direct materials $8.60
direct labor 33.88
direct manufacturing overhead 10.56
total cost $53.04

working:

direct materials:

pounds per unit = 3.20 +0.80

=>4.00 pounds.

cost per unit = 4 pounds*$2

=>$8.00

amount paid per unit

=>$8.00*(95%)........(since 5% discount is given)

=>$7.60.

freight paid = $0.25*4 pounds

=>$1.00

total direct material cost per unit =$7.60+1.00

=>$8.60.

direct labor

=>total time * total rate per hour

=>(2.10+0.10) *(13.20+2.20)

=>$33.88.

manufacturing overhead:

$4.80*2.20 labor hours

=>$10.56

Add a comment
Know the answer?
Add Answer to:
CALCULATOR PRINTER VERSION BACK NEXT Exercise 11-3 (Video) Stefani Company has gathered the following information about...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Exercise 23-3 Stefani Company has gathered the following information about its product. Direct materials: Each unit...

    Exercise 23-3 Stefani Company has gathered the following information about its product. Direct materials: Each unit of product contains 3.20 pounds of materials. The average waste and spoilage per unit produced under normal conditions is 0.10 pounds. Materials cost $2 per pound, but Stefani always takes the 5.00% cash discount all of its suppliers offer. Freight costs average $0.25 per pound Direct labor. Each unit requires 2.10 hours of labor. Setup, cleanup, and downtime average 0.10 hours per unit. The...

  • Exercise 11-3 Stefani Company has gathered the following information about its product Direct materials: Each unit...

    Exercise 11-3 Stefani Company has gathered the following information about its product Direct materials: Each unit of product contains 3.20 pounds of materials. The average waste and spoilage per unit produced under normal conditions is 0.10 pounds. Materials cost $2 per pound, but Stefani always takes the 5.00% cash discount all of its suppliers offer. Freight costs average $0.25 per pound. Direct labor. Each unit requires 2.10 hours of labor. Setup, cleanup, and downtime average 0.10 hours per unit. The...

  • Exercise 11-3 (Video) Stefani Company has gathered the following information about its product. Direct materials: Each...

    Exercise 11-3 (Video) Stefani Company has gathered the following information about its product. Direct materials: Each unit of product contains 3.10 pounds of materials. The average waste and spoilage per unit produced under normal conditions is 0.90 pounds. Materials cost $2 per pound, but Stefani always takes the 4.00% cash discount all of its suppliers offer. Freight costs average $0.45 per pound. Direct labor. Each unit requires 1.30 hours of labor. Setup, cleanup, and downtime average 0.20 hours per unit....

  • Exercise 11-3 (Video) Stefani Company has gathered the following information about its product Direct materials: Each...

    Exercise 11-3 (Video) Stefani Company has gathered the following information about its product Direct materials: Each unit of product contains 3.90 pounds of materials. The average waste and spoilage per unit produced under normal conditions is 1.10 pounds. Materials cost $2 per pound, but Stefani always takes the 1.00 % cash discount all of its suppliers offer. Freight costs average $0.45 per pound. Direct labor. Each unit requires 2.60 hours of labor. Setup, cleanup, and downtime average 0.20 hours per...

  • Exercise 11-3 (Video) Stefani Company has gathered the following information about its product....

    Exercise 11-3 (Video) Stefani Company has gathered the following information about its product. Direct materials: Each unit of product contains 3.10 pounds of materials. The average waste and spoilage per unit produced under normal conditions is 0.90 pounds. Materials cost $4 per pound, but Stefani always takes the 1.00% cash discount all of its suppliers offer. Freight costs average $0.25 per pound. Direct labor. Each unit requires 2.10 hours of labor. Setup, cleanup, and downtime average 0.20 hours per unit....

  • Exercise 24-03 (Video) X Your answer is incorrect. Try again. Stefani Company has gathered the following...

    Exercise 24-03 (Video) X Your answer is incorrect. Try again. Stefani Company has gathered the following information about its product. Direct materials: Each unit of product contains 4.50 pounds of materials. The average waste and spoilage per unit produced under normal conditions is 0.50 pounds. Materials cost $5 per pound, but Stefani always takes the 2.00% cash discount all of its suppliers offer. Freight costs average $0.25 per pound. Direct labor. Each unit requires 2.00 hours of labor. Setup, cleanup,...

  • Stefani Company has gathered the following information about its product. Direct materials: Each unit of product...

    Stefani Company has gathered the following information about its product. Direct materials: Each unit of product contains 3.20 pounds of materials. The average waste and spoilage per unit produced under normal conditions is 0.80 pounds. Materials cost $1 per pound, but Stefani always takes the 1.00% cash discount all of its suppliers offer. Freight costs average $0.25 per pound. Direct labor. Each unit requires 1.00 hours of labor. Setup, cleanup, and downtime average 0.10 hours per unit. The average hourly...

  • Stefani Company has gathered the following information about its product. Direct materials: Each unit of product...

    Stefani Company has gathered the following information about its product. Direct materials: Each unit of product contains 3.10 pounds of materials. The average waste and spoilage per unit produced under normal conditions is 0.10 pounds. Materials cost $1 per pound, but Stefani always takes the 5.00% cash discount all of its suppliers offer. Freight costs average $0.30 per pound. Direct labor. Each unit requires 1.60 hours of labor. Setup, cleanup, and downtime average 0.10 hours per unit. The average hourly...

  • Stefani Company has gathered the following information about its product. Direct materials: Each unit of product...

    Stefani Company has gathered the following information about its product. Direct materials: Each unit of product contains 3.90 pounds of materials. The average waste and spoilage per unit produced under normal conditions is 1.10 pounds. Materials cost $2 per pound, but Stefani always takes the 1.00% cash discount all of its suppliers offer. Freight costs average $0.45 per pound. Direct labor. Each unit requires 2.60 hours of labor. Setup, cleanup, and downtime average 0.20 hours per unit. The average hourly...

  • Stefani Company has gathered the following information about its product. Direct materials: Each unit of product...

    Stefani Company has gathered the following information about its product. Direct materials: Each unit of product contains 3.40 pounds of materials. The average waste and spoilage per unit produced under normal conditions is 0.60 pounds. Materials cost $2 per pound, but Stefani always takes the 2.00% cash discount all of its suppliers offer. Freight costs average $0.25 per pound. Direct labor. Each unit requires 1.00 hours of labor. Setup, cleanup, and downtime average 0.20 hours per unit. The average hourly...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT