim of creating an integrated company. The case illustrates some of the challenges associated with integration. It also presents the obstacles facing companies that undertake projects involving large information technology projects. Bombardier and Its Environment Joseph-Armand Bombardier was 15 years old when he built his first snowmobile...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT