Compute the IRR statistic for Project F. The appropriate cost of
capital is 12 percent. (Do not round intermediate
calculations and round your final answer to 2 decimal
places.)
Project F | |||||
Time: | 0 | 1 | 2 | 3 | 4 |
Cash flow: | −$10,300 | $3,950 | $4,780 | $2,120 | $2,750 |
Should the project be accepted or rejected?
rejected
accepted
Net present cash outflow = 10300
Net present cash inflow = cash inflow /1+coc x 1+coc (multiply till no. Of years it takes to generate inflow)
Year 1. 3950/(1.12) = 3537
Year 2. 4780/(1.12x1.12). = 3810
Year. 3. 2120/(1.12x1.12x1.12). = 1509
Year 4. 2750/(1.12x1.12x1.12x1.12). = 1747
Total net cash inflow. = 10603
Net present value = net cash inflow - net cash outflow
= 10603. - 10300
=. 300
As net present value is positive the project shall accepted.
Compute the IRR statistic for Project F. The appropriate cost of capital is 12 percent. (Do...
Compute the IRR for Project F. The appropriate cost of capital is 11 percent. (Do not round intermediate calculations and round your final answer to 2 decimal places.) Project F Time: Cash flow:-$10,100 $3,850 $4,680 $2,020 $2,650 IRR % Should the project be accepted or rejected? rejected O accepted Compute the IRR static for Project E. The appropriate cost of capital is 7 percent. (Do not round intermediate calculations and round your final answer to 2 decimal places.) Project E...
Compute the IRR for Project F. The appropriate cost of capital is 13 percent. (Do not round intermediate calculations and round your final answer to 2 decimal places.) Project F Time: 2 4 Cash flow: -$9,900 $3,7s0 $4,580 $1,920 $2,550 IRR Should the project be accepted or rejected? ассepted Orejected Compute the IRR static for Project E. The appropriate cost of capital is 7 percent. (Do not round intermediate calculations and round your final answer to 2 decimal places.) Project...
Compute the IRR for Project F. The appropriate cost of capital is 11 percent. (Do not round intermediate calculations and round your final answer to 2 decimal places.) Project F Time: 1 Cash flow: -$10,400 $4,000 4 2 $4,830 3 $2,170 $2,800 IRR % Should the project be accepted or rejected? O rejected O accepted
Compute the IRR for Project F. The appropriate cost of capital is 13 percent. (Do not round intermediate calculations and round your final answer to 2 decimal places.) Project F Time: 0 1 2 3 4 Cash flow: -10-200 $3,900 $4,730 $2,070 $2,700 IRR % Should the project be accepted or rejected? O rejected O accepted
Compute the IRR statistic for Project E. The appropriate cost of capital is 9 percent. (Do not round intermediate calculations and round your final answer to 2 decimal places.) Project E Time: 0 1 2 3 4 5 Cash flow −$1,800 $670 $720 $680 $460 $260 IRR? Should the project be accepted or rejected?
Compute the IRR static for Project E. The appropriate cost of capital is 8 percent. (Do not round intermediate calculations and round your final answer to 2 decimal places.) Project E Time: -$1,000 $350 $480 $520 $300 $100 Cash flow: IRR : :% Should the project be accepted or rejected? O accepted O rejected
Compute the MIRR statistic for Project lif the appropriate cost of capital is 12 percent. (Do not round intermediate calculations and round your final answer to 2 decimal places.) Project I Time: Cash flow: 0 -$11,300 1 $5,480 2 $4,330 3 $1,670 4 $2,150 MIRR % Should the project be accepted or rejected? rejected accepted
Compute the IRR static for Project E. The appropriate cost of capital is 9 percent. (Do not round intermediate calculations. Round your final answer to 2 decimal places.) Project E Time: 0 1 2 3 4 5 Cash flow –$1,800 $670 $720 $680 $460 $260 IRR % Should the project be accepted or rejected? Rejected Accepted
Compute the IRR static for Project E. The appropriate cost of capital is 8 percent. (Do not round intermediate calculations and round your final answer to 2 decimal places.) Project E Time: Cash flow 0 $1,300 1 $470 2 $570 3 $580 4 $360 5 $160 IRR IRR C % Should the project be accepted or rejected? O accepted O rejected
Compute the IRR static for Project E. The appropriate cost of capital is 9 percent. (Do not round intermediate calculations and round your final answer to 2 decimal places.) Project E Time: 0 -$2,900 1 $910 2 $900 3 $800 4 $580 5 $380 Cash flow IRR % Should the project be accepted or rejected? O rejected O accepted