Question

Question 18 1 pts Acme Construction specializes in concrete work. Each job is a project and they rely heavily on part-time wo

0 0
Add a comment Improve this question Transcribed image text
Answer #1


Solution: 16.21101 Actual rate= 353400/21800 39,000 Favorable LABOUR RATE VARIANCE=(Standard rate-actual rate)* actual hours

Add a comment
Know the answer?
Add Answer to:
Question 18 1 pts Acme Construction specializes in concrete work. Each job is a project and...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Question 19 1 pts Acme Manufacturing uses standard costing. Using the following data, calculate the Material...

    Question 19 1 pts Acme Manufacturing uses standard costing. Using the following data, calculate the Material Cost Variance. 29.5 20 Std Materials 5 sheets at $5.90 Std Direct Labor 2 hrs at $10 Std Mfg Ovrhd 2 direct labor hrs at $5 Total Standard Cost per unit Actual Material Price 5 sheets at $6.20 Actual Sheets Used 31 60000 This problem is a variation of the problem on page 204 chapter 24 Remember that when analyzing variances a negative result...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT