Question

On January 1, 2018, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. T

0 0
Add a comment Improve this question Transcribed image text
Answer #1

1 Ans)  The amount of interest that Mason should capitalize using specific interest method.

1st Step- For specific borrowing the interest rate is 15%.

For general borrowing the interest rate is a) 4,000,000*8%= $320,000

b) 6,000,000*10%= $600,000

So the general interest rate is Total borrowings/Total interest=10,000,000/920,000=10.87%

Total interest to be capitalized in 2018-

Date Particulars Specific($) General($)   Total($)

Jan 1,2018 1350000*15% 202,500 202,500

Mar 1,2018 1080000*15%*10/12 135,000 135,000

June 30,2018 1280000*15%*6/12 96,000 96,000

Oct 1,2018 90000*15%*3/12 3375 3,375

Oct 1,2018 (1080000-90000)*10.87%*3/12 254.25 254.25

Total interest to be capitalized in 2018 436,875 254.25 437,129.25

Interest to be capitalized in 2019

Opening balance-5,227,129.25

(1350000+1080000+1280000+90000+990000+436875+254.25)

Out of this 3800000 is specific portion and the rest ie, (5227129.25-3800000=1427129.25 is general portion

Date Particulars Specific($) General($) Total($)

Jan 1,2019 3800000*15%*9/12 427,500

(On specific portion for 9 months)

Jan 1,2019 1427129.25*10.87%*9/12 116,346.71

(On general portion for 9 months)

Jan 31,2019 342000*10.87%*8/12 24,783.60

Apr 30,2019 675000*10.87%*5/12 30,571.88

Aug 31,2019 972,000*10.87%*1/12 8804.70

427,500 180,506.89 608,006.89

Interest Expense 2018($) 2019($)
[(3800000*15%)+(4000000*8%)+(6000000*10%) 1,490,000
[1490000-608006.89]ie, interest capitalized should be deducted 881993.11

  

  

Add a comment
Know the answer?
Add Answer to:
On January 1, 2018, the Mason Manufacturing Company began construction of a building to be used...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • On January 1, 2018, the Mason Manufacturing Company began construction of a building to be used...

    On January 1, 2018, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2019. Expenditures on the project were as follows: January 1, 2018 March 1, 2018 June 30, 2018 October 1, 2018 January 31, 2019 April 30, 2019 August 31, 2019 $1,350,000 1, 080, 000 1, 280,000 1,080,000 342, 000 675, 000 972, 000 On January 1, 2018, the company obtained a $3,800,000 construction loan...

  • On January 1, 2018, the Mason Manufacturing Company began construction of a building to be used...

    On January 1, 2018, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2019. Expenditures on the project were as follows: January 1, 2018 $1,000,000 March 1, 2018 600,000 800,000 June 30, 2018 October 1, 2018 600,000 270,000 January 31, 2019 April 30, 2019 585,000 August 31, 2019 900,000 On January 1, 2018, the company obtained a $3 million construction loan with a 10% interest rate....

  • On January 1, 2018, the Mason Manufacturing Company began construction of a building to be used...

    On January 1, 2018, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2019. Expenditures on the project were as follows: January 1, 2018 $ 2,020,000 March 1, 2018 1,740,000 June 30, 2018 1,940,000 October 1, 2018 1,740,000 January 31, 2019 441,000 April 30, 2019 774,000 August 31, 2019 1,071,000 On January 1, 2018, the company obtained a $4,900,000 construction loan with a 12% interest rate....

  • On January 1, 2018, the Mason Manufacturing Company began construction of a building to be used...

    On January 1, 2018, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2019. Expenditures on the project were as follows: January 1, 2018 $ 1,180,000 March 1, 2018 660,000 June 30, 2018 860,000 October 1, 2018 660,000 January 31, 2019 279,000 April 30, 2019 612,000 August 31, 2019 909,000 On January 1, 2018, the company obtained a $3,100,000 construction loan with a 12% interest rate....

  • On January 1, 2018, the Mason Manufacturing Company began construction of a building to be used...

    On January 1, 2018, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2019. Expenditures on the project were as follows: January 1, 2018 March 1, 2018 June 30, 2018 October 1, 2018 January 31, 2019 April 30, 2019 August 31, 2019 $1,000.000 840,000 480.009 630.000 630,eee 945,000 1,620, DBC On January 1, 2018, the company obtained a $3 million construction loan with a 11% interest...

  • On January 1, 2021, the Mason Manufacturing Company began construction of a building to be used...

    On January 1, 2021, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2022. Expenditures on the project were as follows: January 1, 2021 $ 1,350,000 March 1, 2021 1,080,000 June 30, 2021 1,280,000 October 1, 2021 1,080,000 January 31, 2022 342,000 April 30, 2022 $675,000 August 31, 2022 $972,000 On January 1, 2021, the company obtained a $3,800,000 construction loan with a 15% interest rate....

  • help please On January 1, 2018, the Mason Manufacturing Company began construction of a building to...

    help please On January 1, 2018, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2019 Expenditures on the project were as follows: points 8 03:03:29 January 1, 2018 March 1, 2018 June 30, 2018 October 1, 2018 January 31, 2019 April 30, 2019 August 31, 2019 $1,070,000 840,000 380,000 710,000 1,170,000 1.485.000 2,700,000 eBook Print References On January 1, 2018, the company obtained a $3...

  • help please On January 1, 2018, the Mason Manufacturing Company began construction of a building to...

    help please On January 1, 2018, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2019 Expenditures on the project were as follows: January 1, 2018 March 1, 2018 June 30, 2018 October 1, 2018 January 31, 2019 April 30, 2019 August 31, 2019 $1,070,e00 840,000 380, e00 Dok nt 710,000 1,170,000 1,485,000 2,700,e0e nces On January 1, 2018, the company obtained a $3 million construction...

  • On January 1, 2018, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2019. Expenditures on the...

    On January 1, 2018, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2019. Expenditures on the project were as follows: January 1, 2018 Harch 1, 2018 June 30, 2018 October 1, 2018 January 31, 2019 April 30, 2019 August 31, 2019 $1,170,000 840,000 1,040,000 840,000 306,000 639,000 900,000 points Skipped Print On January 1, 2018, the company obtained a $3,000,000 construction loan with a 15%...

  • help please O t 2018, the Mason Manufacturing Company began construction of a building to be...

    help please O t 2018, the Mason Manufacturing Company began construction of a building to be used as its office en The bug was completed on September 30, 2019 Expenditures on the project were as follows: G . January 1, 2018 March 1, 2018 June 10, 2018 October 1, 2018 January 31, 2019 April , 2019 August 31, 2019 51,070,000 340,000 380,000 710,000 1,170,000 1,485,000 2,700,000 On January 1, 2018, the company obtained a $3 million construction loan with a...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT