Question

Required information Use the following information for the Problems below. [The following information applies to the questionRequired: 1. Compute the direct materials cost variance, including its price and quantity variances. Actual Cost Standard Cos2. Compute the direct labor cost variance, including its rate and efficiency variances. Actual Cost Standard Cost3. Compute the overhead controllable and volume variances. Controllable Variance Actual overhead Budgeted overhead Controllab

0 0
Add a comment Improve this question Transcribed image text
Answer #1

1. Direct Material Cost Variance

Actual Quantity = 1,466,000

Standard Quantity = 1,863,000

Actual Price = $ 7.4

Standard Price = $ 4.4

Material Price Variance =Actual Quantity x Actual Price - Actual Quantity x Standard Price

Material Price Variance = (1466000 * 7.4) - (1466000 * 4.4)

= 10,848,400-6,450,400

=4,398,000(Adverse)

Material Quantity Variance = Actual Quantiy x Standard Price - Standard Quantity x Standard Price

= (1466000 * 4.4) -( 1863000 * 4.4)

=6,450,400 - 8,197,200

= (1,746,800) (Favourable)

Material Cost Variance = Material Price Variance + Material Quantity Variance

= 4,398,000 (A) + (1,746,800) (F)

= 2,651,200 (A)

2. Direct Labour Cost Variance

Standard Direct Labor Hour = 372600

Actual Direct Labor Hour = 291000

Standard Rate/Hour = $ 14/Hr

Actual Rate/Hour = $12.6/Hr

Labor Rate Variance = Actual Labor Hours * Actual Rate - Actual Labor Hours * Standard Rate

= (291000 * 12.6) - (291000 * 14)

= 3,666,600 - 4,074,000

= -407,400 (Favourable)

Labor Efficiency Variance = Actual Hours x Standard Rate - Standard Hours x Standard Rate

= 291000* 14 - 372600* 14

= 4,074,000- 5,216,400

= -1,142,400 (Favourable)

Direct Labor Variance = Labor Rate Variance + Labor Efficiency Variance

= (- 407,400) (f) + (-1,142,400) (f)

= -1,549,800 (Favourable)

3. Overhead Controllable Variance = Actual Factory Overhead-Budgeted Factory overhead

Actual Factory Overhead = 3014600 +3272200 = $ 6,286,800

Budgeted Allowance Based on standard Hours Allowed = $ 7452000

Overhead Controllable variance=6,286,800-7452000

= −1,165,200 Favorable

Overhead Volume Variance = Actual Fixed Cost Absorbed - Budgeted Fixed Cost

= 3014600- 3974400

= - $959,800(Favourable)

5 Direct Material Cost Variance X AQ 1,466,000 SP $4.40 SQ 1863000 Standard cost X I | 8.197,200 SP $4.40 | 10 4.398,000(Adve

Add a comment
Know the answer?
Add Answer to:
Required information Use the following information for the Problems below. [The following information applies to the...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Use the following information for the Problems below. (The following information applies to the questions displayed...

    Use the following information for the Problems below. (The following information applies to the questions displayed below.) Trico Company set the following standard unit costs for its single product. Direct materials (30 Ibs. @ $4.40 per Ib.) Direct labor (6 hrs. @ $14 per hr.) Factory overhead-variable (6 hrs. @ $9 per hr.) Factory overhead-fixed (6 hrs. @ $12 per hr.) Total standard cost $132.00 84.00 54.00 72.00 $342.00 $372.00 The predetermined overhead rate is based on a planned operating...

  • Required information Use the following information for the Problems below. [The following information applies to the...

    Required information Use the following information for the Problems below. [The following information applies to the questions displayed below.] Trico Company set the following standard unit costs for its single product. Direct materials (30 lbs. @ $4.00 per Ib.) Direct labor (7 hrs. @ $14 per hr.) Factory overhead-variable (7 hrs. @ $7 per hr.) Factory overhead-fixed (7 hrs. @ $11 per hr.) Total standard cost $120.00 98.00 49.00 77.00 $344.00 The predetermined overhead rate is based on a planned...

  • Required information Use the following information for the Problems below. The following information applies to the q...

