1. Direct Material Cost Variance
Actual Quantity = 1,466,000
Standard Quantity = 1,863,000
Actual Price = $ 7.4
Standard Price = $ 4.4
Material Price Variance =Actual Quantity x Actual Price - Actual Quantity x Standard Price
Material Price Variance = (1466000 * 7.4) - (1466000 * 4.4)
= 10,848,400-6,450,400
=4,398,000(Adverse)
Material Quantity Variance = Actual Quantiy x Standard Price - Standard Quantity x Standard Price
= (1466000 * 4.4) -( 1863000 * 4.4)
=6,450,400 - 8,197,200
= (1,746,800) (Favourable)
Material Cost Variance = Material Price Variance + Material Quantity Variance
= 4,398,000 (A) + (1,746,800) (F)
= 2,651,200 (A)
2. Direct Labour Cost Variance
Standard Direct Labor Hour = 372600
Actual Direct Labor Hour = 291000
Standard Rate/Hour = $ 14/Hr
Actual Rate/Hour = $12.6/Hr
Labor Rate Variance = Actual Labor Hours * Actual Rate - Actual Labor Hours * Standard Rate
= (291000 * 12.6) - (291000 * 14)
= 3,666,600 - 4,074,000
= -407,400 (Favourable)
Labor Efficiency Variance = Actual Hours x Standard Rate - Standard Hours x Standard Rate
= 291000* 14 - 372600* 14
= 4,074,000- 5,216,400
= -1,142,400 (Favourable)
Direct Labor Variance = Labor Rate Variance + Labor Efficiency Variance
= (- 407,400) (f) + (-1,142,400) (f)
= -1,549,800 (Favourable)
3. Overhead Controllable Variance = Actual Factory Overhead-Budgeted Factory overhead
Actual Factory Overhead = 3014600 +3272200 = $ 6,286,800
Budgeted Allowance Based on standard Hours Allowed = $ 7452000
Overhead Controllable variance=6,286,800-7452000
= −1,165,200 Favorable
Overhead Volume Variance = Actual Fixed Cost Absorbed - Budgeted Fixed Cost
= 3014600- 3974400
= - $959,800(Favourable)
Required information Use the following information for the Problems below. [The following information applies to the...
Use the following information for the Problems below. (The following information applies to the questions displayed below.) Trico Company set the following standard unit costs for its single product. Direct materials (30 Ibs. @ $4.40 per Ib.) Direct labor (6 hrs. @ $14 per hr.) Factory overhead-variable (6 hrs. @ $9 per hr.) Factory overhead-fixed (6 hrs. @ $12 per hr.) Total standard cost $132.00 84.00 54.00 72.00 $342.00 $372.00 The predetermined overhead rate is based on a planned operating...
Required information Use the following information for the Problems below. [The following information applies to the questions displayed below.] Trico Company set the following standard unit costs for its single product. Direct materials (30 lbs. @ $4.00 per Ib.) Direct labor (7 hrs. @ $14 per hr.) Factory overhead-variable (7 hrs. @ $7 per hr.) Factory overhead-fixed (7 hrs. @ $11 per hr.) Total standard cost $120.00 98.00 49.00 77.00 $344.00 The predetermined overhead rate is based on a planned...
Required information Use the following information for the Problems below. The following information applies to the questions displayed below.] Trico Company set the following standard unit costs for its single product. Direct materials (30 Ibs. $5. 10 per Ib.) Direct labor (4 hrs. @$15 per hr.) Factory overhead-variable (4 hrs $6 per hr.) Factory overhead- fixed (4 hrs. Q $11 per hr. ) 153, 00 60, 00 24. 00 44, 00 281. 00 Total standard cost The predetermined overhead rate...
100 points Required information Use the following information for the Problems below. The following information applies to the questions displayed below.] Trico Company set the following standard unit costs for its single product. eBook Direct materials (30 Ibs. $4.90 per Ib.) Direct labor (4 hrs. @ $16 per hr.) Factory overhead Variable (4 hrs. $6 per hr.) Factory overhead-Pixed (4 hrs. @ $10 per hr.) Total standard cost $147.00 64.00 24.00 40.00 $275.00 Print References The predetermined overhead rate is...
Required information Use the following information for the Problems below. The following information applies to the questions displayed below.] Trico Company set the following standard unit costs for its single product. Direct materials (30 lbs. @ $4 per Ib.) Direct labor (5 hrs. @ $14 per hr.) Factory overhead-Variable (5 hrs. @ $8 per hr.) Factory overhead-Fixed (5 hrs. @ $10 per hr.) Total standard cost $120.00 70.00 40.00 50.00 $280.00 The predetermined overhead rate is based on a planned...
Need help with the following accounting problem. Required information Use the following information for the Problems below. [The following information applies to the questions displayed below.) Trico Company set the following standard unit costs for its single product. Direct materials (30 Ibs. @ $5.00 per Ib.) Direct labor (7 hrs. @ $14 per hr.) Factory overhead-variable (7 hrs. @ $7 per hr.) Factory overhead-fixed (7 hrs. @ $9 per hr.) Total standard cost $150.00 98.00 49.00 63.00 $360.00 The predetermined...
Required information Use the following information for the Problems below. [The following information applies to the questions displayed below.] Trico Company set the following standard unit costs for its single product. Direct materials (30 lbs. @ $4.80 per Ib.) Direct labor (8 hrs. @ $16 per hr.) Factory overhead-variable (8 hrs. @ $9 per hr.) Factory overhead-fixed (8 hrs. @ $12 per hr.) Total standard cost $ 144.00 128.00 72.00 96.00 $ 440.00 The predetermined overhead rate is based on...
Required information The following information applies to the questions displayed below] Trico Company set the following standard unit costs for its single product. Direct materials (30 Ibs. $4.80 per 1b.) Direct labor (6 hrs. e $14 per hr.) Factory overhead-variable (6 hrs.e $7 per hr.) Factory overhead-fixed (6 hrs. e $12 per hr.) $144.00 84.00 42.00 72.00 Total standard cost $342.00 The predetermined overhead rate is based on a planned operating volume of 80 % of the productive capacity of...
do 1-3 Required information Use the following information for the Problems below. The following information applies to the questions displayed below.) Trico Company set the following standard unit costs for its single product Direct materials (30 lbs. @ $4.90 per Ib.) Direct labor (4 hrs. @ $16 per hr.) Factory overhead-Variable (4 hrs. @ $6 per hr.) Factory overhead-Fixed (4 hrs. @ $10 per hr.) Total standard cost $147.00 64.00 24.00 40.00 $275.00 The predetermined overhead rate is based on...
[The following information applies to the questions displayed below.] Trico Company set the following standard unit costs for its single product. Direct materials (30 Ibs. @ $5.10 per Ib.) $ 153.00 Direct labor (8 hrs. @ $14 per hr.) 112.00 Factory overhead—variable (8 hrs. @ $6 per hr.) 48.00 Factory overhead—fixed (8 hrs. @ $12 per hr.) 96.00 Total standard cost $ 409.00 The predetermined overhead rate is based on a planned operating volume of 80% of the productive capacity...