On January 1, 2018, the Mason Manufacturing Company began
construction of a building to be used as its office headquarters.
The building was completed on September 30, 2019.
Expenditures on the project were as follows:
January 1, 2018 | $ | 2,020,000 | |
March 1, 2018 | 1,740,000 | ||
June 30, 2018 | 1,940,000 | ||
October 1, 2018 | 1,740,000 | ||
January 31, 2019 | 441,000 | ||
April 30, 2019 | 774,000 | ||
August 31, 2019 | 1,071,000 | ||
On January 1, 2018, the company obtained a $4,900,000 construction
loan with a 12% interest rate. The loan was outstanding all of 2018
and 2019. The company’s other interest-bearing debt included two
long-term notes of $2,000,000 and $8,000,000 with interest rates of
8% and 10%, respectively. Both notes were outstanding during all of
2018 and 2019. Interest is paid annually on all debt. The company’s
fiscal year-end is December 31.
Required:
1. Calculate the amount of interest that Mason
should capitalize in 2018 and 2019 using the specific interest
method.
2. What is the total cost of the building?
3. Calculate the amount of interest expense that
will appear in the 2018 and 2019 income statements
On January 1, 2018, the Mason Manufacturing Company began
construction of a building to be used as its office headquarters.
The building was completed on September 30, 2019.
Expenditures on the project were as follows:
January 1, 2018 | $ | 2,020,000 | |
March 1, 2018 | 1,740,000 | ||
June 30, 2018 | 1,940,000 | ||
October 1, 2018 | 1,740,000 | ||
January 31, 2019 | 441,000 | ||
April 30, 2019 | 774,000 | ||
August 31, 2019 | 1,071,000 | ||
On January 1, 2018, the company obtained a $4,900,000 construction
loan with a 12% interest rate. The loan was outstanding all of 2018
and 2019. The company’s other interest-bearing debt included two
long-term notes of $2,000,000 and $8,000,000 with interest rates of
8% and 10%, respectively. Both notes were outstanding during all of
2018 and 2019. Interest is paid annually on all debt. The company’s
fiscal year-end is December 31.
Required:
1. Calculate the amount of interest that Mason
should capitalize in 2018 and 2019 using the specific interest
method.
2. What is the total cost of the building?
3. Calculate the amount of interest expense that
will appear in the 2018 and 2019 income statements
2018 | 2019 | |||||
Interest Capitalized | $ 5,85,000 | $ 7,33,752 | ||||
Interest Expense | $ 9,63,000 | $ 8,14,248 | ||||
Cost of Building | = | $ 1,10,44,752 | ||||
Workings: | ||||||
Expenditure for 2018 | ||||||
Jan 1,2018 | $ 20,20,000 | X | 12/12 | = | $ 20,20,000 | |
March 1, 2018 | $ 17,40,000 | X | 10/12 | = | $ 14,50,000 | |
June 30, 2018 | $ 19,40,000 | X | 6/12 | = | $ 9,70,000 | |
October 1, 2018 | $ 17,40,000 | X | 3/12 | = | $ 4,35,000 | |
$ 74,40,000 | $ 48,75,000 | |||||
Interest Capitalized in 2018 | ||||||
$ 48,75,000 | X | 12.00% | = | $ 5,85,000 | ||
Expenditure for 2019 | ||||||
Jan 1, 2019 ($74,40,000+$5,85,000) | $ 80,25,000 | X | 9/9 | = | $ 80,25,000 | |
Jan 31, 2019 | $ 4,41,000 | X | 8/9 | = | $ 3,92,000 | |
April 30, 2019 | $ 7,74,000 | X | 5/9 | = | $ 4,30,000 | |
August 31. 2019 | $ 10,71,000 | X | 1/9 | = | $ 1,19,000 | |
$ 1,03,11,000 | $ 89,66,000 | |||||
Interest Capitalized in 2019 | ||||||
$ 89,66,000 | ||||||
Less: | $ 49,00,000 | X | 12.00% | X 9/12 | = | $ 4,41,000 |
$ 40,66,000 | X | 9.60% | X 9/12 | = | $ 2,92,752 | |
Interest Capitalized in 2019 | = | $ 7,33,752 | ||||
Weighted Average rate of all debt:- | ||||||
$ 20,00,000 | X | 8% | = | $ 1,60,000 | ||
$ 80,00,000 | X | 10% | = | $ 8,00,000 | ||
$ 1,00,00,000 | $ 9,60,000 | |||||
Weighted Average rate of all debt = | 9.60% | |||||
($9,60,000 / $1,00,00,000) | ||||||
Interest Expense for 2018: | ||||||
Total Interest Incurred | ($4900000*12%)+($2000000*8%)+($8000000*10%) | = | $ 15,48,000 | |||
Less : Interest Capitalized | = | $ 5,85,000 | ||||
2018 Expense | = | $ 9,63,000 | ||||
Interest Expense for 2019: | ||||||
Total Interest Incurred | = | $ 15,48,000 | ||||
Less : Interest Capitalized | = | $ 7,33,752 | ||||
2019 Expense | = | $ 8,14,248 | ||||
Cost of Building | ||||||
Expenditure for 2018 | = | $ 74,40,000 | ||||
Interest Capitalized in 2018 | = | $ 5,85,000 | ||||
Expenditure for 2019 | = | $ 22,86,000 | ||||
Interest Capitalized in 2019 | = | $ 7,33,752 | ||||
Cost of Building | = | $ 1,10,44,752 |
On January 1, 2018, the Mason Manufacturing Company began construction of a building to be used...