    Required information Use the following information for the Problems below. The following information applies to the questions displayed below.] Trico Company set the following standard unit costs for its single product. Direct materials (30 Ibs. $5. 10 per Ib.) Direct labor (4 hrs. @$15 per hr.) Factory overhead-variable (4 hrs $6 per hr.) Factory overhead- fixed (4 hrs. Q $11 per hr. ) 153, 00 60, 00 24. 00 44, 00 281. 00 Total standard cost The predetermined overhead rate...

  • 100 points Required information Use the following information for the Problems below. The following information applies...

    100 points Required information Use the following information for the Problems below. The following information applies to the questions displayed below.] Trico Company set the following standard unit costs for its single product. eBook Direct materials (30 Ibs. $4.90 per Ib.) Direct labor (4 hrs. @ $16 per hr.) Factory overhead Variable (4 hrs. $6 per hr.) Factory overhead-Pixed (4 hrs. @ $10 per hr.) Total standard cost $147.00 64.00 24.00 40.00 $275.00 Print References The predetermined overhead rate is...

  • Required information Use the following information for the Problems below. The following information applies to the...

    Required information Use the following information for the Problems below. The following information applies to the questions displayed below.] Trico Company set the following standard unit costs for its single product. Direct materials (30 lbs. @ $4 per Ib.) Direct labor (5 hrs. @ $14 per hr.) Factory overhead-Variable (5 hrs. @ $8 per hr.) Factory overhead-Fixed (5 hrs. @ $10 per hr.) Total standard cost $120.00 70.00 40.00 50.00 $280.00 The predetermined overhead rate is based on a planned...

  • Need help with the following accounting problem. Required information Use the following information for the Problems...

    Need help with the following accounting problem. Required information Use the following information for the Problems below. [The following information applies to the questions displayed below.) Trico Company set the following standard unit costs for its single product. Direct materials (30 Ibs. @ $5.00 per Ib.) Direct labor (7 hrs. @ $14 per hr.) Factory overhead-variable (7 hrs. @ $7 per hr.) Factory overhead-fixed (7 hrs. @ $9 per hr.) Total standard cost $150.00 98.00 49.00 63.00 $360.00 The predetermined...

  • Required information Use the following information for the Problems below. [The following information applies to the...

    Required information Use the following information for the Problems below. [The following information applies to the questions displayed below.] Trico Company set the following standard unit costs for its single product. Direct materials (30 lbs. @ $4.80 per Ib.) Direct labor (8 hrs. @ $16 per hr.) Factory overhead-variable (8 hrs. @ $9 per hr.) Factory overhead-fixed (8 hrs. @ $12 per hr.) Total standard cost $ 144.00 128.00 72.00 96.00 $ 440.00 The predetermined overhead rate is based on...

  • Required information The following information applies to the questions displayed below] Trico Company set the following...

    Required information The following information applies to the questions displayed below] Trico Company set the following standard unit costs for its single product. Direct materials (30 Ibs. $4.80 per 1b.) Direct labor (6 hrs. e $14 per hr.) Factory overhead-variable (6 hrs.e $7 per hr.) Factory overhead-fixed (6 hrs. e $12 per hr.) $144.00 84.00 42.00 72.00 Total standard cost $342.00 The predetermined overhead rate is based on a planned operating volume of 80 % of the productive capacity of...

  • do 1-3 Required information Use the following information for the Problems below. The following information applies...

    do 1-3 Required information Use the following information for the Problems below. The following information applies to the questions displayed below.) Trico Company set the following standard unit costs for its single product Direct materials (30 lbs. @ $4.90 per Ib.) Direct labor (4 hrs. @ $16 per hr.) Factory overhead-Variable (4 hrs. @ $6 per hr.) Factory overhead-Fixed (4 hrs. @ $10 per hr.) Total standard cost $147.00 64.00 24.00 40.00 $275.00 The predetermined overhead rate is based on...

  • [The following information applies to the questions displayed below.] Trico Company set the following standard unit...

    [The following information applies to the questions displayed below.] Trico Company set the following standard unit costs for its single product. Direct materials (30 Ibs. @ $5.10 per Ib.) $ 153.00 Direct labor (8 hrs. @ $14 per hr.) 112.00 Factory overhead—variable (8 hrs. @ $6 per hr.) 48.00 Factory overhead—fixed (8 hrs. @ $12 per hr.) 96.00 Total standard cost $ 409.00 The predetermined overhead rate is based on a planned operating volume of 80% of the productive capacity...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT