Solution 1:
Direct Material Cost Variance | ||||||||||||
Actual Cost | Standard cost for actual quantity | Standard Cost | ||||||||||
AQ * | AP = | AQ * | SP = | SQ * | SP = | |||||||
1826000 | $6.70 | $12,234,200.00 | 1826000 | $5.10 | $9,312,600.00 | 1836000 | $5.10 | $9,363,600.00 | ||||
$2,921,600.00 | U | $51,000.00 | F | |||||||||
Direct Material Price Variance | Direct Material Qty variance | |||||||||||
Direct material price variance | $2,921,600.00 | U | ||||||||||
Direct material quantity variance | $51,000.00 | F | ||||||||||
Direct material cost variance | $2,870,600.00 | U |
Solution 2:
Direct Labor Cost Variance | ||||||||||||
Actual Cost | Standard cost for actual quantity | Standard Cost | ||||||||||
AH * | AR = | AH * | SR = | SH * | SR = | |||||||
239800 | $12.00 | $2,877,600.00 | 239800 | $15.00 | $3,597,000.00 | 244800 | $15.00 | $3,672,000.00 | ||||
$719,400.00 | F | $75,000.00 | F | |||||||||
Direct Labor rate Variance | Direct Labor Efficiency Variance | |||||||||||
Direct Labor Rate variance | $719,400.00 | F | ||||||||||
Direct Labor Efficiency variance | $75,000.00 | F | ||||||||||
Direct labor cost variance | $794,400.00 | F |
Solution 3:
Controllable Variance | ||
Actual overhead | $3,761,600.00 | |
Budgeted overhead | $3,862,400.00 | |
Controllable variance | $100,800.00 | F |
Fixed overhead volume variance | ||
Budgeted fixed overhead | $2,393,600.00 | |
Fixed overhead cost applied | $2,692,800.00 | |
Fixed overhead volume variance | $299,200.00 | F |
Required information Use the following information for the Problems below. The following information applies to the q...
Required information Use the following information for the Problems below. [The following information applies to the questions displayed below.) Trico Company set the following standard unit costs for its single product. Direct materials (30 Ibs. @ $4.40 per Ib.) Direct labor (6 hrs. @ $14 per hr.) Factory overhead-variable (6 hrs. @ $8 per hr.) Factory overhead-fixed (6 hrs. @ $12 per hr.) Total standard cost $132.00 84.00 48.00 72.00 $336.00 The predetermined overhead rate is based on a planned...
100 points Required information Use the following information for the Problems below. The following information applies to the questions displayed below.] Trico Company set the following standard unit costs for its single product. eBook Direct materials (30 Ibs. $4.90 per Ib.) Direct labor (4 hrs. @ $16 per hr.) Factory overhead Variable (4 hrs. $6 per hr.) Factory overhead-Pixed (4 hrs. @ $10 per hr.) Total standard cost $147.00 64.00 24.00 40.00 $275.00 Print References The predetermined overhead rate is...
Use the following information for the Problems below. (The following information applies to the questions displayed below.) Trico Company set the following standard unit costs for its single product. Direct materials (30 Ibs. @ $4.40 per Ib.) Direct labor (6 hrs. @ $14 per hr.) Factory overhead-variable (6 hrs. @ $9 per hr.) Factory overhead-fixed (6 hrs. @ $12 per hr.) Total standard cost $132.00 84.00 54.00 72.00 $342.00 $372.00 The predetermined overhead rate is based on a planned operating...
Required information Use the following information for the Problems below. The following information applies to the questions displayed below.] Trico Company set the following standard unit costs for its single product. Direct materials (30 lbs. @ $4 per Ib.) Direct labor (5 hrs. @ $14 per hr.) Factory overhead-Variable (5 hrs. @ $8 per hr.) Factory overhead-Fixed (5 hrs. @ $10 per hr.) Total standard cost $120.00 70.00 40.00 50.00 $280.00 The predetermined overhead rate is based on a planned...
Required information Use the following information for the Problems below. [The following information applies to the questions displayed below.] Trico Company set the following standard unit costs for its single product. Direct materials (30 lbs. @ $4.00 per Ib.) Direct labor (7 hrs. @ $14 per hr.) Factory overhead-variable (7 hrs. @ $7 per hr.) Factory overhead-fixed (7 hrs. @ $11 per hr.) Total standard cost $120.00 98.00 49.00 77.00 $344.00 The predetermined overhead rate is based on a planned...
Required information The following information applies to the questions displayed below] Trico Company set the following standard unit costs for its single product. Direct materials (30 Ibs. $4.80 per 1b.) Direct labor (6 hrs. e $14 per hr.) Factory overhead-variable (6 hrs.e $7 per hr.) Factory overhead-fixed (6 hrs. e $12 per hr.) $144.00 84.00 42.00 72.00 Total standard cost $342.00 The predetermined overhead rate is based on a planned operating volume of 80 % of the productive capacity of...
Required information Use the following information for the Problems below. [The following information applies to the questions displayed below.] Trico Company set the following standard unit costs for its single product. Direct materials (30 lbs. @ $4.80 per Ib.) Direct labor (8 hrs. @ $16 per hr.) Factory overhead-variable (8 hrs. @ $9 per hr.) Factory overhead-fixed (8 hrs. @ $12 per hr.) Total standard cost $ 144.00 128.00 72.00 96.00 $ 440.00 The predetermined overhead rate is based on...
do 1-3 Required information Use the following information for the Problems below. The following information applies to the questions displayed below.) Trico Company set the following standard unit costs for its single product Direct materials (30 lbs. @ $4.90 per Ib.) Direct labor (4 hrs. @ $16 per hr.) Factory overhead-Variable (4 hrs. @ $6 per hr.) Factory overhead-Fixed (4 hrs. @ $10 per hr.) Total standard cost $147.00 64.00 24.00 40.00 $275.00 The predetermined overhead rate is based on...
Need help with the following accounting problem. Required information Use the following information for the Problems below. [The following information applies to the questions displayed below.) Trico Company set the following standard unit costs for its single product. Direct materials (30 Ibs. @ $5.00 per Ib.) Direct labor (7 hrs. @ $14 per hr.) Factory overhead-variable (7 hrs. @ $7 per hr.) Factory overhead-fixed (7 hrs. @ $9 per hr.) Total standard cost $150.00 98.00 49.00 63.00 $360.00 The predetermined...
[The following information applies to the questions displayed below.] Trico Company set the following standard unit costs for its single product. Direct materials (30 Ibs. @ $5.10 per Ib.) $ 153.00 Direct labor (8 hrs. @ $14 per hr.) 112.00 Factory overhead—variable (8 hrs. @ $6 per hr.) 48.00 Factory overhead—fixed (8 hrs. @ $12 per hr.) 96.00 Total standard cost $ 409.00 The predetermined overhead rate is based on a planned operating volume of 80% of the productive capacity...