Question

U WCI is question. xii. If two projects are mutually exclusive... a. neither should be accepted. b. you will always end up ma
0 0
Add a comment Improve this question Transcribed image text
Answer #1

e) none of these is correct

a) is incorrect as the project with better NPV should be accepted.

b) is incorrect as the payback period does not account for time value of money and discounted payback period account for time value of money. Hence, payback period may be less than useful life and the project may be accepted but in same case discounted payback period may be less than useful life and project may be accepted.

c) is incorrect as i case of mutually exclusive projects, NPV and IRR conflict may arise as in one of the project s NPV may be higher and in other IRR may be higher.

d) is incorrect as the NPV for 2 mutually exclusive projects may be different.

Add a comment
Know the answer?
Add Answer to:
U WCI is question. xii. If two projects are mutually exclusive... a. neither should be accepted....
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • b. Positive within-fum extervies c. Negative within-fum externatives. d. Opportunity costs. e. Sunk costs. Duval Inc....

    b. Positive within-fum extervies c. Negative within-fum externatives. d. Opportunity costs. e. Sunk costs. Duval Inc. Uses only equity capital and it has two equally des Division A's cost of capital is 100% Division B's cost is 140, corporate composite) WACC is 12.0%. All of Division A's projects are equally hisky, as are all of Division ' S e cts. However, the projects of Division w CSS nsky than those of Division B Which of the following projects should the...

  • Suppose your firm is considering two mutually exclusive, required projects with the cash flows shown below....

    Suppose your firm is considering two mutually exclusive, required projects with the cash flows shown below. The required rate of return on projects of both of their risk class is 8 percent, and that the maximum allowable payback and discounted payback statistic for the projects are 2 and 3 years, respectively. Time: 0123 Project -35,000 25,000 45,000 16,000 A Cash Flow Project -45,000 25,000 35,000 B Cash Flow Use the NPV decision rule to evaluate these projects; which one(s) should...

  • Suppose your firm is considering two mutually exclusive, required projects with the cash flows shown below....

    Suppose your firm is considering two mutually exclusive, required projects with the cash flows shown below. The required rate of return on projects of both of their risk class is 12 percent, and that the maximum allowable payback and discounted payback statistic for the projects are 2 and 3 years, respectively. Time: 1 2 3 14,000 34,000 Project A Cash Flow 24,000 5,000 24,000 Project B Cash Flow -34,000 14,000 54,000 Use the NPV decision rule to evaluate these projects;...

  • Suppose your firm is considering two mutually exclusive, required projects with the cash flows shown below....

    Suppose your firm is considering two mutually exclusive, required projects with the cash flows shown below. The required rate of return on projects of both of their risk class is 8 percent, and that the maximum allowable payback and discounted payback statistic for the projects are 2 and 3 years, respectively. Time: 0 1 2 3 Project A Cash Flow -30,000 20,000 40,000 11,000 Project B Cash Flow -40,000 20,000 30,000 60,000 Use the NPV decision rule to evaluate these...

  • Suppose your firm is considering two mutually exclusive, required projects with the cash flows shown below....

    Suppose your firm is considering two mutually exclusive, required projects with the cash flows shown below. The required rate of return on projects of both of their risk class is 10 percent, and that the maximum allowable payback and discounted payback statistic for the projects are 2 and 3 years, respectively.   Time: 0 1 2 3   Project A Cash Flow -37,000 27,000 47,000 18,000   Project B Cash Flow -47,000 27,000 37,000 67,000 Use the NPV decision rule to evaluate these...

  • Suppose your firm is considering two mutually exclusive, required projects with the cash flows shown below....

    Suppose your firm is considering two mutually exclusive, required projects with the cash flows shown below. The required rate of return on projects of both of their risk class is 11 percent, and that the maximum allowable payback and discounted payback statistic for the projects are 2 and 3 years, respectively. 0 Time: 43,000 Project A 33,000 23,000 Flow Project B 43,000 23,000 33,000 63,000 Cash Flow Use the discounted payback decision rule to evaluate these projects; which one(s) should...

  • 1. A. Which of the following mutually exclusive projects should be accepted? Project NPV Payback IRR...

    1. A. Which of the following mutually exclusive projects should be accepted? Project NPV Payback IRR A +42,176 2 years, +$10,500 16.4% B +39,090 2 years, +9,670 15.8% C +41,894 3 years, +16,620 13.2% D +43,778 3 years, +11,625 14.9% E +38,952 2 years, +15,475 15.9% B. What is the Payback Period of a project with an initial cost of $75,000, Year 1 cash flow of $20,000 which increases by 5% each year? If the Payback cutoff is 3 years,...

  • Which of the following statements is INCORRECT? Select one: a. For independent projects, the decision to...

    Which of the following statements is INCORRECT? Select one: a. For independent projects, the decision to accept or reject will always be the same using either the MIRR method or the NPV method. b. The IRR method is appealing to some managers because it produces a rate of return upon which to base decisions rather than a dollar amount like the NPV method. c. One of the disadvantages of choosing between mutually exclusive projects on the basis of discounted payback...

  • Suppose your firm is considering two mutually exclusive, required projects with the cash flows shown below....

    Suppose your firm is considering two mutually exclusive, required projects with the cash flows shown below. The required rate of return on projects of both of their risk class is 11 percent, and that the maximum allowable payback and discounted payback statistic for the projects are 2 and 3 years, respectively. 0 3 8000 1 28.000 2 48.000 19.000 Time: Project A Cash Flow Project B Cash Flow -48,000 28,000 2,000 68,000 Use the payback decision rule to evaluate these...

  • Isaac has analyzed two mutually exclusive projects that have 3-year lives. Project A has an NPV...

    Isaac has analyzed two mutually exclusive projects that have 3-year lives. Project A has an NPV of $81,406, a payback period of 2.48 years, and an IRR of 9.31 percent. Project B has an NPV of $82,909, a payback period of 2.57 years, and an IRR of 9.22 percent. The firm’s cost of capital is 9.15 percent and required payback period is 2.8 years. Isaac must make a recommendation and justify it in 15 words or less. What should his...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT