Question

26. Problems with IRR A project has the following cash flows: 13.16% @ 12%: -$1,051.02 @0%: -$14,000 @ 24%: $8,588.97 Year Ca

0 0
Add a comment Improve this question Transcribed image text
Answer #1
CF
IRR is the rate at which NPV =0
IRR 0.131554826
Year 0 1 2
Cash flow stream 64000 -30000 -48000
Discounting factor 1 1.131555 1.280416
Discounted cash flows project 64000 -26512.2 -37487.8
NPV = Sum of discounted cash flows
NPV CF = -2.72469E-06
Where
Discounting factor = (1 + IRR)^(Corresponding period in years)
Discounted Cashflow= Cash flow stream/discounting factor
IRR= 13.16%
Reject project as IRR is more than discount rate
CF
Discount rate 0.12
Year 0 1 2
Cash flow stream 64000 -30000 -48000
Discounting factor 1 1.12 1.2544
Discounted cash flows project 64000 -26785.7 -38265.3
NPV = Sum of discounted cash flows
NPV CF = -1051.02
Where
Discounting factor = (1 + discount rate)^(Corresponding period in years)
Discounted Cashflow= Cash flow stream/discounting factor
Reject project as NPV is negative
Add a comment
Know the answer?
Add Answer to:
26. Problems with IRR A project has the following cash flows: 13.16% @ 12%: -$1,051.02 @0%:...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • A project has the following cash flows: 0 $70,000 48,000 -30,000 a. What is the IRR...

    A project has the following cash flows: 0 $70,000 48,000 -30,000 a. What is the IRR for this project? (Do not round intermediate calculations and enter your answer as a percent rounded to 2 decimal places, e.g., 32.16.) b. What is the NPV of this project if the required return is 5 percent? (A negative answer should be indicated by a minus sign. Do not round intermediate calculations and round your answer to 2 decimal places, e.g., 32.16.) c. What...

  • Vital Silence, Inc., has a project with the following cash flows:     Year Cash Flow 0...

    Vital Silence, Inc., has a project with the following cash flows:     Year Cash Flow 0 –$ 27,400 1 11,400 2 14,400 3 10,400    The required return is 16 percent. What is the IRR for this project? (Do not round intermediate calculations and enter your answer as a percent rounded to 2 decimal places, e.g., 32.16.)   IRR % Should the firm accept the project? Accept Reject

  • A project has the following cash flows: year. Cash flow 0. $71,000 1. -50,000. 2. -29,200...

    A project has the following cash flows: year. Cash flow 0. $71,000 1. -50,000. 2. -29,200 a. What is the IRR for the project? (Do not round intermediate calculations and enter answer as a percent round to 2 decimal places) b. What is the NPV of this project if the required return is 6 percent? c. What is the NPV of the project if the required return is 0 percent? d. What is the NPV of the project if the...

  • Vital Silence, Inc., has a project with the following cash flows Year Cash Flow 0 28,600...

    Vital Silence, Inc., has a project with the following cash flows Year Cash Flow 0 28,600 12,600 15,600 11,600 The required return is 14 percent. What is the IRR for this project? (Do not round intermediate calculations and enter your answer as a percent rounded to 2 decimal places, e.g., 32.16.) IRR Should the firm accept the project? O Accept ○ Reject References eBook & Resources Section: 5 Worksheet Difficulty: 1 Basic

  • Consider Project Theta, its time line of cash flows, and one of the project IRRs: Year....................0.............1............2............IRR...

    Consider Project Theta, its time line of cash flows, and one of the project IRRs: Year....................0.............1............2............IRR Cash Flow......($200).....$850....($700)......15% What is the best decision for Project Theta (accept or reject) if the project’s required rate of return is 15% and why? a. Accept the project because the payback is short b. Accept the project because the NPV is greater than zero c. Reject the project because the IRR is less than the required rate of return d. Reject the project because...

  • 3. You are considering two mutually exclusive projects with the following cash flows. Which project(s) should...

    3. You are considering two mutually exclusive projects with the following cash flows. Which project(s) should you accept if the discount rate is 8.5 percent? What if the discount rate is 13 percent? Year Project A Project B -$80,000 -$80,000 31,000 31,000 0 31,000 110,000 A. accept project A as it always has the higher NPV B. accept project B as it always has the higher NPV C. accept A at 8.5 percent and B at 13 percent D. accept...

  • A firm evaluates all of its projects by applying the IRR rule. A project under consideration has the following cash...

    A firm evaluates all of its projects by applying the IRR rule. A project under consideration has the following cash flows: points Year Cash Flow 0 29.000 13,000 16.000 12.000 eBook References If the required return is 15 percent. what is the IRR for this project? (Do not round intermediate calculations. Enter your answer as a percent rounded to 2 decimal places, e.g. 32.16.) IRR % Should the firm accept the project?

  • Please help and solve this. Please do NOT use excel. Please do NOT show in excel....

    Please help and solve this. Please do NOT use excel. Please do NOT show in excel. Please SHOW ALL work and formulas. Please show step by step. Please keep it neat and organized. Thank you. A project has the following cash flows:    Year Cash Flow 0 $64,000        1 –30,000        2 –48,000          Required: (a) What is the IRR for this project? (Click to select)  13.42%  12.63%  13.82%  13.16%  12.9%    (b) What is the NPV of this project, if the required...

  • Consider Project Theta, its time line of cash flows, and one of the project IRRs: Year...................0..............1...............2...........IRR...

    Consider Project Theta, its time line of cash flows, and one of the project IRRs: Year...................0..............1...............2...........IRR Cash Flow.....($200).....$850.......($700).......15% What is the best decision for Project Theta (accept or reject) if the project’s required rate of return is 15% and why? a. Reject the project because the NPV is less than zero b. Accept the project because the IRR is greater than zero c. Accept the project because the NPV is greater than zero d. Accept the project because the payback...

  • A firm evaluates all of its projects by applying the IRR rule. A project under consideration...

    A firm evaluates all of its projects by applying the IRR rule. A project under consideration has the following cash flows: 0 Year Cash Flow $27,000 11,000 14,000 10,000 6.66 points eBook If the required return is 16 percent, what is the IRR for this project? (Do not round intermediate calculations and enter your answer as a percent rounded to 2 decimal places, e.g., 32.16.) Print References IRR Should the firm accept the project? Yes No

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT