Question

DataSpan, Inc. automated its plant at the start of the current year and installed a flexible manufacturing system. The compan
Required 1 Required 2 Required 3 Evaluate the companys performance over the last four months, (Indicate the effect of each t
Required 1 Required 2 Redased 3 3-a. (Month 5) Refer to the move time, process time, and so forth, given for month 4. Assume
0 0
Add a comment Improve this question Transcribed image text
Answer #1
Move time per unit (A) Process Time per unit(B) Wait time per order(C) Queue Time per unit(D) Inspection time per unit(E) Throughput time(F=A+B+D+E) Delivery Cycle Time(G=A+B+C+D+E) Manufacturing cycle efficiency(H=100*B/F)
Month 1 0.7 3.3 24.0 5.0 0.4 9.4 33.4 35.11%
Month 2 0.4 3.1 26.3 5.9 0.6 10.0 36.3 31%
Month 3 0.5 2.9 31.0 6.9 0.6 10.9 41.9 26.61%
Month 4 0.5 2.7 33.4 8.1 0.4 11.7 45.1 23.08%

The company has been improving its manufacturing process but the manufacturing efficiency is declining over the months. The processing time is declining while throughput time is increasing. This can be attributed to better technology or improvement of manufacturing base but at the same time, Queueing time increasing. This is leading to declining efficiency.

Add a comment
Know the answer?
Add Answer to:
DataSpan, Inc. automated its plant at the start of the current year and installed a flexible...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • DataSpan, Inc., automated its plant at the start of the current year and installed a flexible...

    DataSpan, Inc., automated its plant at the start of the current year and installed a flexible manufacturing system. The company is also evaluating its suppliers and moving toward Lean Production. Many adjustment problems have been encountered, including problems relating to performance measurement. After much study, the company has decided to use the performance measures below, and it has gathered data relating to these measures for the first four months of operations. Month Throughput time (days) Delivery cycle time (days) Manufacturing...

  • DataSpan, Inc., automated its plant at the start of the current year and installed a flexible...

    DataSpan, Inc., automated its plant at the start of the current year and installed a flexible manufacturing system. The company is also evaluating its suppliers and moving toward Lean Production. Many adjustment problems have been encountered, including problems relating to performance measurement. After much study, the company has decided to use the performance measures below, and it has gathered data relating to these measures for the first four months of operations. Month 2 1 Throughput time (days) Delivery cycle time...

  • DataSpan, Inc., automated its plant at the start of the current year and installed a flexible...

    DataSpan, Inc., automated its plant at the start of the current year and installed a flexible manufacturing system. The company is also evaluating its suppliers and moving toward Lean Production. Many adjustment problems have been encountered, including problems relating to performance measurement. After much study, the company has decided to use the performance measures below, and it has gathered data relating to these measures for the first four months of operations. Month 1 2 3 ? Throughput time (days) Delivery...

  • DataSpan, Inc., automated its plant at the start of the current year and installed a flexible...

    DataSpan, Inc., automated its plant at the start of the current year and installed a flexible manufacturing system. The company is also evaluating its suppliers and moving toward Lean Production. Many adjustment problems have been encountered, including problems relating to performance measurement. After much study, the company has decided to use the performance measures below, and it has gathered data relating to these measures for the first four months of operations, Month 34 Throughput time (days) Delivery cycle time (days)...

  • DataSpan, Inc., automated Its plant at the start of the current year and Installed a flexible...

    DataSpan, Inc., automated Its plant at the start of the current year and Installed a flexible manufacturing system. The company is also evaluating its suppliers and moving toward Lean Production. Many adjustment problems have been encountere relating to performance measurement. After much study, the company has decided to use the performance measures below, and it has gathered data relating to these measures for the first four months of operations. Month Throughput time (days) Delivery cycle time (days) Manufacturing cycle efficiency...

  • DataSpan, Inc., automated its plant at the start of the current year and installed a flexible...

    DataSpan, Inc., automated its plant at the start of the current year and installed a flexible manufacturing system. The company is also evaluating its suppliers and moving toward Lean Production. Many adjustment problems have been encountered, including problems relating to performance measurement. After much study, the company has decided to use the performance measures below, and it has gathered data relating to these measures for the first four months of operations. Month ? Throughput time (days) Delivery cycle time (days)...

  • DataSpan, Inc., automated its plant at the start of the current year and installed a flexible...

    DataSpan, Inc., automated its plant at the start of the current year and installed a flexible manufacturing system. The company is also evaluating its suppliers and moving toward Lean Production. Many adjustment problems have been encountered, including problems relating to performance measurement. After much study, the company has decided to use the performance measures below, and it has gathered data relating to these measures for the first four months of operations. Month 1 2 3 4 Throughput time (days) ?...

  • DataSpan, Inc., automated its plant at the start of the current year and installed a flexible...

    DataSpan, Inc., automated its plant at the start of the current year and installed a flexible manufacturing system. The company is also evaluating its suppliers and moving toward Lean Production. Many adjustment problems have been encountered, including problems relating to performance measurement. After much study, the company has decided to use the performance measures below, and it has gathered data relating to these measures for the first four months of operations. Problem 10-14 Measures of Internal Business Process Performance (LO10-3]...

  • DataSpan, Inc., automated its plant at the start of the current year and installed a flexible...

    DataSpan, Inc., automated its plant at the start of the current year and installed a flexible manufacturing system. The company is also evaluating its suppliers and moving toward Lean Production. Many adjustment problems have been encountered, including problems relating to performance measurement. After much study, the company has decided to use the performance measures below, and it has gathered data relating to these measures for the first four months of operations. Month 3 2 ? 4 ? ? ? Throughput...

  • DataSpan, Inc., automated its plant at the start of the current year and installed a flexible manufacturing system. The...

    DataSpan, Inc., automated its plant at the start of the current year and installed a flexible manufacturing system. The company is also evaluating its suppliers and moving toward Lean Production. Many adjustment problems have been encountered, including problems relating to performance measurement. After much study, the company has decided to use the performance measures below, and it has gathered data relating to these measures for the first four months of operations. Month 1 2 3 4 Throughput time (days) ?...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT