Throughput Time |
Delivery Cycle Time |
Manufacturing Cycle Efficiency (MCE) |
||||
Month 1 |
(0.8+3.5+4.2+0.6) =9.1 |
days |
(9.1+22) =31.1 |
days |
(3.5/9.1) =38.5 |
% |
Month 2 |
(0.5+3.3+4.7+0.7) =9.2 |
days |
(9.2+24.1) =33.3 |
days |
(3.3/9.2) =35.9 |
% |
Month 3 |
(0.6+3.2+5.3+0.7) =9.8 |
days |
(9.8+27) =36.8 |
days |
(3.2/9.8) =32.6 |
% |
Month 4 |
(0.6+3+6+0.6) =10.2 |
days |
(10.2+29.2) =39.4 |
days |
(3/10.2) =29.4 |
% |
*Throughput Time = Move Time + Process Time + Queue Time + Inspection Time
*Delivery Cycle Time = Throughput Time + Wait Time
*Manufacturing Cycle Efficiency = Process Time/Throughput Time
DataSpan, Inc, automated its plant at the start of the current year and installed a flexible manufacturing system....
DataSpan, Inc., automated its plant at the start of the current year and installed a flexible manufacturing system. The company is also evaluating its suppliers and moving toward Lean Production. Many adjustment problems have been encountered, including problems relating to performance measurement. After much study, the company has decided to use the performance measures below, and it has gathered data relating to these measures for the first four months of operations. Month Throughput time (days) Delivery cycle time (days) Manufacturing...
DataSpan, Inc., automated its plant at the start of the current year and installed a flexible manufacturing system. The company is also evaluating its suppliers and moving toward Lean Production. Many adjustment problems have been encountered, including problems relating to performance measurement. After much study, the company has decided to use the performance measures below, and it has gathered data relating to these measures for the first four months of operations. Month 1 2 3 4 Throughput time (days) ?...
DataSpan, Inc., automated its plant at the start of the current year and installed a flexible manufacturing system. The company is also evaluating its suppliers and moving toward Lean Production. Many adjustment problems have been encountered, including problems relating to performance measurement. After much study, the company has decided to use the performance measures below, and it has gathered data relating to these measures for the first four months of operations, Month 34 Throughput time (days) Delivery cycle time (days)...
DataSpan, Inc., automated its plant at the start of the current year and installed a flexible manufacturing system. The company is also evaluating its suppliers and moving toward Lean Production. Many adjustment problems have been encountered, including problems relating to performance measurement. After much study, the company has decided to use the performance measures below, and it has gathered data relating to these measures for the first four months of operations. Month 2 1 Throughput time (days) Delivery cycle time...
DataSpan, Inc., automated its plant at the start of the current year and installed a flexible manufacturing system. The company is also evaluating its suppliers and moving toward Lean Production. Many adjustment problems have been encountered, including problems relating to performance measurement. After much study, the company has decided to use the performance measures below, and it has gathered data relating to these measures for the first four months of operations. Month 1 2 3 ? Throughput time (days) Delivery...
DataSpan, Inc., automated its plant at the start of the current year and installed a flexible manufacturing system. The company is also evaluating its suppliers and moving toward Lean Production. Many adjustment problems have been encountered, including problems relating to performance measurement. After much study, the company has decided to use the performance measures below, and it has gathered data relating to these measures for the first four months of operations. Month ? Throughput time (days) Delivery cycle time (days)...
DataSpan, Inc., automated its plant at the start of the current year and installed a flexible manufacturing system. The company is also evaluating its suppliers and moving toward Lean Production. Many adjustment problems have been encountered, including problems relating to performance measurement. After much study, the company has decided to use the performance measures below, and it has gathered data relating to these measures for the first four months of operations. Month 1 2 3 4 Throughput time (days) ?...
DataSpan, Inc., automated its plant at the start of the current year and installed a flexible manufacturing system. The company is also evaluating its suppliers and moving toward Lean Production. Many adjustment problems have been encountered, including problems relating to performance measurement. After much study, the company has decided to use the performance measures below, and it has gathered data relating to these measures for the first four months of operations. Month 1. 4. ? 3 ? > Throughput time...
DataSpan, Inc., automated its plant at the start of the current year and installed a flexible manufacturing system. The company is also evaluating its suppliers and moving toward Lean Production. Many adjustment problems have been encountered, including problems relating to performance measurement. After much study, the company has decided to use the performance measures below, and it has gathered data relating to these measures for the first four months of operations. Problem 10-14 Measures of Internal Business Process Performance (LO10-3]...
DataSpan, Inc. automated its plant at the start of the current year and installed a flexible manufacturing system. The company is also evaluating its suppliers and moving toward Lean Production. Many adjustment problems have been encountered, including problems relating to performance measurement. After much study, the company has decided to use the performance measures below, and it has gathered data relating to these measures for the first four months of operations. Throughout te (days) Delivery cycle time (days) Manufacturing cycle...