Question
I have completed 1and 2, but I need help with number 3 (compute overhead controllable volume variances)
Required information [The following information applies to the questions displayed below Trico Company set the following stan
Direct materials (1,728,000 Ibs. $4.80 per Ib.) 8,294,400 5,644,800 6,048,000 $19,987,200 Direct labor (403,200 hrs. $14 per
Required 1. Compute the direct materials cost variance, including its price and quantity variances. Answer is complete and co
2. Compute the direct labor cost variance, Including its rate and efficiency variances. Answer is complete and correct. Actua
3. Compute the overhead controllable and volume variances. Answer is complete but not entirely correct. Controllable Variance
Required information [The following information applies to the questions displayed below Trico Company set the following standard unit costs for its single product Direct materials (30 Ibs.$4.80 per Ib.) Direct labor (7 hrs. @ $14 per hr. Factory overhead-variable (7 hrs. $6 per hr.) Factory overhead-fixed (7 hrs.$9 per hr) Total standard cost $ 144.0 98.00 42.00 63.00 $ 347.00 The predetermined overhead rate is based on a planned operating volume of 80% of the productive capacity of 6400 units per quarter. The following flexible budget information is available. ng Leve 90% Production in units Standard direct labor hours Budgeted overhead Fixed factory overhead Variable factory overhead 44,800 313,600358,400 1,200 57,600 $3,225,600 $3,225,600 3,225,600 $1,881,6e0 52,150,400 $2,419,200 During the current quarter, the company operated at 90% of capacity and produced 57600 units of product actual direct labor totaled 400.200 hours. Units produced were assigned the following standard costs
Direct materials (1,728,000 Ibs. $4.80 per Ib.) 8,294,400 5,644,800 6,048,000 $19,987,200 Direct labor (403,200 hrs. $14 per hr.) Factory overhead (403, 200 hrs. @$15 per hr.) Total standard cost Actual costs incurred during the current quarter follow Direct materials (1,715,000 Ibs. @$6.30 per lb.) Direct labor (400,200 hrs. $11.00 per hr.) Fixed factory overhead costs Variable factory overhead costs Total actual costs $10,804,500 4,402,200 2,813,8060 2,634,200 $20,654,700
Required 1. Compute the direct materials cost variance, including its price and quantity variances. Answer is complete and correct. Actual Cost Standard Cost Actual Actual Actual quantity ,715,000 Standard Standard Standard price quantity price s 6.30 quantity I 1.728,000 price 1.715,000 4.80 4.80 10,804,500 8,232,000 8,294,400 $ 62,400 2,572,500 Direct materials price variance 2.572.500 62,400- 2,510,100Unfavorable Unfavorable Direct materials quantity variance Favorable Total direct materials variance
2. Compute the direct labor cost variance, Including its rate and efficiency variances. Answer is complete and correct. Actual Cost Standard Cost Actual hours Actual Actual Standard Standard hours 400,200 Standard rate rate hours rate 400,200 14.00 11.00 403,200 14 00 4,402,200 5.602,800 5 644,800 1,200,600 42,000 Direct labor rate variance Favorable 1,200,600 Direct labor efficiency variance 42,000 Favorable Favorable Total direct labor variance 1,242,600
3. Compute the overhead controllable and volume variances. Answer is complete but not entirely correct. Controllable Variance 5,448,000 Actual overhead Budgeted overhead $ 6,128,640 Controllable variance 680,640Favorable
0 0
Add a comment Improve this question Transcribed image text
Answer #1
3. Computation of Overhead controllable and volume variances :-
Controllable Variance
Actual overhead (2,813,800+2,634,200) $      5,448,000
Budgeted overhead (3225600+2419200) $      5,644,800
Controllable Variance $         196,800 Favorable
Fixed Overhead volume variance
Budgeted Fixed Overhead $      3,225,600
Fixed Overhead Applied                                   [(57600 units*7 hours)*$9] $      3,628,800
Fixed Overhead volume variance $         403,200 Favorable

Feel free to ask any clarification, if required. Please provide feedback by thumbs up, if satisfied. It will be highly appreciated. Thank you.

Add a comment
Know the answer?
Add Answer to:
I have completed 1and 2, but I need help with number 3 (compute overhead controllable volume variances) Required...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Trico Company set the following standard unit costs for its single product. Direct materials (30 Ibs....

    Trico Company set the following standard unit costs for its single product. Direct materials (30 Ibs. @ $4.80 per Ib.) $ 144.00 Direct labor (7 hrs. @ $14 per hr.) 98.00 Factory overhead—variable (7 hrs. @ $6 per hr.) 42.00 Factory overhead—fixed (7 hrs. @ $9 per hr.) 63.00 Total standard cost $ 347.00 The predetermined overhead rate is based on a planned operating volume of 80% of the productive capacity of 64,000 units per quarter. The following flexible budget...

  • 2. Compute the direct labor cost variance, including its rate and efficiency variances. Standard Cost Actual...

