Question

1.Which of the following is true about "management by exception"? It requires managers to investigate all...

1.Which of the following is true about "management by exception"?

It requires managers to investigate all favorable and unfavorable variances.

It requires the use of variance analysis.

It rarely requires the use of variance analysis.

It requires managers to calculate standard costs, but ignore actual costs.

None of the answer choices is correct.

2.Which of the following is most likely to cause an unfavorable direct materials quantity variance?

Low quality materials increased waste of materials.

High quality materials reduced waste of materials.

New production techniques reduced waste of materials.

Improved maintenance of production equipment reduced waste of materials.

None of the answer choices is correct.

3.If Ever Green Corporation has an unfavorable fixed overhead spending variance, which of the following would most likely be the reason for this variance?

Actual fixed overhead was less than predicted.

More units were actually produced than predicted.

Actual fixed overhead was more than predicted.

Fewer units were actually produced than predicted.

None of the answer choices is correct.

4.Colfax Company incurred production labor costs of $5,400 in February (payable in March) for work requiring 1,100 standard hours at a standard rate of $15 per hour; 1,200 actual direct labor hours were worked. Based on this information, which one of the following would be included in the journal entry to record the labor costs?

$16,500 credit to Work-in-process Inventory.

$1,500 credit to Labor Efficiency Variance.

$16,200 credit to Wages Payable.

$1,500 credit to Labor Rate Variance.

None of the answer choices is correct

5.If a company has a favorable materials quantity variance of $3,300, the journal entry to record the use of direct materials in production along with this related quantity variance would include:

a credit to Materials Quantity Variance.

a credit to Materials Price Variance.

a debit to Materials Quantity Variance.

a debit to Materials Price Variance.

None of the answer choices is correct.

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Answer to first question in the list: Option-(b): It requires the use of variance analysis Reason: Option-(b) is correct beca

Add a comment
Know the answer?
Add Answer to:
1.Which of the following is true about "management by exception"? It requires managers to investigate all...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • A. The standard costs and actual costs for direct materials for the manufacture of 2,240 actual...

    A. The standard costs and actual costs for direct materials for the manufacture of 2,240 actual units of product are as follows: Standard Costs Direct materials 2,240 kilograms @$8.60 Actual Costs Direct materials 2,300 kilograms The direct materials quantity variance is? Choose the correct answer below $413 favorable $516 unfavorable $516 favorable $413 unfavorable B. The following data relate to direct labor costs for the current period: Standard costs 7,200 hours at $11.30 Actual costs 6,400 hours at $10.80 What...

  • 1.Which of the following remains the same when comparing a flexible budget to a master budget?...

    1.Which of the following remains the same when comparing a flexible budget to a master budget? Total sales. Net income. Total variable costs. Total fixed costs. None of the answer choices is correct. 2.When ideal standards are used, which of the following is most likely true? The standards are not likely to be achieved. The standards allow for occasional downtime for equipment. The standards reflect what really happens in the factory. The standards motivate employees to achieve perfection. None of...

  • Mastery Problem: Manufacturing Cost Variance (Actual Costs Compared to Standard Costs) Manufacturing cost variances may come...

    Mastery Problem: Manufacturing Cost Variance (Actual Costs Compared to Standard Costs) Manufacturing cost variances may come from material costs that are higher or lower than expected, material usage that is not what was expected, higher or lower labor costs than expected, or more or less time spent to produce an item than expected. Overhead cost and volume variances are another cause for costs to be higher or lower than what was expected. The total manufacturing variance can be broken down...

  • 1) 2) 3) 4) 5) A favorable cost variance occurs when Oa. actual costs are the...

    1) 2) 3) 4) 5) A favorable cost variance occurs when Oa. actual costs are the same as standard costs Ob. actual costs are more than standard costs Oc. standard costs are more than actual costs Od. standard costs are less than actual costs The Flapjack Corporation had 8,042 actual direct labor hours at an actual rate of $12.00 per hour. Original production had been budgeted for 1,100 units, but only 999 units were actually produced. Labor standards were 7.9...

  • 1) Stefani Company has gathered the following information about its product. Direct materials: Each unit of...

    1) Stefani Company has gathered the following information about its product. Direct materials: Each unit of product contains 4.50 pounds of materials. The average waste and spoilage per unit produced under normal conditions is 1.50 pounds. Materials cost $3 per pound, but Stefani always takes the 5.00% cash discount all of its suppliers offer. Freight costs average $0.30 per pound. Direct labor. Each unit requires 1.70 hours of labor. Setup, cleanup, and downtime average 0.20 hours per unit. The average...

  • Direct Materials, Direct Labor, and Reports budgeted and actual costs for variable and fixed factory overhead...

    Direct Materials, Direct Labor, and Reports budgeted and actual costs for variable and fixed factory overhead along with the related controllable and volume variances.Factory Overhead Cost Variance Analysis Mackinaw Inc. processes a base chemical into plastic. A detailed estimate of what a product should cost.Standard costs and actual costs for direct materials, direct labor, and factory overhead incurred for the manufacture of 70,000 units of product were as follows: Standard Costs Actual Costs Direct materials 189,000 lbs. at $6.00 187,100...

  • Factory Overhead Cost Variances The following data relate to factory overhead cost for the production of...

    Factory Overhead Cost Variances The following data relate to factory overhead cost for the production of 6,000 computers: Actual: Variable factory overhead $170,200 Fixed factory overhead 57,500 Standard: 6,000 hrs. at $35 210,000 If productive capacity of 100% was 10,000 hours and the total factory overhead cost budgeted at the level of 6,000 standard hours was $233,000, determine the variable factory overhead controllable variance, fixed factory overhead volume variance, and total factory overhead cost variance. The fixed factory overhead rate...

  • Direct Materials, Direct Labor, and Factory Overhead Cost Variance Analysis Mackinaw Inc. processes a base chemical...

    Direct Materials, Direct Labor, and Factory Overhead Cost Variance Analysis Mackinaw Inc. processes a base chemical into plastic. Standard costs and actual costs for direct materials, direct labor, and factory overhead incurred for the manufacture of 5,200 units of product were as follows: Standard Costs Actual Costs Direct materials 6,800 lb. at $4.60 6,700 lb. at $4.40 Direct labor 1,300 hrs. at $18.10 1,330 hrs. at $18.50 Factory overhead Rates per direct labor hr., based on 100% of normal capacity...

  • Static Plexible Volume Purchasing manager Favorable Unfavorable Debit Credit Fixed overhead budget Fixed overhead volune Spending...

    Static Plexible Volume Purchasing manager Favorable Unfavorable Debit Credit Fixed overhead budget Fixed overhead volune Spending Production manager Variable overhead rate Variable overhead effieiency Fixed overhead spending Ixed overhead spending 1. A budget is based on a fixed estimate of sales volume. A volume 2. variance represents the difference between actual and expected levels of activity 3. The is typically responsible for the direct materials quantity variance The variable overhead rate variance is 4 when the actual variable overhead rate...

  • Exercise 21-1 Management by exception LO C1 Resset Co. provides the following results of April's operations:...

    Exercise 21-1 Management by exception LO C1 Resset Co. provides the following results of April's operations: F indicates favorable and U indicates unfavorable. In applying management by exception, the company investigates all variances of $400 or more. Direct materials price variance Direct materials quantity variance $ 300 F Direct labor efficiency variance Controllable overhead variance Fixed overhead volume variance $2,200 F 400 U s00 F 3,000 U Direct labor rate variance 100 U Which variances will the company investigate? (You...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT