Year | Cash Flows | Cumulative cash flows | Investment still to be covered |
0 | -$1,500 | - | ($1,500) |
1 | $500 | $500 | ($1,000) |
2 | $500 | $1,000 | ($500) |
3 | $1,500 | $2,500 | $1,000 |
So, Investment was completely covered in the 3rd year
Payback period = Year before investment covered + [Investment still to be covered/Cash flows @3rd yr]
Payback period = 2 year + [$500 / $1,500]
Payback period = 2 year + 0.33 year
Payback period = 2.33 year
or Payback period = 2.3 year (rounded off to '1' decimal)
Option 'D' is correct
QUESTION 1 Given the following cash flows for project A: Co = -1,500, C1 = 500,...
A project has the following cash flows. Co C1 C2 C3 ($700) $200 $500 $244 a. What is the project's payback period? Round the answer to two decimal places. 2 V year(s) b. Calculate the project's NPV at 9%. Do not round intermediate calculations. Round PVF and PVFA values in intermediate calculations to four decimal places. Round the answer to two decimal places C. Calculate the project's PI at 9%. Do not round intermediate calculations. Round PVF and PVFA values...
Consider the following project Cash flows Cash flows Cash flows Projects CO C1 C2 A -30 20 20 What is the IRR of the project? A) 11.53% B) 21.53% C) 23.15% OD) 33.15%
cash flows project C0 C1 C2 C3 C4 C5 A -1,000 1,000 0 0 0 0 B -2,000 1,000 1,000 1,000 0 0 C -3,000 1,000 1,000 0 1000 1,000 a) If the opportunity cost of capital is 11 percent, which projects have a positive NPV? b) Calculate the payback period for each project. c) Which project(s) would a firm using the payback rule accept if the cutoff period is three years?
Here are the cash flows for two mutually exclusive projects: Project Co C1 $ 39,200 +$15,700 - 39,2000 C2 +$15,700 0 C3 +$ 15,700 + 49,200 B a. Given the following interest rates (0%, 2%, 4%, 6%, 8%, 10%, 12%, 14%, 16%, 18%, 20%), above what interest rates would you prefer project A to B? Interest rates above % b. What is the IRR of each project? (Round your answers to 2 decimal places.) Project Project B IRR %
A project has the following cash flows: Year Cash Flow0 -$4,2001 1,9002 1,8003 1,6004 500 a) Calculate the payback period of the project. b) If the cutoff period is three years, should this project be accepted? Why or why not?
A project has the following cash flows: Year Cash Flow -$4,200 1,900 1,800 1,600 500 Calculate the payback period of the project. (2 points) If the cutoff period is three years, should this project be accepted? Why or why not? (2 points)
Consider the following cash flows: co $24. C1 +$21 C2 +$21 C3 +$21 CA $41 a. Which two of the following rates are the IRRs of this project? (You may select more than one answer. Single click the box with the question mark to produce a check mark for a correct answer and double click the box with the question mark to empty the box for a wrong answer. Any boxes left with a question mark will be automatically graded...
1. You have the chance to participate in a project that produces the following cash flows: Cash Flows ($) C0 C1 C2 4,600 4,400 –10,800 a. The internal rate of return is 12.69%. If the opportunity cost of capital is 12%, what is the NPV of the project? (A negative answer should be indicated by a minus sign. Do not round intermediate calculations. Round your answer to 2 decimal places.) NPV $ __________. 2. Consider the following projects: Cash Flows...
A project has the following forecasted cash flows: Cash flows C0 C1 C2 C3 (100) 40 60 50 The estimated project beta is 1.5. The market return r m is 16%, and the risk-free rate r f is 7%. a. Estimate the opportunity cost of capital and the project’s PV (using the same rate to discount each cash flow). b. What are the certainty-equivalent cash flows in each year? c. What is the ratio of the certainty-equivalent cash flow to...
A project has the following forecasted cash flows: Cash flows C0 C1 C2 C3 (100) 40 60 50 The estimated project beta is 1.5. The market return r m is 16%, and the risk-free rate r f is 7%. a. Estimate the opportunity cost of capital and the project’s PV (using the same rate to discount each cash flow). b. What are the certainty-equivalent cash flows in each year? c. What is the ratio of the certainty-equivalent cash flow to...