Solution 1:
Year 2018: Weighted-Average accumulated expenditure and interest capitalized | |||
Date | Amount | Capitalization period | Weighted Average Accumulated Expenditures |
1-Jan-18 | $1,870,000 | 12/12 | $1,870,000 |
1-Mar-18 | $1,560,000 | 10/12 | $1,300,000 |
30-Jun-18 | $1,760,000 | 6/12 | $880,000 |
1-Oct-18 | $1,560,000 | 3/12 | $390,000 |
Total | $6,750,000 | $4,440,000 | |
*Interest rate | 15% | ||
Interest capitalized in 2018 | $666,000 | ||
Year 2019: Weighted-Average accumulated expenditure | |||
Date | Amount | Capitalization period | Weighted Average Accumulated Expenditures |
1-Jan-19 | $7,416,000 | 9/9 | $7,416,000 |
31-Jan-19 | $414,000 | 8/9 | $368,000 |
30-Apr-19 | $747,000 | 5/9 | $415,000 |
31-Aug-19 | $1,044,000 | 1/9 | $116,000 |
Total | $9,621,000 | $8,315,000 | |
Weighted average interest rate of all other debt | |||
Debt | Amount | Interest rate | Interest amount |
8% Note | $2,000,000 | 8% | $160,000 |
12% Note | $8,000,000 | 12% | $960,000 |
Totals | $10,000,000 | $1,120,000 | |
Weighted average rate (total interets/ total debt) | 11.20% | ||
Year 2019: Interest Capitalized | |||
Debt | Amount | ||
4600000*15%*9/12 = | $517,500 | ||
(8315000- 4600000)*11.20%*9/12 = | $312,060 | ||
Total interest capitalized in 2019 | $829,560 |
Solution 2:
Computation of Cost of Building | |
Total expenditure before capitalization(9621000-666000) | $8,955,000 |
Add: Interest capitalized in 2018 | $666,000 |
Add: Interest capitalized in 2019 | $829,560 |
Total cost of Building | $10,450,560 |
Solution 3:
Computation of Interest expense | |||
Debt | Amount | Interest rate | Interest amount |
Construction Loan | $4,600,000 | 15% | $690,000 |
8% Note | $2,000,000 | 8% | $160,000 |
12% Note | $8,000,000 | 12% | $960,000 |
Total interest incurred | $1,810,000 | ||
2018 | 2019 | ||
Total inerest incurred | $1,810,000 | $1,810,000 | |
Less: Interest Capitalized | $666,000 | $829,560 | |
Interest Expense | $1,144,000 | $980,440 |
Problem 10-9 Interest capitalization; specific interest method (LO10-7) On January 1, 2018, the Mason Manufacturing Company...
Problem 10-9 Interest capitalization; specific interest method [LO10-7) On January 1, 2018, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2019 Expenditures on the project were as follows: January 1, 2018 March 1, 2018 June 30, 2018 October 1, 2018 January 31, 2019 April 30, 2019 August 31, 2019 $2,050,000 1,800,000 2,800,000 1,800,000 450,000 783,000 1,080,000 On January 1, 2018, the company obtained a $5,000,000...
Problem 10-9 Interest capitalization; specific interest method (L010-7] On January 1, 2018, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30.2019 Expenditures on the project were as follows: January 1 2018 March 1, 2018 June 30, 2018 October 2016 January 31, 2019 April 30, 2019 August 31, 2019 $1,870,000 1,560, ate 1,760,089 1,560, eee 214.000 747 1,044,999 On January 1 2018, the company obtained a $4,600,000...
Problem 10-10 Interest capitalization; weighted average method (LO10-7) On January 1, 2018, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2019. Expenditures on the project were as follows: January 1, 2018 March 1, 2018 June 30, 2018 October 1, 2018 January 31, 2019 April 30, 2019 August 31, 2019 $1,360,000 810,000 160,000 670,000 585,000 900,000 1,530,000 On January 1, 2018, the company obtained a $3...
Problem 10-9 (Static) Interest capitalization, specific interest method (LO10-7] On January 1, 2021, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2022. Expenditures on the project were as follows: January 1, 2021 March 1, 2021 June 30, 2021 October 1, 2021 January 31, 2022 April 30, 2022 August 31, 2022 $1,000,000 600,000 800,000 600,000 270,000 585,000 900,000 On January 1, 2021, the company obtained a...
Problem 10-9 (Static) Interest capitalization; specific interest method [LO10-7) On January 1, 2021, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2022. Expenditures on the project were as follows: January 1, 2021 March 1, 2021 June 30, 2021 October 1, 2021 January 31, 2022 April 30, 2022 August 31, 2022 $1,000,000 600,000 800.000 600,000 270,000 585.000 900.000 On January 1, 2021, the company obtained a...
Problem 10-9 (Static) Interest capitalization; specific interest method [LO10-7] On January 1, 2021, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2022. Expenditures on the project were as follows: January 1, 2021 $ 1,000,000 March 1, 2021 600,000 June 30, 2021 800,000 October 1, 2021 600,000 January 31, 2022 270,000 April 30, 2022 585,000 August 31, 2022 900,000 On January 1, 2021, the company obtained...
Problem 10-9 (Static) Interest capitalization; specific interest method [LO10-7] On January 1, 2021, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2022. Expenditures on the project were as follows: January 1, 2021 $ 1,000,000 March 1, 2021 600,000 June 30, 2021 800,000 October 1, 2021 600,000 January 31, 2022 270,000 April 30, 2022 585,000 August 31, 2022 900,000 On January 1, 2021, the company obtained...
On January 1, 2018, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2019. Expenditures on the project were as follows: January 1, 2018 March 1, 2018 June 30, 2018 October 1, 2018 January 31, 2019 April 30, 2019 August 31, 2019 $1,350,000 1, 080, 000 1, 280,000 1,080,000 342, 000 675, 000 972, 000 On January 1, 2018, the company obtained a $3,800,000 construction loan...
On January 1, 2018, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2019. Expenditures on the project were as follows: January 1, 2018 March 1, 2018 June 30, 2018 October 1, 2018 January 31, 2019 April 30, 2019 August 31, 2019 $1,350,000 1, 080, 000 1, 280,000 1,080,000 342, 000 675, 000 972, 000 On January 1, 2018, the company obtained a $3,800,000 construction loan...
Help Save & E. Chec Problem 10-9 (Static) Interest capitalization; specific interest method [LO10-7) On January 1, 2021, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2022. Expenditures on the project were as follows: January 1, 2021 March 1, 2021 June 30, 2021 October 1, 2021 January 31, 2022 April 30, 2022 August 31, 2022 $1.000.000 600,000 800.000 600,000 270.000 585,000 900,000 mces On January...