Question

14) Switsdorf Company has the following information available for variable overhead costs. Direct labor hours are the cost dr

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Variable overhead efficiency variance

= (Standard hours - Actual hours) * standard voh rate

= (1,000*3 - 2,000) * 3

= (3,000 - 2,000) * 3

= 1,000 * 3

= 3,000 Favourable

Add a comment
Know the answer?
Add Answer to:
14) Switsdorf Company has the following information available for variable overhead costs. Direct labor hours are...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • 13) Dooley Company has the following information available for variable overhead costs. Direct labor hours are...

    13) Dooley Company has the following information available for variable overhead costs. Direct labor hours are the cost driver for variable overhead costs, Actual variable overhead costs Standard variable overhead costs Actual direct labor hours Standard direct labor hours per unit Units produced $4,700 $1.20 per hour 3,750 hours 5 hours 700 What is the variable overhead efficiency variance? A) $500 Favorable C) $300 Unfavorable B) $300 Favorable D) $500 Unfavorable

  • 12) Simmons Company has the following information available for variable overhead costs. Direct labor hours are...

    12) Simmons Company has the following information available for variable overhead costs. Direct labor hours are the cost driver for variable overhead costs. Actual variable overhead costs Standard variable overhead costs Actual direct labor hours Standard direct labor hours per unit Units produced $4,700 $1.20 per hour 3,750 hours 5 hours 700 What is the variable overhead spending variance? A) $200 Favorable C) $500 Favorable B) $500 Unfavorable D) $200 Unfavorable

  • Harrangue Company's standard variable overhead rate is $6 per direct labor hour, and each unit requires...

    Harrangue Company's standard variable overhead rate is $6 per direct labor hour, and each unit requires 2 standard direct labor hours. During March, Harry recorded 6,000 actual direct labor hours, $37,000 actual variable overhead costs, and 2,900 units of product manufactured. What is the variable overhead efficiency variance for March for Harrangue? a.$2,200 (U) b.$1,200 (U) c.$600 (U) d.$2,200 (F) Synergy Manufacturing Company has a normal monthly activity of 7,500 units. Standard factory overhead rates are based on a normal...

  • Willow Inc. has provided the following information: Standards: Direct materials Direct labor Variable overhead Fixed overhead...

    Willow Inc. has provided the following information: Standards: Direct materials Direct labor Variable overhead Fixed overhead Total Per unit 10 lbs @ $2.90/lb $ 29.00 2 hours @ $17.50/hour 35.00 2 hours @ $11/hour 22.00 25.00 $111.00 Budgeted production = 7,300 units 75,050 lbs 14,100 actual hours Actual results Materials Direct labor Variable overhead Fixed overhead Units produced $216,015 $236,815 $ 161,570 $179,860 7,500 units a. Calculate the direct materials price variance. (Do not round your intermediate calculations. Indicate the...

  • 1. Lee Manufacturing uses a standard cost system with overhead applied based on direct labor hours....

    1. Lee Manufacturing uses a standard cost system with overhead applied based on direct labor hours. The manufacturing budget for the production of 5,000 units for the month of May included the following information. Direct labor (10,000 hours at $15 per hour) $150,000 Variable overhead                                          $30,000 Fixed overhead                                                $80,000 During May, 6,000 units were produced and the direct labor efficiency variance was $1,500 unfavorable. Based on this information, the actual number of direct labor hours used in...

  • Beverly Company has determined a standard variable overhead rate of $3.70 per direct labor hour and...

    Beverly Company has determined a standard variable overhead rate of $3.70 per direct labor hour and expects to incur 0.50 labor hour per unit produced. Last month, Beverly incurred 1,550 actual direct labor hours in the production of 3.200 units. The company has also determined that its actual variable overhead rate is $2.40 per direct labor hour Calculate the variable overhead rate and efficiency variances as well as the total amount of over- or underapplied variable overhead. (Indicate the effect...

  • Units produced = 120,000; Standard Direct labor hours per Unit = 0.35; Standard variable overhead rate...

    Units produced = 120,000; Standard Direct labor hours per Unit = 0.35; Standard variable overhead rate per direct labor hour = $4; Actual variable overhead costs = $105,000; Actual hours worked = 30,000. Calculate variable overhead spending variance and variable overhead efficiency variance

  • Prado Company applies fixed manufacturing overhead costs to products based on direct labor hours. Information for the mo...

    Prado Company applies fixed manufacturing overhead costs to products based on direct labor hours. Information for the month of April appears below. Prado's expected to produce and sell 500 units for the month. Budgeted fixed overhead costs $240,000 Budgeted direct labor hours ÷ 12,000 Standard cost per direct labor hour $ 20 Standard direct labor hours per unit 18 Actual production 520 units Actual fixed overhead costs $210,000 Required: Calculate the fixed overhead spending variance and production volume variance. Clearly...

  • Glavine & Co. produces a single product, each unit of which requires three direct labor hours...

    Glavine & Co. produces a single product, each unit of which requires three direct labor hours (DLHs). Practical capacity (for setting the factory overhead application rate) is 58,000 DLHs, on an annual basis. The information below pertains to the most recent year: Standard direct labor hours (DLHs) per unit produced 3.00 Practical capacity, in DLHs (per year) 58,000 Variable overhead efficiency variance $ 19,000 unfavorable (U) Actual production for the year 16,500 units Budgeted fixed manufacturing overhead $ 1,160,000 Standard...

  • Total Variable Overhead Variance Rath Company showed the following information for the year: Standard variable overhead...

    Total Variable Overhead Variance Rath Company showed the following information for the year: Standard variable overhead rate (SVOR) per direct labor hour $3.75 Standard hours (SH) allowed per unit 4 Actual production in units 15,000 Actual variable overhead costs $222,816 57,200 Actual direct labor hours Required: 1. Calculate the standard direct labor hours for actual production. hours 2. Calculate the applied variable overhead. 3. Calculate the total variable overhead variance. Enter amount as a positive number and select Favorable or...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT