1) | Predetermined Overhead rate | $ 3.60 | per machine hour |
2) | Total Applied manufacturing overhead | $ 18,000 | |
3) | Ending work in process inventory | $ 13,240 | |
4) | Gross profit | $ 17,920 | |
5)a | Balance | $ 800 | |
5)b | is it over - or - under applied | over applied |
ALL EXPLANATION IS GIVEN BELOW :
REQUIRED : | ||||||||
1) | Calculate the predetermined overhead rate : | |||||||
Predetermined overhead rate = Estimated total manufacturing overhead cost / Estimated total machine hours | ||||||||
Predetermined overhead rate = $ 222,840 / 61,900 machine hours | ||||||||
Predetermined overhead rate = $ 3.60 per machine hour | ||||||||
2) | Calculate the Total applied manufacturing overhead : | |||||||
Total applied manufacturing overhead = predetermined overhead rate * actual amount of allocation based used | ||||||||
Total applied manufacturing overhead = $ 3.60 * 5000 machine hours | ||||||||
Total applied manufacturing overhead = $ 18,000 | ||||||||
3) | Calculate the Ending work in process inventory : | |||||||
here, Job 103 was the only unfinished job at the end of the first month . The cost associated with the job were | ||||||||
Ending work in process inventory : | ||||||||
Direct materials | $ 5,300 | |||||||
Direct labor | $ 4,700 | |||||||
Manufacturing overhead(900 hours*3.60) | $ 3,240 | |||||||
Total work in process cost | $ 13,240 | |||||||
4) | Calculate the Gross profit : | |||||||
Here only Job 101 was completed and sold during the period . The cost of job 101 was | ||||||||
Direct materials | $ 10,400 | |||||||
Direct labor | $ 17,300 | |||||||
Manufacturing overhead(1300 hours*3.60) | $ 4,680 | |||||||
Total cost (cost of goods sold ) | $ 32,380 | |||||||
The gross profit before the adjustment for over or under applied manufacturing is | ||||||||
sales ( given ) | $ 50,300 | |||||||
less: Cost of goods sold ( above calculation ) | ($32,380) | |||||||
Gross profit | $ 17,920 |
5)(a) | Calculate the balance in the manufacturing overhead account : |
Manufacturing overhead | |||
Actual | $ 17,200 | $ 18,000 | Applied |
(Given) | ( see required 2) | ||
Balance | $ 800 | ||
(18,000-17,200) |
5)(b) | Calculate the over or under applied : | ||
Applied | $ 18,000 | ||
less: Actual | ($ 17,200) | ||
over applied | $ 800 |
Tyler Tooling Company uses a job order cost system with overhead applied to products on the...
Tyler Tooling Company uses a job order cost system with overhead applied to products on the basis of machine hours. For the upcoming year, the company estimated its total manufacturing overhead cost at $228,660 and total machine hours at 61,800. During the first month of operations, the company worked on three jobs and recorded the following actual direct materials cost, direct labor cost, and machine hours for each job: Job 101 Job 102 Job 103 Total Direct materials used $...
Tyler Tooling Company uses a job order cost system with overhead applied to products on the basis of machine hours. For the upcoming year, the company estimated its total manufacturing overhead cost at $217,700 and total machine hours at 62,200. During the first month of operations, the company worked on three jobs and recorded the following actual direct materials cost, direct labor cost, and machine hours for each job Job 101 Job 102 Job 103 $ 5,600 $ 4,700 Total...
Tyler Tooling Company uses a job order cost system with overhead applied to products on the basis of machine hours. For the upcoming year, the company estimated its total manufacturing overhead cost at $214,540 and total machine hours at 63,100. During the first month of operations, the company worked on three jobs and recorded the following actual direct materials cost, direct labor cost, and machine hours for each job: Direct materials used Direct labor Machine hours Job 101 Job 102...
Tyler Tooling Company uses a job order cost system with overhead applied to products on the basis of machine hours. For the upcoming year, the company estimated Its total manufacturing overhead cost at $204.930 and total machine hours at 62,100. During the first month of operations, the company worked on three jobs and recorded the following actual direct materials cost, direct labor cost, and machine hours for each job: Direct materials used Direct labor Machine hours Job 101 Job 102...
Tyler Tooling Company uses a job order cost system with overhead applied to products on the basis of machine hours. For the upcoming year, the company estimated its total manufacturing overhead cost at $250,400 and total machine hours at 62,600. During the first month of operations, the company worked on three jobs and recorded the following actual direct materials cost, direct labor cost, and machine hours for each job: Job 101 Job 102 Job 103 Total Direct materials used $11,800...
Tyler Tooling Company uses a job order cost system with overhead applied to products on the basis of machine hours. For the upcoming year, the company estimated its total manufacturing overhead cost at $233,100 and total machine hours at 63,000. During the first month of operations, the company worked on three jobs and recorded the following actual direct materials cost, direct labor cost, and machine hours for each job: Direct materials used Direct labor Machine hours Job 101 Job 102...
Tyler Tooling Company uses a job order cost system with overhead applied to products on the basis of machine hours. For the upcoming year, the company estimated its total manufacturing overhead cost at $205,920 and total machine hours at 62,400. During the first month of operations, the company worked on three jobs and recorded the following actual direct materials cost, direct labor cost, and machine hours for each job: Job 101 Job 102 Job 103 Total Direct materials used $...
Tyler Tooling Company uses a job order cost system with overhead applied to products on the basis of machine hours. For the upcoming year, the company estimated its total manufacturing overhead cost at $202,240 and total machine hours at 63,200. During the first month of operations, the company worked on three jobs and recorded the following actual direct materials cost, direct labor cost, and machine hours for each job: Job 101 Job 102 Job 103 Total Direct materials used $10,800...
Tyler Tooling Company uses a job order cost system with overhead applied to products on the basis of machine hours. For the upcoming year, the company estimated its total manufacturing overhead cost at $251600 and total machine hours at 62.900. During the first month of operations, the company worked on three jobs and recorded the following actual direct materials cost. direct labor cost, and machine hours for each job: Direct materials used Direct labor Machine hours Job 181 Job 102...
Tyler Tooling Company uses a job order cost system with overhead applied to products on the basis of machine hours. For the upcoming year, the company estimated its total manufacturing overhead cost at $249,600 and total machine hours at 62,400. During the first month of operations, the company worked on three jobs and recorded the following actual direct materials cost, direct labor cost, and machine hours for each jot Job 101 Job 102 S 8,400 S 5,000 Job 103 S...