Question

On January 1, 2021, the Mason Manufacturing Company began construction of a building to be used as its office headquarte...

On January 1, 2021, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2022. Expenditures on the project were as follows:

January 1, 2021 $ 1,740,000
March 1, 2021 1,380,000
June 30, 2021 1,580,000
October 1, 2021 1,380,000
January 31, 2022 387,000
April 30, 2022 720,000
August 31, 2022 1,017,000


On January 1, 2021, the company obtained a $4,300,000 construction loan with a 12% interest rate. The loan was outstanding all of 2021 and 2022. The company’s other interest-bearing debt included two long-term notes of $3,000,000 and $7,000,000 with interest rates of 8% and 10%, respectively. Both notes were outstanding during all of 2021 and 2022. Interest is paid annually on all debt. The company’s fiscal year-end is December 31.

Required:
1. Calculate the amount of interest that Mason should capitalize in 2021 and 2022 using the specific interest method.
2. What is the total cost of the building?
3. Calculate the amount of interest expense that will appear in the 2021 and 2022 income statements.



0 0
Add a comment Improve this question Transcribed image text
Answer #1

Solution 1:

Year 2021: Weighted-Average accumulated expenditure and interest capitalized
Date Amount Capitalization period Weighted Average Accumulated Expenditures
1-Jan-21 $1,740,000 12/12 $1,740,000
1-Mar-21 $1,380,000 10/12 $1,150,000
30-Jun-21 $1,580,000 6/12 $790,000
1-Oct-21 $1,380,000 3/12 $345,000
Total $6,080,000 $4,025,000
*Interest rate 12%
Interest capitalized in 2021 $483,000
Year 2022: Weighted-Average accumulated expenditure
Date Amount Capitalization period Weighted Average Accumulated Expenditures
1-Jan-22 $6,563,000 9/9 $6,563,000
31-Jan-22 $387,000 8/9 $344,000
30-Apr-22 $720,000 5/9 $400,000
31-Aug-22 $1,017,000 1/9 $113,000
Total $8,687,000 $7,420,000
Weighted average interest rate of all other debt
Debt Amount Interest rate Interest amount
8% Note $3,000,000 8% $240,000
10% Note $7,000,000 10% $700,000
Totals $10,000,000 $940,000
Weighted average rate (total interets/ total debt) 9.40%
Year 2022: Interest Capitalized
Debt Amount
4300000*12%*9/12 = $225,000
(7400000- 4300000)*9.40%*9/12 = $218,550
Total interest capitalized in 2022 $443,550

Solution 2:

Computation of Cost of Building
Total expenditure before capitalization(8687000-483000) $8,204,000
Add: Interest capitalized in 2021 $483,000
Add: Interest capitalized in 2022 $443,550
Total cost of Building $9,130,550

Solution 3:

Computation of Interest expense
Debt Amount Interest rate Interest amount
Construction Loan $4,300,000 12% $516,000
6% Note $3,000,000 8% $240,000
8% Note $7,000,000 10% $700,000
Total interest incurred $1,456,000
2021 2022
Total interest incurred $1,456,000 $1,456,000
Less: Interest Capitalized $483,000 $443,550
Interest Expense $973,000 $1,012,450
Add a comment
Know the answer?
Add Answer to:
On January 1, 2021, the Mason Manufacturing Company began construction of a building to be used as its office headquarte...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • On January 1, 2021, the Mason Manufacturing Company began construction of a building to be used...

    On January 1, 2021, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2022. Expenditures on the project were as follows: January 1, 2021 $ 1,740,000 March 1, 2021 1,380,000 June 30, 2021 1,580,000 October 1, 2021 1,380,000 January 31, 2022 387,000 April 30, 2022 720,000 August 31, 2022 1,017,000 On January 1, 2021, the company obtained a $4,300,000 construction loan with a 12% interest rate....

  • On January 1, 2021, the Mason Manufacturing Company began construction of a building to be used...

