Question

Zephyr Farming Pty Ltd is considering the purchase of a wind turbine generator in order to...

Zephyr Farming Pty Ltd is considering the purchase of a wind turbine generator in order to generate electricity and to reduce the electricity costs for their offices, which are located in Toowoomba. Currently the business uses 60,000 kilowatt hours (kWh) per quarter (3 months) at an average cost of $0.30 per kwh, supplied by the local coal fired power station. The current required rate of return used to evaluate projects is 6%, with a required payback period of 3 years.
The Queensland government started a scheme to provide an incentive for business to use alternative sources of renewable power. The incentives are 5% immediate reimbursement of the purchase and installation costs. This reimbursement can be paid to the supplier providing and installing the equipment. Therefore, the net cash flow from Zephyr Farming Pty Ltd is the purchase cost plus the installation cost less the 5% incentive back from government to offset these costs.
Project details:
Cost of wind turbine generator          $6,000
Cost to install turbine and generator (by supplier)        $450
Expected cash incentive back from government to offset cost of the panels paid immediately the wind turbine generator installed           5% of total costs
Turbine expected (on average) generated kilowatt              300 hours per month
Generator’s expected life (in years)                   15 years

4. Calculate the net present value (NPV) of the project with a required rate of return at 6%. As the savings are the same each year, use the present value table on the next page for an ordinary annuity. (9 marks)
5. Comment on whether Zephyr should proceed with this project using the Net Present Value method and whether you should base your decision only in this quantitative calculation. (1 mark)

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Answer 4:

Initial Investment:

Cost of wind turbine generator = $6,000
Cost to install turbine and generator (by supplier) = $450

Total cost = $6,000 + $450 = $6,450

Expected cash incentive = $6,450 * 5% = $322.50

Net Investment = $6,450 - $322.50 = $6,127.50

Annual cash flow:

Turbine expected (on average) generated kilowatt = 300 hours per month

Annual generated KWH expected = 300 * 12 = 3,600

Annual cash flow = 3,600 * $0.30 = $1,080

PV Factors for a One-Dollar Annuity Discounted at 6% for 15 Periods = [1 - 1/(1 + k) n ] / k = (1 - (1 / (1 + 6%) 15) / 6% = 9.71225

NPV = Annual cash flow * PV factor - Net Initial investment

= $1,080 * 9.71225 - $6127.50

= $4361.73

NPV = $4,361.73

Answer 5:

NPV is positive at $4,361.73 and the project is acceptable.

Zephyr should also consider non quantitative factors while evaluating this project. In general there is a need to look for alternative sources of energy like power generated through wind turbine or solar energy.

Add a comment
Know the answer?
Add Answer to:
Zephyr Farming Pty Ltd is considering the purchase of a wind turbine generator in order to...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Zephyr Farming Pty Ltd is considering the purchase of a wind turbine generator in order to...

    Zephyr Farming Pty Ltd is considering the purchase of a wind turbine generator in order to generate electricity and to reduce the electricity costs for their offices, which are located in Toowoomba. Currently the business uses 60,000 kilowatt hours (kWh) per quarter (3 months) at an average cost of $0.30 per kwh, supplied by the local coal fired power station. The current required rate of return used to evaluate projects is 6%, with a required payback period of 3 years....

  • Zephyr Farming Pty Ltd is considering the purchase of a wind turbine generator in order to...

    Zephyr Farming Pty Ltd is considering the purchase of a wind turbine generator in order to generate electricity and to reduce the electricity costs for their offices, which are located in Toowoomba. Currently the business uses 60,000 kilowatt hours (kWh) per quarter (3 months) at an average cost of $0.30 per kwh, supplied by the local coal fired power station. The current required rate of return used to evaluate projects is 6%, with a required payback period of 3 years....

  • Zephyr Farming Pty Ltd is considering the purchase of a wind turbine generator in order to...

    Zephyr Farming Pty Ltd is considering the purchase of a wind turbine generator in order to generate electricity and to reduce the electricity costs for their offices, which are located in Toowoomba. Currently the business uses 60,000 kilowatt hours (kWh) per quarter (3 months) at an average cost of $0.30 per kwh, supplied by the local coal fired power station. The current required rate of return used to evaluate projects is 6%, with a required payback period of 3 years....

  • Zephyr Farming Pty Ltd is considering the purchase of a wind turbine generator in order to...

    Zephyr Farming Pty Ltd is considering the purchase of a wind turbine generator in order to generate electricity and to reduce the electricity costs for their offices, which are located in Toowoomba. Currently the business uses 60,000 kilowatt hours (kWh) per quarter (3 months) at an average cost of $0.30 per kwh, supplied by the local coal fired power station. The current required rate of return used to evaluate projects is 6%, with a required payback period of 3 years....

  • Zephyr Farming Pty Ltd is considering the purchase of a wind turbine generator in order to...

    Zephyr Farming Pty Ltd is considering the purchase of a wind turbine generator in order to generate electricity and to reduce the electricity costs for their offices, which are located in Toowoomba. Currently the business uses 60,000 kilowatt hours (kWh) per quarter (3 months) at an average cost of $0.30 per kwh, supplied by the local coal fired power station. The current required rate of return used to evaluate projects is 6%, with a required payback period of 3 years....

  • T m Now 186 « Cengage The ghi nhd: Acco... Q eBook Calculator Print Item Wind...

    T m Now 186 « Cengage The ghi nhd: Acco... Q eBook Calculator Print Item Wind turbine capital investment analysis Central Plains Power Company is considering an investment in wind farm technology to reduce its use of natural gas. Initial Installation costs are expected to be $1,200 per kilowatt-hour of capacity. The wind turbine has a capacity of generating 2 megawatts per hour. A kilowatt-hour is 1,000 watts generated per hour and a megawatt hours 1,000 kilowatts generated per hour....

  • this is the full question tho 3. (20%) A certain wind turbine is rated at 5...

    this is the full question tho 3. (20%) A certain wind turbine is rated at 5 MW and has an installed cost of $6,000,000. The capacity factor is 0.38. The turbine is paid for with a down payment of 1/10 of the installed cost and a loan. The loan interest rate, b, is 8% and the period of the loan, N, is 15 years. The economic lifetime of the turbine, L, is to be 20 years, the inflation rate is...

  • - 5 IBX Pty Ltd is considering the purchase of a new machine that is expected to save the company...

    - 5 IBX Pty Ltd is considering the purchase of a new machine that is expected to save the company $89,000 at the end of each year in reduced wages. The machine costs $279,000, plus another $14,000 to be installed. It is expected to last for five years after which it can be sold as scrap for $53,000. Operating expenses (such as fuel and maintenance) are $8,000 pa. a)Determine the annual net cash flows of this investment (ignore the effect...

  • A firm that purchases electricity from the local utility is considering installing a steam generator. A...

    A firm that purchases electricity from the local utility is considering installing a steam generator. A large generator costs $280,000 whereas a small generator costs $210,000. The cost of operating the generator would be $100,000 per year for the large and $125,000 for the small. Either generator will last for five years. The cost of capital is 9%. For each generator option, assume immediate installation, with purchase and operating costs in the current year and operating costs continuing for the...

  • A firm that purchases electricity from the local utility is considering installing a steam generator. A...

    A firm that purchases electricity from the local utility is considering installing a steam generator. A large generator costs $290,000 whereas a small generator costs $170,000. The cost of operating the generator would be $300,000 per year for the large and $320,000 for the small. Either generator will last for five years. The cost of capital is 11%. For each generator option, assume immediate installation, with purchase and operating costs in the current year and operating costs continuing for the...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT