Question

Required information The following information applies to the questions displayed below] Trico Company set the following stan
During the current quarter, the company operated at 90 % of capacity and produced 59,400 units of product; actual direct labo
Required information Actual Cost Standard Cost AQ AP AQ SP SQ SP 0 0 2. Compute the direct labor cost variance, including its
Required information 2. Compute the direct labor cost variance, including its rate and efficiency variances. AH-Actual Hours
3. Compute the overhead controllable and volume variances. Controllable Variance Actual overhead Budgeted overhead Controllab
Fixed overhead volume variance Budgeted fixed overhead Fixed overhead cost applied Fixed overhead volume variance
Required information The following information applies to the questions displayed below] Trico Company set the following standard unit costs for its single product. Direct materials (30 Ibs. $4.80 per 1b.) Direct labor (6 hrs. e $14 per hr.) Factory overhead-variable (6 hrs.e $7 per hr.) Factory overhead-fixed (6 hrs. e $12 per hr.) $144.00 84.00 42.00 72.00 Total standard cost $342.00 The predetermined overhead rate is based on a planned operating volume of 80 % of the productive capacity of 66,000 units per quarter. The following flexible budget informations available. Operating Levels 70% 90% 80% Production in units Standard direct 1abor hours Budgeted overhead Fixed factory overhead Variable factory overhead 46,200 277,200 52,800 316,800 59,400 356,400 $3,801,600 $3,801,600 $3,801,600 $1,940,400 $2,217,600 $2,494.800
During the current quarter, the company operated at 90 % of capacity and produced 59,400 units of product; actual direct labor totaled 303,800 hours. Units produced were assigned the following standard costs. Direct materials (1,782,000 Ibs. e $4.80 per Ib.) Direct labor (356,400 hrs. $14 per hr.) Factory overhead (356,400 hrs.e $19 per hr. 8,553,600 4,989,600 6,771,600 Total standard cost $20,314,800 Actual costs incurred during the current quarter follow Direct materials (1,522,000 Ibs. e $7.30 per lb.) Direct labor (303,800 hrs. e $13. 10 per hr.) Fixed factory overhead costs $11,110,600 3,979,780 2,336,900 Variable factory overhead costs 2,637,700 $20,064,980 Total actual costs Required: 1. Compute the direct materials cost variance, including its price and quantity variances. AQ Actual Quantity SQ-Standard Quantity AP Actual Price SP- Standard Price
Required information Actual Cost Standard Cost AQ AP AQ SP SQ SP 0 0 2. Compute the direct labor cost variance, including its rate and efficiency variances. AH-Actual Hours SH Standard Hours AR Actual Rate SR Standard Rate
Required information 2. Compute the direct labor cost variance, including its rate and efficiency variances. AH-Actual Hours SH=Standard Hours AR Actual Rate SR Standard Rate Actual Cost Standard Cost S 0 S 0
3. Compute the overhead controllable and volume variances. Controllable Variance Actual overhead Budgeted overhead Controllable variance
Fixed overhead volume variance Budgeted fixed overhead Fixed overhead cost applied Fixed overhead volume variance
0 0
Add a comment Improve this question Transcribed image text
Answer #1

la) Compute the yariable overhead spendirg and efficiency variances Standard Cost Actual cost AP SH 572 000 30 4,F0 $11,110,6

Add a comment
Know the answer?
Add Answer to:
Required information The following information applies to the questions displayed below] Trico Company set the following...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • [The following information applies to the questions displayed below.] Trico Company set the following standard unit...

    [The following information applies to the questions displayed below.] Trico Company set the following standard unit costs for its single product. Direct materials (30 Ibs. @ $5.10 per Ib.) $ 153.00 Direct labor (8 hrs. @ $14 per hr.) 112.00 Factory overhead—variable (8 hrs. @ $6 per hr.) 48.00 Factory overhead—fixed (8 hrs. @ $12 per hr.) 96.00 Total standard cost $ 409.00 The predetermined overhead rate is based on a planned operating volume of 80% of the productive capacity...

  • [The following information applies to the questions displayed below.] Trico Company set the following standard unit...

    [The following information applies to the questions displayed below.] Trico Company set the following standard unit costs for its single product. Direct materials (30 Ibs. @ $5.10 per Ib.) $ 153.00 Direct labor (4 hrs. @ $15 per hr.) 60.00 Factory overhead—variable (4 hrs. @ $6 per hr.) 24.00 Factory overhead—fixed (4 hrs. @ $11 per hr.) 44.00 Total standard cost $ 281.00 The predetermined overhead rate is based on a planned operating volume of 80% of the productive capacity...

  • Use the following information for the Problems below. (The following information applies to the questions displayed...

    Use the following information for the Problems below. (The following information applies to the questions displayed below.) Trico Company set the following standard unit costs for its single product. Direct materials (30 Ibs. @ $4.40 per Ib.) Direct labor (6 hrs. @ $14 per hr.) Factory overhead-variable (6 hrs. @ $9 per hr.) Factory overhead-fixed (6 hrs. @ $12 per hr.) Total standard cost $132.00 84.00 54.00 72.00 $342.00 $372.00 The predetermined overhead rate is based on a planned operating...

  • The following information applies to the questions displayed below.] Trico Company set the following standard unit...

    The following information applies to the questions displayed below.] Trico Company set the following standard unit costs for its single product. Direct materials (30 Ibs. @ $5.00 per Ib.) $ 150.00 Direct labor (7 hrs. @ $14 per hr.) 98.00 Factory overhead—variable (7 hrs. @ $7 per hr.) 49.00 Factory overhead—fixed (7 hrs. @ $9 per hr.) 63.00 Total standard cost $ 360.00 The predetermined overhead rate is based on a planned operating volume of 80% of the productive capacity...

  • [The following information applies to the questions displayed below.] Trico Company set the following standard unit...

    [The following information applies to the questions displayed below.] Trico Company set the following standard unit costs for its single product. Direct materials (30 Ibs. @ $5.10 per Ib.) Direct labor (8 hrs. @ $15 per hr.) Factory overhead-variable (8 hrs. @ $6 per hr.) Factory overhead-fixed (8 hrs. @ $9 per hr.) Total standard cost $153.00 120.00 48.00 72.00 $393.00 The predetermined overhead rate is based on a planned operating volume of 80% of the productive capacity of 65,000...

  • please assist with the information provided: Trico Company set the following standard unit costs for its...

    please assist with the information provided: Trico Company set the following standard unit costs for its single product. Direct materials (30 Ibs. @ $4.40 per Ib.) Direct labor (6 ha. @ $14 per hr.) Factory overhead-variable (6 hrs. @ $8 per hr.) Factory overhead-fixed 16 hrs. @ $11 per hr.) Total standard cost $132.00 84.00 48.00 66.00 $330.00 The predetermined overhead rate is based on a planned operating volume of 80% of the productive capacity of 60,000 units per quarter....

  • Trico Company set the following standard unit costs for its single product. Direct materials (30 Ibs....

    Trico Company set the following standard unit costs for its single product. Direct materials (30 Ibs. @ $5.10 per Ib.) $ 153.00 Direct labor (8 hrs. @ $14 per hr.) 112.00 Factory overhead—variable (8 hrs. @ $6 per hr.) 48.00 Factory overhead—fixed (8 hrs. @ $12 per hr.) 96.00 Total standard cost $ 409.00 The predetermined overhead rate is based on a planned operating volume of 80% of the productive capacity of 66,000 units per quarter. The following flexible budget...

  • please answer in given format. yes, this is one question. Trico Company set the following standard...

    please answer in given format. yes, this is one question. Trico Company set the following standard unit costs for its single product. Direct materials (30 Ibs. @ $4.40 per Ib.) Direct labor (6 hrs. @ $14 per hr.) Factory overhead-variable (6 hrs. @ $8 per hr.) Factory overhead-fixed (6 hrs. @ $11 per hr.) Total standard cost $132.00 84.00 48.00 66.00 $330.00 The predetermined overhead rate is based on a planned operating volume of 80% of the productive capacity of...

  • Trico Company set the following standard unit costs for its single product. Direct materials (30 Ibs....

    Trico Company set the following standard unit costs for its single product. Direct materials (30 Ibs. @ $4.80 per Ib.) $ 144.00 Direct labor (7 hrs. @ $14 per hr.) 98.00 Factory overhead—variable (7 hrs. @ $6 per hr.) 42.00 Factory overhead—fixed (7 hrs. @ $9 per hr.) 63.00 Total standard cost $ 347.00 The predetermined overhead rate is based on a planned operating volume of 80% of the productive capacity of 64,000 units per quarter. The following flexible budget...

  • Required information Use the following information for the Problems below. [The following information applies to the...

    Required information Use the following information for the Problems below. [The following information applies to the questions displayed below.) Trico Company set the following standard unit costs for its single product. Direct materials (30 Ibs. @ $4.40 per Ib.) Direct labor (6 hrs. @ $14 per hr.) Factory overhead-variable (6 hrs. @ $8 per hr.) Factory overhead-fixed (6 hrs. @ $12 per hr.) Total standard cost $132.00 84.00 48.00 72.00 $336.00 The predetermined overhead rate is based on a planned...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question