Data Span Inc. | |||||||
1a) | Throughput time=Process Time+Inspection time+Move Time+Queue Time | ||||||
Month 1 | Month 2 | Month 3 | Month 4 | ||||
Process Time | 2.3 | 2.2 | 2.1 | 2 | Days | ||
Inspection Time | 0.8 | 1.1 | 1.1 | 0.8 | Days | ||
Move Time | 0.6 | 0.3 | 0.4 | 0.4 | Days | ||
Queue Time | 4.7 | 5.5 | 6.4 | 7.4 | Days | ||
ThroughPut time | 8.4 | 9.1 | 10 | 10.6 | Days | ||
1b | Delivery Cycle Time=Wait Time+Throughput Time | ||||||
Month 1 | Month 2 | Month 3 | Month 4 | ||||
Wait Time=(a) | 20 | 21.9 | 26 | 28 | Days | ||
Throughput Time=(b) | 8.4 | 9.1 | 10 | 10.6 | Days | ||
Delivery Cycle Time=(a)+(b) | 28.4 | 31 | 36 | 38.6 | Days | ||
1c | Manufacturing Cycle Efficiency=Process Time/Throughput Time | ||||||
Month 1 | Month 2 | Month 3 | Month 4 | ||||
Process Time=(a) | 2.3 | 2.2 | 2.1 | 2 | Days | ||
Throughput Time=(b) | 8.4 | 9.1 | 10 | 10.6 | Days | ||
Manufacturing Cycle Efficiency=(a)/(b) | 27.38% | 24.18% | 21.00% | 18.87% | |||
2 | Throughput time increases each year because its means that time spend to convert raw material into finished goods is increases. | ||||||
Manufacturing Cycle efficiency decreases it means that time spend on non value added activities is reduces. | |||||||
As per HomeworkLib policy, only first 4 subparts need to be solved |
DataSpan, Inc., automated its plant at the start of the current year and installed a flexible...
DataSpan, Inc., automated its plant at the start of the current year and installed a flexible manufacturing system. The company is also evaluating its suppliers and moving toward Lean Production. Many adjustment problems have been encountered, including problems relating to performance measurement. After much study, the company has decided to use the performance measures below, and it has gathered data relating to these measures for the first four months of operations. Month Throughput time (days) Delivery cycle time (days) Manufacturing...
DataSpan, Inc., automated its plant at the start of the current year and installed a flexible manufacturing system. The company is also evaluating its suppliers and moving toward Lean Production. Many adjustment problems have been encountered, including problems relating to performance measurement. After much study, the company has decided to use the performance measures below, and it has gathered data relating to these measures for the first four months of operations, Month 34 Throughput time (days) Delivery cycle time (days)...
DataSpan, Inc., automated its plant at the start of the current year and installed a flexible manufacturing system. The company is also evaluating its suppliers and moving toward Lean Production. Many adjustment problems have been encountered, including problems relating to performance measurement. After much study, the company has decided to use the performance measures below, and it has gathered data relating to these measures for the first four months of operations. Month ? Throughput time (days) Delivery cycle time (days)...
DataSpan, Inc., automated its plant at the start of the current year and installed a flexible manufacturing system. The company is also evaluating its suppliers and moving toward Lean Production. Many adjustment problems have been encountered, including problems relating to performance measurement. After much study, the company has decided to use the performance measures below, and it has gathered data relating to these measures for the first four months of operations. Month 2 1 Throughput time (days) Delivery cycle time...
DataSpan, Inc., automated its plant at the start of the current year and installed a flexible manufacturing system. The company is also evaluating its suppliers and moving toward Lean Production. Many adjustment problems have been encountered, including problems relating to performance measurement. After much study, the company has decided to use the performance measures below, and it has gathered data relating to these measures for the first four months of operations. Month 1 2 3 ? Throughput time (days) Delivery...
DataSpan, Inc., automated its plant at the start of the current year and installed a flexible manufacturing system. The company is also evaluating its suppliers and moving toward Lean Production. Many adjustment problems have been encountered, including problems relating to performance measurement. After much study, the company has decided to use the performance measures below, and it has gathered data relating to these measures for the first four months of operations. Month 1 2 3 4 Throughput time (days) ?...
DataSpan, Inc., automated its plant at the start of the current
year and installed a flexible manufacturing system. The company is
also evaluating its suppliers and moving toward Lean Production.
Many adjustment problems have been encountered, including problems
relating to performance measurement. After much study, the company
has decided to use the performance measures below, and it has
gathered data relating to these measures for the first four months
of operations.
Problem 10-14 Measures of Internal Business Process Performance (LO10-3]...
DataSpan, Inc., automated Its plant at the start of the current year and Installed a flexible manufacturing system. The company is also evaluating its suppliers and moving toward Lean Production. Many adjustment problems have been encountere relating to performance measurement. After much study, the company has decided to use the performance measures below, and it has gathered data relating to these measures for the first four months of operations. Month Throughput time (days) Delivery cycle time (days) Manufacturing cycle efficiency...
DataSpan, Inc. automated its plant at the start of the current year and installed a flexible manufacturing system. The company is also evaluating its suppliers and moving toward Lean Production. Many adjustment problems have been encountered, including problems relating to performance measurement. After much study, the company has decided to use the performance measures below, and it has gathered data relating to these measures for the first four months of operations. Throughout te (days) Delivery cycle time (days) Manufacturing cycle...
DataSpan, Inc., automated its plant at the start of the current year and installed a flexible manufacturing system. The company is also evaluating its suppliers and moving toward Lean Production. Many adjustment problems have been encountered, including problems relating to performance measurement. After much study, the company has decided to use the performance measures below, and it has gathered data relating to these measures for the first four months of operations. Month 3 2 ? 4 ? ? ? Throughput...