Answer: Option A is correct. The company should invest in Project 1.
The company should invest in the project that would give higher
net present value.
Net present value=-Initial investment + Present value of future
cash flows at the discount rate of 10%
Project 1:
Net present value=-300 +
150/(1+10%)^1+150/(1+10%)^2+150/(1+10%)^3
=-300 + 150/1.1+150/1.21+150/1.331
=-300 + 136.3636364+123.9669421+112.6972201
=73.0277986 or $73.03 (Rounded to 2 decimal places)
Project 2:
Net present value=-300 +
350/(1+10%)^1+0/(1+10%)^2+0/(1+10%)^3
=-300 + 350/1.1+0
=18.18181818 or $18.18 (Rounded to 2 decimal places)
Answer: As the net present value of project 1 is higher than
project 2, project 1 should be accepted.
Alternative solution using excel:
Answer: As the net present value of project 1 is higher between the two projects, it should be accepted.
A company has the following two projects: Time 1 Time 3 Time 0 Time 2 Project...
Consider the following two projects: Project Year 0 Year 1 Year 2 Year 3 Year 4 Year 5 Year 6 Year 7 Discount C/F C/F C/F C/F C/F C/F C/F C/F Rate Alpha - 79 20 25 30 35 40 NA NA 15% Beta - 80 25 25 25 25 25 25 25 16% Assume that projects Alpha and Beta are mutually exclusive. The correct investment decision and the best rationale for that decision is to O A invest in...
Consider the following two projects: Year 0 Yearl Year 2 Year 3 Year 4 Year 5 Year 6 Year 7 Discount Project C/E C/F C/E C/E C/F C/E C/F C/F Rate Alpha -79 20 25 30 35 40 N/A N/A 15% Beta -80 25 25 25 25 25 25 25 16% Which of the following statements is correct? Select one: A. You should invest in project Alpha since IRRAlpha > IRRBeta. B. You should invest in project Beta since NPVBeta...
A firm with a WACC of 10% is considering the following mutually exclusive projects: 1 2 - 4 5 $50 $215 $215 Project 1 -$400 $50 $50 Project 2 -$600 $350 $350 Which project would you recommend? $110 $110 $110 Select the correct answer. O 10 10 O O a. Project 1, since the NPV1 > NPV2 b. Both Projects 1 and 2, since both projects have NPV's > 0. c. Neither Project 1 nor 2, since each project's NPV...
Most Company has an opportunity to invest in one of two new projects. Project Y requires a $340,000 investment for new machinery with a five-year life and no salvage value. Project Z requires a $340,000 investment for new machinery with a four-year life and no salvage value. The two projects yield the following predicted annual results. The company uses straight-line depreciation, and cash flows occur evenly throughout each year. (PV of S1, FV of $1, PVA of $1, and FVA...
Consider the following two projects: Project Year 0 Year 1 Year 2 Year 3 Year 4 Cash Flow Cash Flow Cash Flow Cash Flow Cash Flow A - 100 40 50 60 N/A B -73 30 30 30 30 Discount Rate 0.16 0.16 The net present value (NPV) of project A is closest to: O A. 11.1 B. 25.2 O C. 10.1 OD. 12.6
Clifford Company is choosing between two projects. The larger project has an initial cost of $100,000, annual cash flows of $30,000 for 5 years, and an IRR of 15.24%. The smaller project has an initial cost of $50,000, annual cash flows of $16,000 for 5 years, and an IRR of 16.63%. The projects are equally risky. Which of the following statements is CORRECT? Since the smaller project has the higher IRR, the two projects’ NPV profiles will cross, and the...
A firm with a WACC of 10% is considering the following mutually exclusive projects: 12 3 4 5 $40 $150 $165 $150 $165 $150 Project 1 -$450 $40 $40 Project 2 -$600 $200 $200 Which project would you recommend? Select the correct answer. O O O O O a. Project 1, since the NPV, > NPV2. b. Both Projects 1 and 2, since both projects have IRR's > 0. c. Both Projects 1 and 2, since both projects have NPV's...
A firm with a WACC of 10% is considering the following mutually exclusive projects: 0 1 2 3 4 5 Project 1 -$450 $40 $40 $40 $165 $165 Project 2 -$450 $350 $350 $110 $110 $110 Which project would you recommend? Select the correct answer. a. Both Projects 1 and 2, since both projects have IRR's > 0. b. Project 2, since the NPV2 > NPV1. c. Neither Project 1 nor 2, since each project's NPV < 0. d. Project...
A firm with a WACC of 10% is considering the following mutually exclusive projects: 0 1 2 3 4 5 Project 1 -$400 $55 $55 $55 $205 $205 Project 2 -$650 $250 $250 $150 $150 $150 Which project would you recommend? Select the correct answer. a. Project 1, since the NPV1 > NPV2. b. Both Projects 1 and 2, since both projects have IRR's > 0. c. Both Projects 1 and 2, since both projects have NPV's > 0. d....
A firm with a WACC of 10% is considering the following mutually exclusive projects: o 1 2 3 4 5 Project 1 Project 2 -$200 -$700 $75 $350 $75 $350 $75 $100 $230 $100 $230 $100 Which project would you recommend? Select the correct answer. a. Both Projects 1 and 2, since both projects have NPV's > 0. Ob. Project 2, since the NPV2 > NPV1. Oc. Neither Project 1 nor 2, since each project's NPV < 0. O d....