    2. Compute the direct labor cost variance, including its rate and efficiency variances. Standard Cost Actual Cost $ $ 0 0 0 0 3. Compute the overhead controllable and volume variances. Controllable Variance Actual overhead Budgeted overhead Controllable variance Fixed overhead volume variance Budgeted fixed overhead Fixed overhead cost applied Fixed overhead volume variance Check my work 1 ! Required information 12.5 [The following information applies to the questions displayed below.] points Trico Company set the following standard unit costs...

  • Required information The following information applies to the questions displayed below] Trico Company set the following...

    Required information The following information applies to the questions displayed below] Trico Company set the following standard unit costs for its single product. Direct materials (30 Ibs. $4.80 per 1b.) Direct labor (6 hrs. e $14 per hr.) Factory overhead-variable (6 hrs.e $7 per hr.) Factory overhead-fixed (6 hrs. e $12 per hr.) $144.00 84.00 42.00 72.00 Total standard cost $342.00 The predetermined overhead rate is based on a planned operating volume of 80 % of the productive capacity of...

  • Required information Use the following information for the Problems below. The following information applies to the q...

    Required information Use the following information for the Problems below. The following information applies to the questions displayed below.] Trico Company set the following standard unit costs for its single product. Direct materials (30 Ibs. $5. 10 per Ib.) Direct labor (4 hrs. @$15 per hr.) Factory overhead-variable (4 hrs $6 per hr.) Factory overhead- fixed (4 hrs. Q $11 per hr. ) 153, 00 60, 00 24. 00 44, 00 281. 00 Total standard cost The predetermined overhead rate...

  • Need help with the following accounting problem. Required information Use the following information for the Problems...

    Need help with the following accounting problem. Required information Use the following information for the Problems below. [The following information applies to the questions displayed below.) Trico Company set the following standard unit costs for its single product. Direct materials (30 Ibs. @ $5.00 per Ib.) Direct labor (7 hrs. @ $14 per hr.) Factory overhead-variable (7 hrs. @ $7 per hr.) Factory overhead-fixed (7 hrs. @ $9 per hr.) Total standard cost $150.00 98.00 49.00 63.00 $360.00 The predetermined...

  • 100 points Required information Use the following information for the Problems below. The following information applies...

    100 points Required information Use the following information for the Problems below. The following information applies to the questions displayed below.] Trico Company set the following standard unit costs for its single product. eBook Direct materials (30 Ibs. $4.90 per Ib.) Direct labor (4 hrs. @ $16 per hr.) Factory overhead Variable (4 hrs. $6 per hr.) Factory overhead-Pixed (4 hrs. @ $10 per hr.) Total standard cost $147.00 64.00 24.00 40.00 $275.00 Print References The predetermined overhead rate is...

  • please answer in given format. yes, this is one question. Trico Company set the following standard...

    please answer in given format. yes, this is one question. Trico Company set the following standard unit costs for its single product. Direct materials (30 Ibs. @ $4.40 per Ib.) Direct labor (6 hrs. @ $14 per hr.) Factory overhead-variable (6 hrs. @ $8 per hr.) Factory overhead-fixed (6 hrs. @ $11 per hr.) Total standard cost $132.00 84.00 48.00 66.00 $330.00 The predetermined overhead rate is based on a planned operating volume of 80% of the productive capacity of...

  • Trico Company set the following standard unit costs for its single product. Direct materials (30 Ibs....

    Trico Company set the following standard unit costs for its single product. Direct materials (30 Ibs. @ $4.80 per Ib.) Direct labor (8 hrs. @ $16 per hr.) Factory overhead-variable (8 hrs. @ $9 per hr.) Factory overhead-fixed (8 hrs. @ $12 per hr.) Total standard cost $144.00 128.00 72.00 96.00 $440.00 The predetermined overhead rate is based on a planned operating volume of 80% of the productive capacity of 59.000 units per quarter. The following flexible budget information is...

  • Factory Overhead Cost Variances The following data relate to factory overhead cost for the production of...

    Factory Overhead Cost Variances The following data relate to factory overhead cost for the production of 6,000 computers: Actual: Variable factory overhead $170,200 Fixed factory overhead 57,500 Standard: 6,000 hrs. at $35 210,000 If productive capacity of 100% was 10,000 hours and the total factory overhead cost budgeted at the level of 6,000 standard hours was $233,000, determine the variable factory overhead controllable variance, fixed factory overhead volume variance, and total factory overhead cost variance. The fixed factory overhead rate...

  • Required information Use the following information for the Problems below. The following information applies to the...

    Required information Use the following information for the Problems below. The following information applies to the questions displayed below.] Trico Company set the following standard unit costs for its single product. Direct materials (30 lbs. @ $4 per Ib.) Direct labor (5 hrs. @ $14 per hr.) Factory overhead-Variable (5 hrs. @ $8 per hr.) Factory overhead-Fixed (5 hrs. @ $10 per hr.) Total standard cost $120.00 70.00 40.00 50.00 $280.00 The predetermined overhead rate is based on a planned...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT