Answer:
Given
One time cost A= RM 10 million=RM 10,000,000
Salvage Value S =RM 250,000
Project Life n= 10 years
Annual Cost P= RM 11 miilion=RM 11,000,000
MARR r=15% per year
PV = -PV of Annual cost+PV of salvage cost- One time cost
PV of Annual cost= P*(1-(1+r)^-n)/r=11,000,000*(1-(1+15%)^-10)/15%=RM 55,206,454.88
PV of salvage value= S/(1+r)^n=250000/(1+15%)^10=RM 61796.18
PV =-55,206,454.88+61796.18-10,000,000=-RM 65,144,658.71
For make in house machine PV of in house machine should be less than PV of purchased machine.
b) Is the cost of the solar project justified by the savings? (10 marks) QUESTION 2...
QUESTION 2 (25 MARKS) For several years, CC Corporation has purchased the carafe assembly of its major coffeemaker line at an annual cost of RM 11 million. The suggestion to make the component in-house has been made. For the three departments involved, the annual indirect cost rates, estimated material, labor and hours are found in Table Q2. The allocated hours column is the time necessary to produce the carafes for a year. Equipment must be purchased with the following estimates:...
QUESTION 2 (25 MARKS) A chemical company is considering two processes for isolating DNA material. The incremental cash flows between the two alternatives, J and S, have an incremental internal rate of return that is less than 40%, which is the MARR of the company. However, the company CEO prefers the more expensive process S. She believes the company can implement cost controls to reduce the annual cost of the more expensive process. By how much would she have to...
1/ A retrofit project is estimated to cost $250,000. The energy savings are expected to last 10 years. The retrofit is expected to save 325 MWh per year. Assuming a discount rate of 6%, and an electricity cost of $0.15/kWh: a/ What is the net-present value of the system (4 marks)? b/ What is the equivalent cost of the saved energy (4 marks)?
A university spent $1.8 million to install solar panels atop a parking garage. These panels will have a capacity of 500kw, have a life expectancy of 20 years and suppose the discount rate is 10%. a. If electricity can be purchased for costs of $0.10 per kwh, how many hours per year will the solar panels have to operate to make this project break even? b. If efficient systems operate for 2400 hours per year, would the project break even?...
Your firm is implementing a new energy efficiency project. The initial cost will be $235.000. and the useful life of the needed equipment is 8 years. The firm is uncertain about the annual savings. The optimistic value for the savings is $37,000 per year, the most likely value is $29,000 per year, and the pessimistic value is $18,000 per year. The MARR is 10% a) Use the range of estimates to u te the mean annual savings by the beta...
Question 1 (25 marks) You are the Chief Operating Officer (COO) of an electrical appliances company, Sung-Sam. Currently you are considering replacing the existing old assembly line with a new one in order to boost the production capacity and product variety. The old assembly line was purchased seven years ago at a total cost of $2.4 million. It has a 12-year economic life with five years remaining and zero salvage value. If this assembly line was to be sold today,...
1) A machinery upgrade project will cost $14 million, and produce cost savings of $1 million in perpetuity. What is the project NPV if the required rate of return is 11%? Enter answer in millions, to two decimal places. 2) Your company is considering a project that requires an initial investment of $12 million, and is expected to produce cash flows of $4 million each year for 10 years. At the end of year 11, the project will require site...
Question 2 Untuk terus berdaya saing, syarikat pembekal untuk sebuah syarikat semikonduktor terkemuka perlu melabur untuk platform 'big data'. Anggaran ekonomi untuk setiap pakej ditunjukkan dalam Jadual Q2 di bawah. To remain competitive, a supplier for a huge semiconductor company has to invest for a big data platform. The economic estimates for each package are shown in Table Q2 below Jadual S2/Table Q2 Pakei Package Pelaburan permulaan Initial investment Penerimaan tahunan Annual receipts Perbelanjaan tahunarn Annual expenses Jangka hayat (tahun)...
A university spent $2 million to install solar panels atop a parking garage. These panels will have a capacity of 800 kilowatts (kW) and have a life expectancy of 20 years. Suppose that the discount rate is 10%, that electricity can be purchased at $0.30 per kilowatt-hour (kWh), and that the marginal cost of electricity production using the solar panels is zero. Hint: It may be easier to think of the present value of operating the solar panels for 1...
CONFIDENTIA BFF/BFM/151611/BFF1922 QUESTION 3 (25 MARKS) The projected market value and operation & maintenance (O&M) costs associated with a presently owned machine are shown in Table 3. An outside vendor of services has offered to provide the service of the existing machine at a fixed price per year. If the presently owned machine is replaced now, the cost of the fixed-price contract will be RM330,000 for each of the next 3 years. If the presently owned machine is replaced next...