    On January 1, 2021, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2022. Expenditures on the project were as follows: January 1, 2021 $ 1,740,000 March 1, 2021 1,380,000 June 30, 2021 1,580,000 October 1, 2021 1,380,000 January 31, 2022 387,000 April 30, 2022 720,000 August 31, 2022 1,017,000 On January 1, 2021, the company obtained a $4,300,000 construction loan with a 12% interest rate....

  • On January 1, 2021, the Mason Manufacturing Company began construction of a building to be used...

    On January 1, 2021, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2022. Expenditures on the project were as follows: January 1, 2021 March 1, 2021 June 30, 2021 October 1, 2021 January 31, 2022 April 30, 2022 August 31, 2022 $1,740,000 1,380,000 1, 580,000 1, 380,000 387,000 720,000 1, 017, 000 On January 1, 2021, the company obtained a $4,300,000 construction loan with a...

  • On January 1, 2021, the Mason Manufacturing Company began construction of a building to be used...

    On January 1, 2021, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2022. Expenditures on the project were as follows: January 1, 2021 March 1, 2021 June 30, 2021 October 1, 2021 January 31, 2022 April 30, 2022 August 31, 2022 $1,280,000 720,000 920,000 720,000 288,000 621,000 918,000 On January 1, 2021, the company obtained a $3,200,000 construction loan with a 15% interest rate. The...

  • On January 1, 2021, the Mason Manufacturing Company began construction of a building to be used...

    On January 1, 2021, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2022. Expenditures on the project were as follows: January 1, 2021 March 1, 2021 June 30, 2021 October 1, 2021 $1,280,000 720,000 920,000 720,000 288,000 621,000 918,000 January 31, 2022 April 30, 2022 August 31, 2022 On January 1, 2021, the com 2021 and 2022. The company's other interest-bearing debt included two long-term...

  • On January 1, 2021, the Mason Manufacturing Company began construction of a building to be used...

    On January 1, 2021, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2022. Expenditures on the project were as follows: January 1, 2021 $ 1,310,000 March 1, 2021 1,020,000 June 30, 2021 1,220,000 October 1, 2021 1,020,000 January 31, 2022 333,000 April 30, 2022 666,000 August 31, 2022 963,000 On January 1, 2021, the company obtained a $3,700,000 construction loan with a 12% interest rate....

  • On January 1, 2021, the Mason Manufacturing Company began construction of a building to be used as its office headquarte...

    On January 1, 2021, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2022. Expenditures on the project were as follows: January 1, 2021 $ 1,680,000 March 1, 2021 1,260,000 June 30, 2021 1,460,000 October 1, 2021 1,260,000 January 31, 2022 369,000 April 30, 2022 702,000 August 31, 2022 999,000 On January 1, 2021, the company obtained a $4,000,000 construction loan with a 12% interest rate....

  • On January 1, 2021, the Mason Manufacturing Company began construction of a building to be used as its office headquart...

    On January 1, 2021, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2022. Expenditures on the project were as follows: January 1, 2021 March 1, 2021 June 30, 2021 October 1, 2021 January 31, 2022 April 30, 2022 August 31, 2022 $1,310,000 1,020,000 1,220,000 1,020,000 333,000 666,000 963,000 On January 1, 2021, the company obtained a $3,700,000 construction loan with a 12% interest rate. The...

  • On January 1, 2021, the Mason Manufacturing Company began construction of a building to be used...

    On January 1, 2021, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2022. Expenditures on the project were as follows: January 1, 2021 $ 1,000,000 March 1, 2021 600,000 June 30, 2021 800,000 October 1, 2021 600,000 January 31, 2022 270,000 April 30, 2022 585,000 August 31, 2022 900,000 On January 1, 2021, the company obtained a $3 million construction loan with a 10% interest...

  • On January 1, 2021, the Mason Manufacturing Company began construction of a building to be used...

    On January 1, 2021, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2022. Expenditures on the project were as follows: January 1, 2021 $ 1,500,000 March 1, 2021 1,200,000 June 30, 2021 1,400,000 October 1, 2021 1,200,000 January 31, 2022 360,000 April 30, 2022 693,000 August 31, 2022 990,000 On January 1, 2021, the company obtained a $4,000,000 construction loan with a 14% interest rate....

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT