Question

Exercise 21-1 Management by exception LO C1 Resset Co. provides the following results of Aprils operations: F indicates favo
0 0
Add a comment Improve this question Transcribed image text
✔ Recommended Answer
Answer #1

rate positively .

Correct answer are option- because they are more than 400 variance item
Direct material quantity variance
Direct labor effeciency variance
Controllable overhead variance
Fixed overhead volume variance
Add a comment
Know the answer?
Add Answer to:
Exercise 21-1 Management by exception LO C1 Resset Co. provides the following results of April's operations:...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Similar Homework Help Questions
  • 10. Abrams, Inc., provides the following results of March's operations: Direct materials price variance ... Direct...

    10. Abrams, Inc., provides the following results of March's operations: Direct materials price variance ... Direct materials quantity variance .......... Direct labor rate variance ............. Direct labor efficiency variance .............. Variable overhead spending variance ...... Variable overhead efficiency variance Fixed overhead spending variance Fixed overhead volume variance ....... $ 400F 2,000U 100U 1,200F 400U 800F 100U 600F Required: (a) Determine the total overhead cost variance for March. (b) Applying the management by exception approach, which of the variances shown are...

  • 1.Which of the following is true about "management by exception"? It requires managers to investigate all...

    1.Which of the following is true about "management by exception"? It requires managers to investigate all favorable and unfavorable variances. It requires the use of variance analysis. It rarely requires the use of variance analysis. It requires managers to calculate standard costs, but ignore actual costs. None of the answer choices is correct. 2.Which of the following is most likely to cause an unfavorable direct materials quantity variance? Low quality materials increased waste of materials. High quality materials reduced waste...

  • X Data Table 1 Standard Cost Information Quantity Cost 0.15 per part Direct Materials 2 parts...

    X Data Table 1 Standard Cost Information Quantity Cost 0.15 per part Direct Materials 2 parts 0.02 hours Direct Labor 9.00 per hour Variable Manufacturing Overhead 0.02 hours 9.00 per hour Fixed Manufacturing Overhead ($31,360 for static budget volume of 98,000 units and 1,960 hours, or $16 per hour) Actual Cost Information $ 0.20 per part) $ 42,200 (211,000 parts@ Direct Materials $ 9.15 per hour) Direct Labor (1,660 hours@ 15,189 Variable Manufacturing Overhead 10,000 Fixed Manufacturing Overhead 30,000 Print...

  • Pepper Industries uses a standard cost accounting system. During March, 2019, the company reported the following...

    Pepper Industries uses a standard cost accounting system. During March, 2019, the company reported the following manufacturing variances: Materials price variance $1,600 F Materials quantity variance 2,400 U Labor price variance 600 U Labor quantity variance 2,200 U Overhead controllable 500 F Overhead volume 3,000 U In addition, 15,000 units of product were sold at $18 per unit. Each unit sold had a standard cost of $14. Selling and administrative expenses for the month were $15,000. Prepare an income statement...

  • Which of the following standard cost variances would usually be least controllable by a production supervisor?...

    Which of the following standard cost variances would usually be least controllable by a production supervisor? Multiple Choice Fixed overhead volume variance Variable overhead efficiency variance Direct labor efficiency variance Materials usage (quantity) variance

  • The management of Zeta Fire Alarms has calculated the following variances: Direct materials cost variance Direct...

    The management of Zeta Fire Alarms has calculated the following variances: Direct materials cost variance Direct materials efficiency variance Direct labor cost variance Direct labor efficiency variance Total variable overhead variance Total fixed overhead variance $9,000 U 35,000 F 16,500 F 13,000 U 8,000 F 3,500 F What is the total direct materials variance of the company? O A. $11,500 F OB. $7,500 F OC. $26,000 F O D. $3,500 F

  • Downton Company manufactures two products, Abby and Mansion. The company prepares its master budget on the...

    Downton Company manufactures two products, Abby and Mansion. The company prepares its master budget on the basis of standard costs. The following data are for January: Standards Abby Mansion Direct materials 3 ounces at $14.50 per ounce 4 ounces at $17.30 per ounce Direct labor 5 hours at $60.50 per hour 6 hours at $81.00 per hour Variable overhead (per direct labor-hour) $48.00 $53.50 Fixed overhead (per month) $368,068 $399,360 Expected activity (direct labor-hours) 6,680 7,800 Actual results Direct material...

  • select from formulas given above Headsound manufactures headphone cases. During September 2018, the company produced and...

    select from formulas given above Headsound manufactures headphone cases. During September 2018, the company produced and sold 108,000 cases and recorded the following cost data: (Click the icon to view the cost data) Read the requirements. Requirement 1. Compute the cost and efficiency variances for direct materials and direct labor. Begin with the cost variances. Select the required formulas, compute the cost variances for direct materials and direct labor, and identify whether each variance is favorable (F) or unfavorable (U)....

  • Ander's Clothing manufactures embroidered jackets. The company uses a standard cost system to control manufacturing costs....

    Ander's Clothing manufactures embroidered jackets. The company uses a standard cost system to control manufacturing costs. The following data represent the standard unit cost of a​ jacket:   i Data Table $4.15 per sq. ft.) Direct materials 3.0 sq. ft x 12.45 Direct labor $9.70 per hour) ( 2,0 hours x 19.40 Manufacturing overhead: Variable 2.0 hours x $0.68 per hour) 1.36 4.40 5.76 2.0 hours x $2.20 per hour) Fixed 37.61 Total standard cost per jacket Fixed overhead in total...

  • Required information Use the following information for the Problems below. The following information applies to the...

    Required information Use the following information for the Problems below. The following information applies to the questions displayed below.] Trico Company set the following standard unit costs for its single product. Direct materials (30 lbs. @ $4 per Ib.) Direct labor (5 hrs. @ $14 per hr.) Factory overhead-Variable (5 hrs. @ $8 per hr.) Factory overhead-Fixed (5 hrs. @ $10 per hr.) Total standard cost $120.00 70.00 40.00 50.00 $280.00 The predetermined overhead rate is based on a planned...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT