Question

At the beginning of the year, Fort Worth Manufacturing estimated that its annual variable factory overhead would be $923,400,

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Solution a:

Variable Overhead Cost Variance
Actual Cost Standard cost for actual quantity Standard Cost
AH * AR = AH * SR = SH * SR =
45500 $20.00 $910,000.00 45500 $19.00 $864,500.00 48000 $19.00 $912,000.00
$45,500.00 Unfavorable $47,500.00 Favorable
Variable overhead rate variance Variable overhead efficiency variance
Variable overhead rate variance $45,500.00 Unfavorable
Variable overhead efficiency variance $47,500.00 Favorable
Variable overhead cost variance $2,000.00 Favorable

solution b:

Fixed Overhead Cost Variance
Actual Fixed OH Cost Budgeted Fixed Overhead Standard Cost (FOH Applies)
SH* BR
$1,750,000.00 $1,798,200.00 48000 $37.00 $1,776,000.00
$48,200.00 Favorable $22,200.00 Unfavorable
Fixed overhead Budget Variance Fixed overhead volume variance
Fixed overhead Budget Variance $48,200.00 Favorable
Fixed overhead volume variance $22,200.00 Unfavorable
Total Fixed overhead variance $26,000.00 Favorable
Add a comment
Know the answer?
Add Answer to:
At the beginning of the year, Fort Worth Manufacturing estimated that its annual variable factory overhead...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Factory Overhead Cost Variances The following data relate to factory overhead cost for the production of...

    Factory Overhead Cost Variances The following data relate to factory overhead cost for the production of 6,000 computers: Actual: Variable factory overhead $170,200 Fixed factory overhead 57,500 Standard: 6,000 hrs. at $35 210,000 If productive capacity of 100% was 10,000 hours and the total factory overhead cost budgeted at the level of 6,000 standard hours was $233,000, determine the variable factory overhead controllable variance, fixed factory overhead volume variance, and total factory overhead cost variance. The fixed factory overhead rate...

  • Factory Overhead Cost Variances The following data relate to factory overhead cost for the production of...

    Factory Overhead Cost Variances The following data relate to factory overhead cost for the production of 8,000 computers: Actual: Variable factory overhead $166,800 Fixed factory overhead 45,500 Standard: 8,000 hrs. at $25 200,000 If productive capacity of 100% was 13,000 hours and the total factory overhead cost budgeted at the level of 8,000 standard hours was $217,500, determine the variable factory overhead Controllable Variance, fixed factory overhead volume variance, and total factory overhead cost variance. The fixed factory overhead rate...

  • Trico Company set the following standard unit costs for its single product. Direct materials (30 Ibs....

    Trico Company set the following standard unit costs for its single product. Direct materials (30 Ibs. @ $5.10 per Ib.) Direct labor (8 hrs. @ $15 per hr.) Factory overhead-Variable (8 hrs. @ $6 per hr.) Factory overhead-Fixed (8 hrs. @ $9 per hr.) Total standard cost $ 153.00 120.00 48.00 72.00 $ 393.00 The predetermined overhead rate is based on a planned operating volume of 80% of the productive capacity of 65,000 units per quarter. The following flexible budget...

  • Direct Materials, Direct Labor, and Reports budgeted and actual costs for variable and fixed factory overhead...

    Direct Materials, Direct Labor, and Reports budgeted and actual costs for variable and fixed factory overhead along with the related controllable and volume variances.Factory Overhead Cost Variance Analysis Mackinaw Inc. processes a base chemical into plastic. A detailed estimate of what a product should cost.Standard costs and actual costs for direct materials, direct labor, and factory overhead incurred for the manufacture of 70,000 units of product were as follows: Standard Costs Actual Costs Direct materials 189,000 lbs. at $6.00 187,100...

  • Factory Overhead Cost Variance Report Tannin Products Inc. prepared the following factory overhead cost budget for...

    Factory Overhead Cost Variance Report Tannin Products Inc. prepared the following factory overhead cost budget for the Trim Department for July of the current year, during which it expected to use 14,000 hours for production: Variable overhead costs: Indirect factory labor $47,600 Power and light 10,360 Indirect materials 15,400    Total variable overhead cost $73,360 Fixed overhead costs: Supervisory salaries $56,430 Depreciation of plant and equipment 14,850 Insurance and property taxes 27,720    Total fixed overhead cost 99,000 Total factory overhead cost...

  • Choose the correct bolded choices to complete the sentences. The variable overhead cost variance is (favorable,...

    Choose the correct bolded choices to complete the sentences. The variable overhead cost variance is (favorable, unfavorable) because Longman actually spent (less, more) than budgeted. The variable overhead efficiency variance is (favorable, unfavorable) because the actual hours used was (more, less) than budgeted. The fixed overhead cost variance is (favorable, unfavorable) because Longman actually spent (less, more) than budgeted for fixed overhead. The fixed overhead volume variance is (favorable, unfavorable) because Longman allocated (more, less) overhead to jobs than the...

  • Direct Materials and Direct Labor, Variance Analysis; Factory Overhead Cost Variance Analysis Route 66 Tire Co....

    Direct Materials and Direct Labor, Variance Analysis; Factory Overhead Cost Variance Analysis Route 66 Tire Co. manufactures automobile tires. Standard costs and actual costs for direct materials, direct labor, and factory overhead Incurred for the manufacture of 7,200 tires were as follows: Standard Costs Actual Costs Direct materials 9,400 lbs. at $5.50 9,300 lbs. at $5.40 Direct labor 1,800 hrs. at $17.60 1,840 hrs. at $17.90 Factory overhead Rates per direct labor hr. based on 100% of normal capacity of...

  • Direct Materials and Direct Labor, Variance Analysis; Factory Overhead Cost Variance Analysis Route 66 Tire Co....

    Direct Materials and Direct Labor, Variance Analysis; Factory Overhead Cost Variance Analysis Route 66 Tire Co. manufactures automobile tires. Standard costs and actual costs for direct materials, direct labor, and factory overhead incurred for the manufacture of 7,200 tires were as follows: Standard Costs Actual Costs 9,300 lbs. at $5.40 Direct materials 9,400 lbs. at $5.50 1,800 hrs. at $17.60 1,840 hrs. at $17.90 Direct labor Factory overhead Rates per direct labor hr., based on 100% of normal capacity of...

  • I have completed 1and 2, but I need help with number 3 (compute overhead controllable volume variances) Required...

    I have completed 1and 2, but I need help with number 3 (compute overhead controllable volume variances) Required information [The following information applies to the questions displayed below Trico Company set the following standard unit costs for its single product Direct materials (30 Ibs.$4.80 per Ib.) Direct labor (7 hrs. @ $14 per hr. Factory overhead-variable (7 hrs. $6 per hr.) Factory overhead-fixed (7 hrs.$9 per hr) Total standard cost $ 144.0 98.00 42.00 63.00 $ 347.00 The predetermined overhead...

  • Factory Overhead Variance Corrections The data related to Shunda Enterprises Inc.'s factory overh...

    Factory Overhead Variance Corrections The data related to Shunda Enterprises Inc.'s factory overhead cost for the production of 50,000 units of product are as follows: Actual: Variable factory overhead Fixed factory overhead 76,000 hrs. at $7 ($4.10 for variable factory overhead) $308,500 220,200 532,000 Standard: Productive capacity at 100% of normal was 75,100 hours, and the factory overhead cost budgeted at the level of 76,000 standard hours was $528,800. Based on these data the chief cost accountant prepared the following...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT