Question

[The following information applies to the questions displayed below.]

Trico Company set the following standard unit costs for its single product.

Direct materials (30 Ibs. @ $5.10 per Ib.) $ 153.00
Direct labor (8 hrs. @ $14 per hr.) 112.00
Factory overhead—variable (8 hrs. @ $6 per hr.) 48.00
Factory overhead—fixed (8 hrs. @ $12 per hr.) 96.00
Total standard cost $ 409.00


The predetermined overhead rate is based on a planned operating volume of 80% of the productive capacity of 52,000 units per quarter. The following flexible budget information is available.

Operating Levels
70% 80% 90%
Production in units 36,400 41,600 46,800
Standard direct labor hours 291,200 332,800 374,400
Budgeted overhead
Fixed factory overhead $ 3,993,600 $ 3,993,600 $ 3,993,600
Variable factory overhead $ 1,747,200 $ 1,996,800 $ 2,246,400


During the current quarter, the company operated at 90% of capacity and produced 46,800 units of product; actual direct labor totaled 370,400 hours. Units produced were assigned the following standard costs.

Direct materials (1,404,000 Ibs. @ $5.10 per Ib.) $ 7,160,400
Direct labor (374,400 hrs. @ $14 per hr.) 5,241,600
Factory overhead (374,400 hrs. @ $18 per hr.) 6,739,200
Total standard cost $ 19,141,200


Actual costs incurred during the current quarter follow.

Direct materials (1,385,000 Ibs. @ $6.70 per lb.) $ 9,279,500
Direct labor (370,400 hrs. @ $11.50 per hr.) 4,259,600
Fixed factory overhead costs 3,196,600
Variable factory overhead costs 3,016,800
Total actual costs $ 19,752,500

Problem 21-4A Computation of materials, labor, and overhead variances LO P2, P3

Required:
1. Compute the direct materials cost variance, including its price and quantity variances.

AQ = Actual Quantity
SQ = Standard Quantity
AP = Actual Price
SP = Standard PriceActual Cost Standard CostActual Cost Standard CostControllable Variance Actual overhead Budgeted overhead Controllable varianceFixed overhead volume variance Budgeted fixed overhead Fixed overhead cost applied Fixed overhead volume variance

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Please note that I have solved all the required variances for your reference. Additionally I have also provided you the different formula that can be used for calculating variances.

Variable Overhead Total Variance@ (Standard Variable Overheads for Production - Actual Variable Overheads) Variable OverheadDirect Labour Variances Direct Labour Total Variance (Standard Cost? - Actual Cost] (The difference between the Standard DireFormulae Direct Material Variances Direct Material Total Variance [Standard Cost - Actual Cost] (The difference between the SVariable Overhead Cost Variance = (Standard Rate * Standard Hours) -* (Actual Rate * Actual Hours) Standard Hours Standard RaActual Hours 370400 Actual Rate 11.5 14 Standard Hours Standard Rate 374400 |(46800*8) Labour Cost Variance = (Standard HoursActual Qty Actual Price 1385000 6.7| 5.1 Material Cost Variance = (Standard Qty * Standard Price) - (Actual Qty * Actual PricGiven Information in Question Standard Cost Information Direct Material Direct labour Vraible Manufacturing Overhead Fixed Maall

Add a comment
Know the answer?
Add Answer to:
[The following information applies to the questions displayed below.] Trico Company set the following standard unit...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • [The following information applies to the questions displayed below.] Trico Company set the following standard unit...

    [The following information applies to the questions displayed below.] Trico Company set the following standard unit costs for its single product. Direct materials (30 Ibs. @ $5.10 per Ib.) Direct labor (8 hrs. @ $15 per hr.) Factory overhead-variable (8 hrs. @ $6 per hr.) Factory overhead-fixed (8 hrs. @ $9 per hr.) Total standard cost $153.00 120.00 48.00 72.00 $393.00 The predetermined overhead rate is based on a planned operating volume of 80% of the productive capacity of 65,000...

  • [The following information applies to the questions displayed below.] Trico Company set the following standard unit...

    [The following information applies to the questions displayed below.] Trico Company set the following standard unit costs for its single product. Direct materials (30 Ibs. @ $5.10 per Ib.) $ 153.00 Direct labor (4 hrs. @ $15 per hr.) 60.00 Factory overhead—variable (4 hrs. @ $6 per hr.) 24.00 Factory overhead—fixed (4 hrs. @ $11 per hr.) 44.00 Total standard cost $ 281.00 The predetermined overhead rate is based on a planned operating volume of 80% of the productive capacity...

  • Required information The following information applies to the questions displayed below] Trico Company set the following...

    Required information The following information applies to the questions displayed below] Trico Company set the following standard unit costs for its single product. Direct materials (30 Ibs. $4.80 per 1b.) Direct labor (6 hrs. e $14 per hr.) Factory overhead-variable (6 hrs.e $7 per hr.) Factory overhead-fixed (6 hrs. e $12 per hr.) $144.00 84.00 42.00 72.00 Total standard cost $342.00 The predetermined overhead rate is based on a planned operating volume of 80 % of the productive capacity of...

  • The following information applies to the questions displayed below.] Trico Company set the following standard unit...

    The following information applies to the questions displayed below.] Trico Company set the following standard unit costs for its single product. Direct materials (30 Ibs. @ $5.00 per Ib.) $ 150.00 Direct labor (7 hrs. @ $14 per hr.) 98.00 Factory overhead—variable (7 hrs. @ $7 per hr.) 49.00 Factory overhead—fixed (7 hrs. @ $9 per hr.) 63.00 Total standard cost $ 360.00 The predetermined overhead rate is based on a planned operating volume of 80% of the productive capacity...

  • Trico Company set the following standard unit costs for its single product.      Direct materials (29...

    Trico Company set the following standard unit costs for its single product.      Direct materials (29 Ibs. @ $3 per Ib.) $ 87.00   Direct labor (6 hrs. @ $6 per hr.) 36.00   Factory overhead—variable (6 hrs. @ $4 per hr.) 24.00   Factory overhead—fixed (6 hrs. @ $5 per hr.) 30.00      Total standard cost $ 177.00    The predetermined overhead rate is based on a planned operating volume of 70% of the productive capacity of 60,000 units per quarter. The...

  • please assist with the information provided: Trico Company set the following standard unit costs for its...

    please assist with the information provided: Trico Company set the following standard unit costs for its single product. Direct materials (30 Ibs. @ $4.40 per Ib.) Direct labor (6 ha. @ $14 per hr.) Factory overhead-variable (6 hrs. @ $8 per hr.) Factory overhead-fixed 16 hrs. @ $11 per hr.) Total standard cost $132.00 84.00 48.00 66.00 $330.00 The predetermined overhead rate is based on a planned operating volume of 80% of the productive capacity of 60,000 units per quarter....

  • Trico Company set the following standard unit costs for its single product. Direct materials (30 Ibs....

    Trico Company set the following standard unit costs for its single product. Direct materials (30 Ibs. @ $4.80 per Ib.) $ 144.00 Direct labor (7 hrs. @ $14 per hr.) 98.00 Factory overhead—variable (7 hrs. @ $6 per hr.) 42.00 Factory overhead—fixed (7 hrs. @ $9 per hr.) 63.00 Total standard cost $ 347.00 The predetermined overhead rate is based on a planned operating volume of 80% of the productive capacity of 64,000 units per quarter. The following flexible budget...

  • Use the following information for the Problems below. (The following information applies to the questions displayed...

    Use the following information for the Problems below. (The following information applies to the questions displayed below.) Trico Company set the following standard unit costs for its single product. Direct materials (30 Ibs. @ $4.40 per Ib.) Direct labor (6 hrs. @ $14 per hr.) Factory overhead-variable (6 hrs. @ $9 per hr.) Factory overhead-fixed (6 hrs. @ $12 per hr.) Total standard cost $132.00 84.00 54.00 72.00 $342.00 $372.00 The predetermined overhead rate is based on a planned operating...

  • Trico Company set the following standard unit costs for its single product. Direct materials (30 Ibs....

    Trico Company set the following standard unit costs for its single product. Direct materials (30 Ibs. @ $5.10 per Ib.) $ 153.00 Direct labor (8 hrs. @ $14 per hr.) 112.00 Factory overhead—variable (8 hrs. @ $6 per hr.) 48.00 Factory overhead—fixed (8 hrs. @ $12 per hr.) 96.00 Total standard cost $ 409.00 The predetermined overhead rate is based on a planned operating volume of 80% of the productive capacity of 66,000 units per quarter. The following flexible budget...

  • please answer in given format. yes, this is one question. Trico Company set the following standard...

    please answer in given format. yes, this is one question. Trico Company set the following standard unit costs for its single product. Direct materials (30 Ibs. @ $4.40 per Ib.) Direct labor (6 hrs. @ $14 per hr.) Factory overhead-variable (6 hrs. @ $8 per hr.) Factory overhead-fixed (6 hrs. @ $11 per hr.) Total standard cost $132.00 84.00 48.00 66.00 $330.00 The predetermined overhead rate is based on a planned operating volume of 80% of the productive capacity of...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT