Question

On January 1, 2021, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. T

0 0
Add a comment Improve this question Transcribed image text
Answer #1
2021 2022
Interest Capitalized $               3,78,000 $         5,01,453
Interest Expense $            13,42,000 $       12,18,547
Cost of Building = $       63,46,453
Workings:
Expenditure for 2021
Jan 1,2021 $            12,80,000 X 12/12 = $        12,80,000
March 1, 2021 $               7,20,000 X 10/12 = $          6,00,000
June 30, 2021 $               9,20,000 X 6/12 = $          4,60,000
October 1, 2021 $               7,20,000 X 3/12 = $          1,80,000
$            36,40,000 $        25,20,000
Interest Capitalized in 2021
$            25,20,000 X 15.00% = $          3,78,000
Expenditure for 2022
Jan 1, 2022 ($3640000+$378000) $            40,18,000 X 9/9 = $        40,18,000
Jan 31, 2022 $               2,88,000 X 8/9 = $          2,56,000
April 30, 2022 $               6,21,000 X 5/9 = $          3,45,000
August 31. 2022 $               9,18,000 X 1/9 = $          1,02,000
$            58,45,000 $        47,21,000
Interest Capitalized in 2020
$                       47,21,000
Less: $                       32,00,000 X 15.00% X 9/12 = $          3,60,000
$                       15,21,000 X 12.40% X 9/12 = $          1,41,453
Interest Capitalized in 2020 = $          5,01,453
Weighted Average rate of all debt:-
$            30,00,000 X 11% = $          3,30,000
$            70,00,000 X 13% = $          9,10,000
$         1,00,00,000 $        12,40,000
Weighted Average rate of all debt = 12.40%
($1240000/ 100,00,000)
Interest Expense for 2021:
Total Interest Incurred ($3200000*15%)+($3000000*11%)+($7000000*13%) = $        17,20,000
Less : Interest Capitalized = $          3,78,000
2021 Expense = $        13,42,000
Interest Expense for 2022:
Total Interest Incurred = $        17,20,000
Less : Interest Capitalized = $          5,01,453
2022 Expense = $        12,18,547
Cost of Building
Expenditure for 2021 = $        36,40,000
Interest Capitalized in 2021 = $          3,78,000
Expenditure for 2022 = $        18,27,000
Interest Capitalized in 2022 = $          5,01,453
Cost of Building = $        63,46,453
Add a comment
Know the answer?
Add Answer to:
On January 1, 2021, the Mason Manufacturing Company began construction of a building to be used...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • On January 1, 2021, the Mason Manufacturing Company began construction of a building to be used...

    On January 1, 2021, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2022. Expenditures on the project were as follows: January 1, 2021 March 1, 2021 June 30, 2021 October 1, 2021 January 31, 2022 April 30, 2022 August 31, 2022 $1,280,000 720,000 920,000 720,000 288,000 621,000 918,000 On January 1, 2021, the company obtained a $3,200,000 construction loan with a 15% interest rate. The...

  • On January 1, 2021, the Mason Manufacturing Company began construction of a building to be used...

    On January 1, 2021, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2022. Expenditures on the project were as follows: January 1, 2021 March 1, 2021 June 30, 2021 October 1, 2021 January 31, 2022 April 30, 2022 August 31, 2022 $1,740,000 1,380,000 1, 580,000 1, 380,000 387,000 720,000 1, 017, 000 On January 1, 2021, the company obtained a $4,300,000 construction loan with a...

  • On January 1, 2021, the Mason Manufacturing Company began construction of a building to be used...

    On January 1, 2021, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2022. Expenditures on the project were as follows: January 1, 2021 $ 1,740,000 March 1, 2021 1,380,000 June 30, 2021 1,580,000 October 1, 2021 1,380,000 January 31, 2022 387,000 April 30, 2022 720,000 August 31, 2022 1,017,000 On January 1, 2021, the company obtained a $4,300,000 construction loan with a 12% interest rate....

  • On January 1, 2021, the Mason Manufacturing Company began construction of a building to be used...

    On January 1, 2021, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2022. Expenditures on the project were as follows: January 1, 2021 $ 1,740,000 March 1, 2021 1,380,000 June 30, 2021 1,580,000 October 1, 2021 1,380,000 January 31, 2022 387,000 April 30, 2022 720,000 August 31, 2022 1,017,000 On January 1, 2021, the company obtained a $4,300,000 construction loan with a 12% interest rate....

  • On January 1, 2021, the Mason Manufacturing Company began construction of a building to be used...

    On January 1, 2021, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2022. Expenditures on the project were as follows: January 1, 2021 March 1, 2021 June 30, 2021 October 1, 2021 January 31, 2022 April 30, 2022 August 31, 2022 $1,280,000 960,000 1,160,000 960,000 324,000 657,000 954,000 On January 1, 2021, the company obtained a $3,600,000 construction loan with a 15% interest rate. The...

  • On January 1, 2021, the Mason Manufacturing Company began construction of a building to be used...

    On January 1, 2021, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2022. Expenditures on the project were as follows: January 1, 2021 $ 1,350,000 March 1, 2021 1,080,000 June 30, 2021 1,280,000 October 1, 2021 1,080,000 January 31, 2022 342,000 April 30, 2022 $675,000 August 31, 2022 $972,000 On January 1, 2021, the company obtained a $3,800,000 construction loan with a 15% interest rate....

  • On January 1, 2021, the Mason Manufacturing Company began construction of a building to be used as its office headquarte...

    On January 1, 2021, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2022. Expenditures on the project were as follows: January 1, 2021 $ 1,740,000 March 1, 2021 1,380,000 June 30, 2021 1,580,000 October 1, 2021 1,380,000 January 31, 2022 387,000 April 30, 2022 720,000 August 31, 2022 1,017,000 On January 1, 2021, the company obtained a $4,300,000 construction loan with a 12% interest rate....

  • On January 1, 2021, the Mason Manufacturing Company began construction of a building to be used...

    On January 1, 2021, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2022. Expenditures on the project were as follows: January 1, 2021 $ 1,310,000 March 1, 2021 1,020,000 June 30, 2021 1,220,000 October 1, 2021 1,020,000 January 31, 2022 333,000 April 30, 2022 666,000 August 31, 2022 963,000 On January 1, 2021, the company obtained a $3,700,000 construction loan with a 12% interest rate....

  • On January 1, 2021, the Mason Manufacturing Company began construction of a building to be used as its office headquart...

    On January 1, 2021, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2022. Expenditures on the project were as follows: January 1, 2021 March 1, 2021 June 30, 2021 October 1, 2021 January 31, 2022 April 30, 2022 August 31, 2022 $1,310,000 1,020,000 1,220,000 1,020,000 333,000 666,000 963,000 On January 1, 2021, the company obtained a $3,700,000 construction loan with a 12% interest rate. The...

  • On January 1, 2021, the Mason Manufacturing Company began construction of a building to be used...

    On January 1, 2021, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2022. Expenditures on the project were as follows: January 1, 2021 March 1, 2021 June 30, 2021 October 1, 2021 January 31, 2022 April 30, 2022 August 31, 2022 $1,310,000 1,020,000 1,220,000 1,020,000 333,000 666,000 963,000 On January 1, 2021, the company obtained a $3,700,000 construction loan with a 12% interest rate. The...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT