Question

Which of the followin is correct? A. Because discounted payback takes account of the required rate...

Which of the followin is correct?
A. Because discounted payback takes account of the required rate of return, a projects discounted payback is normally shorter than its regular payback.
B. The npv and irr methods use the same basic equation, but in the npv method the discount rate is specified and the equation is solved for npv, while in the irr method the npv is set equal zero and the discount rate is found.
C. If the required rate of return is less than the crossover rate for two mutually exclusive projects npv profiles, a npv/irr conflict will not occurr.
D. If you choosing between two projects which have the same file and if their npv profiles cross, then tha smaller project will probably be the one with the steeper npv profile.
0 0
Add a comment Improve this question Transcribed image text
Answer #1

Net present value (NPV) = Present value of cash inflows-Present value of cash outflows.

These present values are calculated at the required rate.

Internal rate of return is implied return from cash flows.

Hence, correct option is “B. The npv and irr methods use the same basic equation, but in the npv method the discount rate is specified and the equation is solved for npv, while in the irr method the npv is set equal zero and the discount rate is found.”

Add a comment
Know the answer?
Add Answer to:
Which of the followin is correct? A. Because discounted payback takes account of the required rate...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • KEY TERMS Define the following terms: a. Capital budgeting; strategic business plan b. Net present value...

    KEY TERMS Define the following terms: a. Capital budgeting; strategic business plan b. Net present value (NPV) c. Internal rate of return (IRR) d. NPV profile; crossover rate e. Mutually exclusive projects; independent projects f. Nonnormal cash flows; normal cash flows; multiple IRRS g. Modified internal rate of return (MIRR) h. Payback period; discounted payback CAPITAL BUDGETING CRITERIA You must analyze two projects, X and Y. Each project costs $10,000, and the firm's WACC is 12%. The expected cash flows...

  • First Blank: always, sometimes, never Second Blank: IRR, MIRR, required rate of return Third Blank: IRR,...

    First Blank: always, sometimes, never Second Blank: IRR, MIRR, required rate of return Third Blank: IRR, MIRR, required rate of return Fourth Blank: IRR method, NPV method 6. Understanding the NPV profile If projects are mutually exclusive, only one project can be chosen. The internal rate of return (IRR) and the net present value (NPV) methods will not always choose the same project. If the crossover rate on the NPV profile is below the horizontal axis, the methods will agree....

  • Dropdown options first 2 blanks: (internal rate of return IRR, required rate of return, modified internal...

    Dropdown options first 2 blanks: (internal rate of return IRR, required rate of return, modified internal rate of return MIRR) Dropdown options 3rd blank: (NPV method, IRR method) If projects are mutually exclusive, only one project can be chosen. The internal rate of return (IRR) and the net present value (NPV) methods will not always choose the same project. If the crossover rate on the NPV profile is below the horizontal axis, the methods will agree. always Projects Y and...

  • Which of the following statements is correct? A project's discounted payback period (DBP) is normally shorter...

    Which of the following statements is correct? A project's discounted payback period (DBP) is normally shorter than its traditional payback period (PB) because DPB accounts for the time value of money, whereas PB does not. To compute the NPV for a project, the firm's required rate of return must be known. To compute a project's internal rate of return (IRR), the firm's required rate of return is not used because the IRR is the discount rate where the project's NPV...

  • Which of the following statements is INCORRECT? Select one: a. For independent projects, the decision to...

    Which of the following statements is INCORRECT? Select one: a. For independent projects, the decision to accept or reject will always be the same using either the MIRR method or the NPV method. b. The IRR method is appealing to some managers because it produces a rate of return upon which to base decisions rather than a dollar amount like the NPV method. c. One of the disadvantages of choosing between mutually exclusive projects on the basis of discounted payback...

  • Which one of these statements related to discounted payback is correct? Multiple Choice Payback is a...

    Which one of these statements related to discounted payback is correct? Multiple Choice Payback is a better method of analysis than discounted payback. Discounted payback is used more frequently in business than payback. Discounted payback does not require a cutoff point. Discounted payback is biased towards short-term projects The discounted payback period increases as the discount rate decreases.

  • Clifford Company is choosing between two projects. The larger project has an initial cost of $100,000,...

    Clifford Company is choosing between two projects. The larger project has an initial cost of $100,000, annual cash flows of $30,000 for 5 years, and an IRR of 15.24%. The smaller project has an initial cost of $50,000, annual cash flows of $16,000 for 5 years, and an IRR of 16.63%. The projects are equally risky. Which of the following statements is CORRECT? Since the smaller project has the higher IRR, the two projects’ NPV profiles will cross, and the...

  • Help and verified and be clear. The net present value (NPV) and internal rate of return...

    Help and verified and be clear. The net present value (NPV) and internal rate of return (IRR) methods of investment analysis are interrelated and are sometimes used together to make capital budgeting decisions. Consider the case of Blue Hamster Manufacturing Inc.: Last Tuesday, Blue Hamster Manufacturing Inc. lost a portion of its planning and financial data when both its main and its backup servers crashed. The company's CFO remembers that the internal rate of return (IRR) of Project Lambda is...

  • Question text Which of the following statements is CORRECT? Select one: a. The discounted payback method...

    Question text Which of the following statements is CORRECT? Select one: a. The discounted payback method is generally regarded by academics as being the best single method for evaluating capital budgeting projects. b. The modified internal rate of return method (MIRR) is generally regarded by academics as being the best single method for evaluating capital budgeting projects. c. The net present value method (NPV) is generally regarded by academics as being the best single method for evaluating capital budgeting projects....

  • A project's NPV profile graph intersects the Y-axis at 0% cost of capital and intersects the...

    A project's NPV profile graph intersects the Y-axis at 0% cost of capital and intersects the X-axis at the project's Select (where NPV = 0). The Y-axis intersection point represents the project's undiscounted NPV. The point at which 2 projects' profiles cross one another is the crossover rate. The crossover rate can be found by calculating the Select of the differences in the projects' cash flows (Project Delta). A Select NPV profile indicates that increases in the cost of capital...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT