rate positively .
Year | Cash flow | ||||||||
0 | -24 | ||||||||
1 | 21 | ||||||||
2 | 21 | ||||||||
3 | 21 | ||||||||
4 | -41 | ||||||||
Ans a) | IRR 1 = | 8.1% | |||||||
IRR 2 = | 27.6% | ||||||||
And b to d | |||||||||
Year | Cash flow | PVIF @ 6% | PVIF @ 18% | PVIF @ 36% | Present value @ 6% | Present value @ 18% | Present value @ 36% | ||
0 | -24 | 1 | 1 | 1 | (24.000) | (24.000) | (24.000) | ||
1 | 21 | 0.943396 | 0.8474576 | 0.7352941 | 19.811 | 17.797 | 15.441 | ||
2 | 21 | 0.889996 | 0.7181844 | 0.5406574 | 18.690 | 15.082 | 11.354 | ||
3 | 21 | 0.839619 | 0.6086309 | 0.3975422 | 17.632 | 12.781 | 8.348 | ||
4 | -41 | 0.792094 | 0.5157889 | 0.2923105 | (32.476) | (21.147) | (11.985) | ||
(0.343) | 0.512 | (0.841) | |||||||
Ans b . | NPV | (0.343) | |||||||
Ans c . | NPV | 0.512 | |||||||
Ans d . | NPV | (0.841) |
Consider the following cash flows: co $24. C1 +$21 C2 +$21 C3 +$21 CA $41 a....
Consider the following cash flows: CA co 45 G +$41 C2 +$41 C3 +$41 a. Which two of the following rates are the IRRs of this project? (You may select more than one answer. Single click the box with the question mark to produce a check mark for a correct answer and double click the box with the question mark to empty the box for a wrong answer. Any boxes left with a question mark will be automatically graded as...
Consider the following cash flows: Ce C1 C2 C3 C4 +$37 +$37 +$37 $41 $74 a. Which two of the following rates are the IRRS of this project? (You may select more than one answer. Single click the box with the question mark to produce a check mark for a correct answer and double click the box with the question mark to empty the box for a wrong answer. Any boxes left with a question mark will be automatically graded...
A project has the following cash flows. Co C1 C2 C3 ($700) $200 $500 $244 a. What is the project's payback period? Round the answer to two decimal places. 2 V year(s) b. Calculate the project's NPV at 9%. Do not round intermediate calculations. Round PVF and PVFA values in intermediate calculations to four decimal places. Round the answer to two decimal places C. Calculate the project's PI at 9%. Do not round intermediate calculations. Round PVF and PVFA values...
Project A B Co A $ 24,800 - 24,800 C1 +$ 9,850 C2 +$9,850 0 C3 +$ 9,850 + 31,200 a. Given the following interest rates (0%, 2%, 4%, 6%, 8%, 10%, 12%, 14%, 16%, 18%, 20%), above what interest rates would you prefer project A to B? Interest rates above [ 1% b. What is the IRR of each project? (Round your answers to 2 decimal places.) IRR Project T % Project B %
Consider two mutually exclusive projects A and B: Cash Flows (dollars) Project C0 C1 C2 NPV at 11% A −36,500 26,200 26,200 +$8,368 B −56,500 39,500 39,500 +11,145 a. Calculate IRRs for A and B. (Do not round intermediate calculations. Enter your answers as a percent rounded to 2 decimal places.) b. Which project does the IRR rule suggest is best? Project A Project B c. Which project is really best?
A project has the following forecasted cash flows: Cash flows C0 C1 C2 C3 (100) 40 60 50 The estimated project beta is 1.5. The market return r m is 16%, and the risk-free rate r f is 7%. a. Estimate the opportunity cost of capital and the project’s PV (using the same rate to discount each cash flow). b. What are the certainty-equivalent cash flows in each year? c. What is the ratio of the certainty-equivalent cash flow to...
A project has the following forecasted cash flows: Cash flows C0 C1 C2 C3 (100) 40 60 50 The estimated project beta is 1.5. The market return r m is 16%, and the risk-free rate r f is 7%. a. Estimate the opportunity cost of capital and the project’s PV (using the same rate to discount each cash flow). b. What are the certainty-equivalent cash flows in each year? c. What is the ratio of the certainty-equivalent cash flow to...
Here are the cash flows for two mutually exclusive projects: Project Co C1 $ 39,200 +$15,700 - 39,2000 C2 +$15,700 0 C3 +$ 15,700 + 49,200 B a. Given the following interest rates (0%, 2%, 4%, 6%, 8%, 10%, 12%, 14%, 16%, 18%, 20%), above what interest rates would you prefer project A to B? Interest rates above % b. What is the IRR of each project? (Round your answers to 2 decimal places.) Project Project B IRR %
Exercise 21-1 Management by exception LO C1 Resset Co. provides the following results of April's operations: F indicates favorable and U indicates unfavorable. In applying management by exception, the company investigates all variances of $400 or more. Direct materials price variance Direct materials quantity variance $ 300 F Direct labor efficiency variance Controllable overhead variance Fixed overhead volume variance $2,200 F 400 U s00 F 3,000 U Direct labor rate variance 100 U Which variances will the company investigate? (You...
Consider the following cash flows: Cash Flows ($) CO С1 -7,750 5,500 20,000 a. Calculate the net present value of the above project for discount rates of 0, 50, and 100%. (Do not round intermediate calculations. Round your answers to the nearest whole dollar amount.) NPV 0% NPV @50% NPV @100% b. What is the IRR of the project? (Do not round intermediate calculations. Enter your answer as a percent rounded to the nearest whole number.) IRR