On January 1, 2018, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2019. Expenditures on the project were as follows: January 1, 2018 $ 1,180,000 March 1, 2018 660,000 June 30, 2018 860,000 October 1, 2018 660,000 January 31, 2019 279,000 April 30, 2019 612,000 August 31, 2019 909,000 On January 1, 2018, the company obtained a $3,100,000 construction loan with a 12% interest rate....
On January 1, 2018, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2019. Expenditures on the project were as follows: January 1, 2018 $1,000,000 March 1, 2018 600,000 800,000 June 30, 2018 October 1, 2018 600,000 270,000 January 31, 2019 April 30, 2019 585,000 August 31, 2019 900,000 On January 1, 2018, the company obtained a $3 million construction loan with a 10% interest rate....
help please On January 1, 2018, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2019 Expenditures on the project were as follows: points 8 03:03:29 January 1, 2018 March 1, 2018 June 30, 2018 October 1, 2018 January 31, 2019 April 30, 2019 August 31, 2019 $1,070,000 840,000 380,000 710,000 1,170,000 1.485.000 2,700,000 eBook Print References On January 1, 2018, the company obtained a $3...
help please On January 1, 2018, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2019 Expenditures on the project were as follows: January 1, 2018 March 1, 2018 June 30, 2018 October 1, 2018 January 31, 2019 April 30, 2019 August 31, 2019 $1,070,e00 840,000 380, e00 Dok nt 710,000 1,170,000 1,485,000 2,700,e0e nces On January 1, 2018, the company obtained a $3 million construction...
On January 1, 2018, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2019. Expenditures on the project were as follows: January 1, 2018 March 1, 2018 June 30, 2018 October 1, 2018 January 31, 2019 April 30, 2019 August 31, 2019 $1,000.000 840,000 480.009 630.000 630,eee 945,000 1,620, DBC On January 1, 2018, the company obtained a $3 million construction loan with a 11% interest...
On January 1, 2018, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2019. Expenditures on the project were as follows: January 1, 2018 March 1, 2018 June 30, 2018 October 1, 2018 January 31, 2019 April 30, 2019 August 31, 2019 $1,350,000 1, 080, 000 1, 280,000 1,080,000 342, 000 675, 000 972, 000 On January 1, 2018, the company obtained a $3,800,000 construction loan...
On January 1, 2018, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2019. Expenditures on the project were as follows: January 1, 2018 March 1, 2018 June 30, 2018 October 1, 2018 January 31, 2019 April 30, 2019 August 31, 2019 $1,350,000 1, 080, 000 1, 280,000 1,080,000 342, 000 675, 000 972, 000 On January 1, 2018, the company obtained a $3,800,000 construction loan...
On January 1, 2021, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2022. Expenditures on the project were as follows: January 1, 2021 $ 1,740,000 March 1, 2021 1,380,000 June 30, 2021 1,580,000 October 1, 2021 1,380,000 January 31, 2022 387,000 April 30, 2022 720,000 August 31, 2022 1,017,000 On January 1, 2021, the company obtained a $4,300,000 construction loan with a 12% interest rate....
On January 1, 2021, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2022. Expenditures on the project were as follows: January 1, 2021 $ 1,740,000 March 1, 2021 1,380,000 June 30, 2021 1,580,000 October 1, 2021 1,380,000 January 31, 2022 387,000 April 30, 2022 720,000 August 31, 2022 1,017,000 On January 1, 2021, the company obtained a $4,300,000 construction loan with a 12% interest rate....
On January 1, 2021, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2022. Expenditures on the project were as follows: January 1, 2021 $ 1,740,000 March 1, 2021 1,380,000 June 30, 2021 1,580,000 October 1, 2021 1,380,000 January 31, 2022 387,000 April 30, 2022 720,000 August 31, 2022 1,017,000 On January 1, 2021, the company obtained a $4,300,000 construction loan with a 12% interest rate....