Question

Clifford Company is choosing between two projects. The larger project has an initial cost of $100,000,...

  1. Clifford Company is choosing between two projects. The larger project has an initial cost of $100,000, annual cash flows of $30,000 for 5 years, and an IRR of 15.24%. The smaller project has an initial cost of $50,000, annual cash flows of $16,000 for 5 years, and an IRR of 16.63%. The projects are equally risky. Which of the following statements is CORRECT?

Since the smaller project has the higher IRR, the two projects’ NPV profiles will cross, and the larger project will look better based on the NPV at all positive values of WACC.

If the company uses the NPV method, it will tend to favor smaller, shorter-term projects over larger, longer-term projects, regardless of how high or low the WACC is.

Since the smaller project has the higher IRR but the larger project has the higher NPV at a zero discount rate, the two projects’ NPV profiles will cross, and the larger project will have the higher NPV if the WACC is less than the crossover rate.

Since the smaller project has the higher IRR and the larger NPV at a zero discount rate, the two projects’ NPV profiles will cross, and the smaller project will look better if the WACC is less than the crossover rate.

Since the smaller project has the higher IRR, the two projects’ NPV profiles cannot cross, and the smaller project's NPV will be higher at all positive values of WACC.

0 0
Add a comment Improve this question Transcribed image text
Answer #1

C) Since the smaller project has the higher IRR but the larger project has the higher NPV at a zero discount rate, the two projects’ NPV profiles will cross, and the larger project will have the higher NPV if the WACC is less than the crossover rate.

Add a comment
Know the answer?
Add Answer to:
Clifford Company is choosing between two projects. The larger project has an initial cost of $100,000,...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • OOSING MANDATORY PROJECTS ON THE BASIS OF LEAST COST m Inc. must install a new air...

    OOSING MANDATORY PROJECTS ON THE BASIS OF LEAST COST m Inc. must install a new air conditioning unit in its main plant. Kim must install one or the other of the units; otherwise, the highly profitable plant ould have to shut down. Two units are available, HCC and LCC (for high and low capital costs, respectively). HCC has a high capital cost but relatively love erating costs, while LCC has a low capital cost but higher operating costs because it...

  • Which of the following statements is CORRECT? To find the MIRR, we first compound cash flows...

    Which of the following statements is CORRECT? To find the MIRR, we first compound cash flows at the regular IRR to find the TV, and then we discount the TV at the WACC to find the PV. The NPV and IRR methods both assume that cash flows can be reinvested at the WACC. However, the MIRR method assumes reinvestment at the MIRR itself. If two projects have the same cost, and if their NPV profiles cross in the upper right...

  • You are choosing between two projects. The cash flows for the projects are given in the...

    You are choosing between two projects. The cash flows for the projects are given in the following table​ ($ million): a. What are the IRRs of the two​ projects? The IRR for project A is ______​%. ​(Round to one decimal​ place.) The IRR for project B is ______​%. ​(Round to one decimal​ place.) b. If your discount rate is 4.8 %​, what are the NPVs of the two​ projects? If your discount rate is 4.8%​, the NPV for project A...

  • ON EXCEL The director of capital budgeting for Giant Inc. has identified two mutually exclusive projects,...

    ON EXCEL The director of capital budgeting for Giant Inc. has identified two mutually exclusive projects, L and S, with the following expected net cash flows and a required rate of return of 10 percent: Expected Net Cash Flows Year Project S Project L ($210,000) 0 ($161,000) 90,000 10,000 - 0 20,000 60,000 80,000 20,000 60,000 + 90,000 90,000 10,000 Build an automatic spread sheet that calculates: 1. the NPV of both projects with 2 different methods (NPV of excel...

  • Which of the followin is correct? A. Because discounted payback takes account of the required rate...

    Which of the followin is correct? A. Because discounted payback takes account of the required rate of return, a projects discounted payback is normally shorter than its regular payback. B. The npv and irr methods use the same basic equation, but in the npv method the discount rate is specified and the equation is solved for npv, while in the irr method the npv is set equal zero and the discount rate is found. C. If the required rate of...

  • You are choosing between two projects. The cash flows for the projects are given in the...

    You are choosing between two projects. The cash flows for the projects are given in the following table ($ milion); Project Year Year 2 Year o -$48 - $101 Year 3 $21 $50 Year 4 $14 $27 $20 $40 $62 Tes a What are the IRRs of the two projects? b. If your discount rate is 4.7%, what are the NPVs of the two projects? c. Why do IRR and NPV rank the two projects differently? a. What are the...

  • You are choosing between two projects. The cash flows for the projects are given in the...

    You are choosing between two projects. The cash flows for the projects are given in the following table ($ million): Project Year 0 Year 1 Year 2 Year 3 Year 4 - $50 $18 $19 $17 - $101 $21 $40 $51 $26 $59 a. What are the IRRs of the two projects? b. If your discount rate is 5.1%, what are the NPVs of the two projects? c. Why do IRR and NPV rank the two projects differently? a. What...

  • An oil-drilling company must choose between two mutually exclusive extraction projects, and each requires an initial...

    An oil-drilling company must choose between two mutually exclusive extraction projects, and each requires an initial outlay at t = 0 of $11.2 million. Under Plan A, all the oil would be extracted in 1 year, producing a cash flow at t = 1 of $13.44 million. Under Plan B, cash flows would be $1.9901 million per year for 20 years. The firm's WACC is 12.3%. Construct NPV profiles for Plans A and B. Enter your answers in millions. For...

  • An oil-drilling company must choose between two mutually exclusive extraction projects, and each requires an initial...

    An oil-drilling company must choose between two mutually exclusive extraction projects, and each requires an initial outlay at t = 0 of $11.2 million. Under Plan A, all the oil would be extracted in 1 year, producing a cash flow at t = 1 of $13.44 million. Under Plan B, cash flows would be $1.9901 million per year for 20 years. The firm's WACC is 11.5%. Construct NPV profiles for Plans A and B. Enter your answers in millions. For...

  • An oil-drilling company must choose between two mutually exclusive extraction projects, and each requires an initial...

    An oil-drilling company must choose between two mutually exclusive extraction projects, and each requires an initial outlay at t = 0 of $12.4 million. Under Plan A, all the oil would be extracted in 1 year, producing a cash flow at t = 1 of $14.88 million. Under Plan B, cash flows would be $2.2034 million per year for 20 years. The firm's WACC is 11%. Construct NPV profiles for Plans A and B. Enter your answers in millions. For...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT