Question

3. (20%) A certain wind turbine is rated at 5 MW and has an installed cost of $6,000,000. The capacity factor is 0.38. The tu

this is the full question tho

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Answer PF wind turbine rated @ SMW. capacity factor - Rated power 0.38 = Aug. powelle Selling power @ P= 5x0.38 sa p .= 1.9 mof payment of Installing wind turbine done by / down payment of installerent, & as loan in installent cost o pot Down pagnien- Ocetrat a Chlorear) Po out Net pore value output - Inpert so you 1 to 0.95 66000 5942.000 166000 1664 000 -4333600. 600000

Add a comment
Know the answer?
Add Answer to:
this is the full question tho 3. (20%) A certain wind turbine is rated at 5...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Zephyr Farming Pty Ltd is considering the purchase of a wind turbine generator in order to...

    Zephyr Farming Pty Ltd is considering the purchase of a wind turbine generator in order to generate electricity and to reduce the electricity costs for their offices, which are located in Toowoomba. Currently the business uses 60,000 kilowatt hours (kWh) per quarter (3 months) at an average cost of $0.30 per kwh, supplied by the local coal fired power station. The current required rate of return used to evaluate projects is 6%, with a required payback period of 3 years....

  • Zephyr Farming Pty Ltd is considering the purchase of a wind turbine generator in order to...

    Zephyr Farming Pty Ltd is considering the purchase of a wind turbine generator in order to generate electricity and to reduce the electricity costs for their offices, which are located in Toowoomba. Currently the business uses 60,000 kilowatt hours (kWh) per quarter (3 months) at an average cost of $0.30 per kwh, supplied by the local coal fired power station. The current required rate of return used to evaluate projects is 6%, with a required payback period of 3 years....

  • Zephyr Farming Pty Ltd is considering the purchase of a wind turbine generator in order to...

    Zephyr Farming Pty Ltd is considering the purchase of a wind turbine generator in order to generate electricity and to reduce the electricity costs for their offices, which are located in Toowoomba. Currently the business uses 60,000 kilowatt hours (kWh) per quarter (3 months) at an average cost of $0.30 per kwh, supplied by the local coal fired power station. The current required rate of return used to evaluate projects is 6%, with a required payback period of 3 years....

  • Zephyr Farming Pty Ltd is considering the purchase of a wind turbine generator in order to...

    Zephyr Farming Pty Ltd is considering the purchase of a wind turbine generator in order to generate electricity and to reduce the electricity costs for their offices, which are located in Toowoomba. Currently the business uses 60,000 kilowatt hours (kWh) per quarter (3 months) at an average cost of $0.30 per kwh, supplied by the local coal fired power station. The current required rate of return used to evaluate projects is 6%, with a required payback period of 3 years....

  • Zephyr Farming Pty Ltd is considering the purchase of a wind turbine generator in order to...

    Zephyr Farming Pty Ltd is considering the purchase of a wind turbine generator in order to generate electricity and to reduce the electricity costs for their offices, which are located in Toowoomba. Currently the business uses 60,000 kilowatt hours (kWh) per quarter (3 months) at an average cost of $0.30 per kwh, supplied by the local coal fired power station. The current required rate of return used to evaluate projects is 6%, with a required payback period of 3 years....

  • Zephyr Farming Pty Ltd is considering the purchase of a wind turbine generator in order to...

    Zephyr Farming Pty Ltd is considering the purchase of a wind turbine generator in order to generate electricity and to reduce the electricity costs for their offices, which are located in Toowoomba. Currently the business uses 60,000 kilowatt hours (kWh) per quarter (3 months) at an average cost of $0.30 per kwh, supplied by the local coal fired power station. The current required rate of return used to evaluate projects is 6%, with a required payback period of 3 years....

  • An industrial wind turbine has blades that are 35 m long. On a 20?C day, wind at atmospheric pressure blows with a velocity of 12 m/s

    An industrial wind turbine has blades that are 35 m long. On a 20?C day, wind at atmospheric pressure blows with a velocity of 12 m/s , and wind in the turbine wake only has a velocity of 11 m/s .(a) If we assume that all of the kinetic energy lost by the wind is converted to electrical energy by the turbine, then what is the power generated by this turbine? (density is 1.205 kg/m^3)(b) This turbine is rated as...

  • 319 71% 120:12 3. Present worth (PW) 4 pts A wind farm in Victoria consists of...

    319 71% 120:12 3. Present worth (PW) 4 pts A wind farm in Victoria consists of rated wind power of [RP] MW, with a capacity factor of [CF]%. The capital cost is about $[cc]/kW rated power. The electricity produced over one year is sold at $[LCOE]/kWh. The farm needs to spend about [OM]% of the capital cost for maintenance every year and at the end of [n] years it is expected to have a salvage value of [S]% of the...

  • . A typical commercial wind turbine costs approximately $2 million per MW of installed power and...

    . A typical commercial wind turbine costs approximately $2 million per MW of installed power and requires 5.76 TJ per million dollars of energy to manufacture the wind turbine. (a) Calculate the amount of energy that is consumed (i.e. energy invested) in the manufacture ofa 1.5 MW wind turbine, assuming that turbine manufacture requires 5.76 TJ per million dollars spent. (TJ Tera-joules 1012 joules) (b) If the wind turbine has blades that are 40 meters (radius) long and the average...

  • Question 2 Portugal has a typical insolation of 1000 W/m2. A solar PV plant located there has an ...

    Question 2 Portugal has a typical insolation of 1000 W/m2. A solar PV plant located there has an output of 11 MWp. Since the collectors track the sun, the power output is steady at 11 MW from 09:00 to 16:00 Hrs and almost zero outside this time. The lifetime of the system is 20 years with an annual operating cost and total capital investment of €1 million and €75 million, respectively. The cost of capital is 7% p.a. The efficiency...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT