QUESTION 12
TRUE
Opportunity costs are included in the analysis of a project. The discount rate to evaluate the project is nothing but the opportunity cost of capital.
QUESTION 13
FALSE
Sunk costs are not considered in the cash flow of a project. Sunk costs are not recoverable and hence they are not considered.
QUESTION 14
Option D is correct.
The rate at which the NPV of two projects equal is the crossover point.
Option A is incorrect because it doesn't define the crossover point
Option B is incorrect because it is the definition of IRR
Option C is incorrect because it doesn't define the crossover point
Option E is incorrect because the crossover rate is not the rate at which NPV turns negative
Can you please upvote? Thank You :-)
QUESTION 12 Opportunity costs should be included in the analysis of a project. True False QUESTION...
Which one of the following is FALSE for a project whose NPV equals zero? Group of answer choices The project will have no impact on firm value. The project earns more than the required return. The IRR is equal to the required rate of return The projects cash outflows are equal to the present value of the cash inflows.
You are using a net present value profile to compare Projects A and B, which are mutually exclusive. Which one of the following statements correctly applies to the crossover point between these two? The internal rate of return for Project A equals that of Project B, but generally does not equal zero. The internal rate of return of each project is equal to zero. The net present value of each project is equal to zero. The net present value of...
True or false and why? 5. The internal rate of return (IRR) is such a discount rate that ensures the sum of present value of the cash outflows (or costs) with the sum of future value of the cash inflows. 6. A basic rule in capital budgeting is that if a projects NPV is larger than or equal to its IRR, then the project should be accepted.
A key difference between a replacement project analysis and an expansion project analysis is that the net present value (NPV) technique that is used to evaluate capital budgeting projects should only be used to evaluate expansion projects, whereas either the NPV technique or the internal rate of return (IRR) technique can be used to evaluate replacement projects. True False
Your answer: (CHAPTER 9) Two projects have the following estimated cash flows: Today 1 year from today 2 years from today 3 years from today Project "A" -$100,000 $55,000 $65,000 $35,000 Project "B" $100,000 $52,000 $64,000 $40,000 Calculate the "crossover rate", in percent. (Do NOT use "%" in your answer. Round your answer to TWO decimal places. For example, if your IRR is 12.34%, put 12.34) TRUE or FALSE? Both projects have a zero Net Present Value at a discount...
18. Which of the following is NOT true about the internal rate of return: A) A good project is one with IRR greater than the required return. B) IRR is the discount rate that results in a zero net present value for the project. C) Crossover rate for two projects is the IRR of the project with the difference of the cash flows of the two projects.. D) For two projects of the same size, IRR will usually choose the...
If investment funds are limited, the net present value of one project should not be compared directly to the net present value of another project unless the initial investments in these projects are equal. True or False and why?
Question 7 (10 marks] 7.1. 7.2. Operating cash flows, rather than accounting profits, are used in project analysis. What is the basis for this emphasis on cash flows as opposed to net income? (4) Why is it true, in general, that a failure to adjust expected cash flows for expected inflation biases the calculated NPV downward? (2) Explain why sunk costs should not be included in a capital budgeting analysis but opportunity costs and externalities should be included. 7.3.
Question #7 Finance Which of these is a true statement? A. Project specific risk should be used to discount cash flows rather than company level risk. B. When a project is undertaken it should have an IRR that is below your risk adjusted discount rate. C. Risk should not be accounted for in capital budgeting projects. D. A company will always accept the project with the highest possible return. Sunk costs should always be included when evaluating an opportunity. E....
True/False Answer all questions. Write out the word True or False in the space provided. ( 2 Pts. Ea.) 1. Standard Costs serve as a device for measuring efficiency. 2. The Standard cost is how much a product should cost to manufacture. 3. Standard costs should always be revised when they differ from actual costs. 4. Changes in technology, machinery, or production methods may make past cost data irrelevant when setting standards. 5. Differential revenue is the amount of increase...