Question

Which one of the following is FALSE for a project whose NPV equals zero? Group of...

Which one of the following is FALSE for a project whose NPV equals zero?

Group of answer choices

The project will have no impact on firm value.

The project earns more than the required return.

The IRR is equal to the required rate of return

The projects cash outflows are equal to the present value of the cash inflows.

0 0
Add a comment Improve this question Transcribed image text
Answer #1

When Net present value = 0, it means the present value of cash inflows less present value of cash outflows equal to zero.

NPV = 0, when the required return is equal to the Internal rate of return

So, the firm will be indifferent in taking decisions.

So, the False statement is The project Earns more than the required return

Option '2' is False

Add a comment
Know the answer?
Add Answer to:
Which one of the following is FALSE for a project whose NPV equals zero? Group of...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • True or false and why? 5. The internal rate of return (IRR) is such a discount...

    True or false and why? 5. The internal rate of return (IRR) is such a discount rate that ensures the sum of present value of the cash outflows (or costs) with the sum of future value of the cash inflows. 6. A basic rule in capital budgeting is that if a projects NPV is larger than or equal to its IRR, then the project should be accepted.

  • 18. Which of the following is NOT true about the internal rate of return: A) A...

    18. Which of the following is NOT true about the internal rate of return: A) A good project is one with IRR greater than the required return. B) IRR is the discount rate that results in a zero net present value for the project. C) Crossover rate for two projects is the IRR of the project with the difference of the cash flows of the two projects.. D) For two projects of the same size, IRR will usually choose the...

  • Which of the following statements is CORRECT? Assume that the project being considered has normal cash...

    Which of the following statements is CORRECT? Assume that the project being considered has normal cash flows, with one outflow followed by a series of inflows. Group of answer choices A) If a project's IRR is positive, then its NPV must also be positive. B) A project's IRR is the discount rate that causes the PV of the inflows to equal the project's cost. C) If a project's IRR is smaller than the WACC, then its NPV will be positive....

  • QUESTION 12 Opportunity costs should be included in the analysis of a project. True False QUESTION...

    QUESTION 12 Opportunity costs should be included in the analysis of a project. True False QUESTION 13 Sunk costs are considered cash flows of a project. True False QUESTION 14 The crossover point is defined as the discount rate that: Indicates the point where the IRR equals zero as IRR moves in a downward direction. Causes the net present value of a project to equal zero. Causes the IRR of one project to exceed the IRR of a second project....

  • Help and verified and be clear. The net present value (NPV) and internal rate of return...

    Help and verified and be clear. The net present value (NPV) and internal rate of return (IRR) methods of investment analysis are interrelated and are sometimes used together to make capital budgeting decisions. Consider the case of Blue Hamster Manufacturing Inc.: Last Tuesday, Blue Hamster Manufacturing Inc. lost a portion of its planning and financial data when both its main and its backup servers crashed. The company's CFO remembers that the internal rate of return (IRR) of Project Lambda is...

  • Which of the following statements is correct? A project's discounted payback period (DBP) is normally shorter...

    Which of the following statements is correct? A project's discounted payback period (DBP) is normally shorter than its traditional payback period (PB) because DPB accounts for the time value of money, whereas PB does not. To compute the NPV for a project, the firm's required rate of return must be known. To compute a project's internal rate of return (IRR), the firm's required rate of return is not used because the IRR is the discount rate where the project's NPV...

  • If the net present value (NPV) of an investment proposal is positive, it would indicate that...

    If the net present value (NPV) of an investment proposal is positive, it would indicate that the a. PV of cash outflows exceeds the PV of cash inflows. b. Payback period is less than one-half the life of the project. c. Internal rate of return (IRR) is equal to the discount percentage used in the NPV calculation. d. PV of cash inflows exceeds the PV of cash outflows 2. Sales forecasts are the first step in the budgeting process because...

  • The net present value (NPV) method implicitly assumes that the rate at which cash flows can...

    The net present value (NPV) method implicitly assumes that the rate at which cash flows can be reinvested is the required rate of return, whereas the internal rate of return (IRR) method implies that the firm has the opportunity to reinvest at the project's IRR. Group of answer choices False True

  • Which of the following statements is most correct? Group of answer choices If a project with...

    Which of the following statements is most correct? Group of answer choices If a project with normal cash flows has an IRR, which exceeds the cost of capital (required rate of return), then the project must have a positive NPV. If the IRR of Project A exceeds the IRR of Project B, then Project A must also have a higher NPV. Assuming a project has normal cash flows, the NPV will be positive if the IRR is less than the...

  • 3. Understanding the IRR and NPV The net present value (NPV) and internal rate of return...

    3. Understanding the IRR and NPV The net present value (NPV) and internal rate of return (IRR) methods of Investment make capital budgeting decisions Consider the case of Blue Hamster Manufacturing Inc Last Tuesday, Blue Hamster Manufacturing Inc. lost a portion of its planning and financial data when both its main and servers crashed. The company's CFO remembers that the internal rate of retur (IRR) of Project Zeta is 13.8%, but he can't reca much Blue Hamster originally invested in...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT