Statement No. 34 issued by Financial Accounting Standard Board in 1979, lays down principles for Capitalization of Interest cost for certain assets. Business can use specific method or weighted average method to determine portion of interest cost to be capitalized.
In light of given principles, we shall answer following questions one by one.
(Question : 1 ) Amount of Interest to be Capitalized in 2021 and 2022:
Step: 1 For year 2021, determine average accumulated expenditure.
Step: 2 Calculate Interest Cost to be Capitalized:
Interest cost to be capitalized for 2021 = $2,520,000 X 15% (Using Construction Loan)
= $378,000
Amount of interest cost to be capitalized in 2021 = $378,000
Account balance of asset at end of 2021 = ($1,280,000 + $720,000 + $920,000 + $720,000) + $378,000 = $4,018,000
Step 3: For year 2022, determine average accumulated expenditure:
It can be noticed that actual average accumulated expenditure in $4,721,000 which exceeds amount o construction loan of $3,200,000. hence it can be said that difference portion of expenditure of $1,521,000 ($4,721,000 - $3,200,000) is funded by utilization of Two long term notes.
Step 4: To calculate Interest cost to be capitalized, we need to find out Weighted average rate of Interest for long term notes:
Weighted average rate of interest = $1,240,000 / ($3,000,000 + $7,000,000) X 100
= 12.4%
Interest cost to be capitalized on 2022 = [($3,200,000 X 15%) + ($1,521,000 X 12.4%)] X 9/12
= ($480,000 + $188,604) X 9/12
= ($480,000 X 9/12) + ($188,604 X 9/12)
= $360,000 + $141,453
= $501,453
Amount of interest cost to be capitalized in 2022 = $501,453
Amount of Interest to be capitalized:
For Year 2021 = $378,000
For Year 2022 = $501,453
(Question 2) Total Cost of Building:
Total Cost of Building = Expenditures + Interest cost to be capitalized
=($1,280,000 + $720,000 + $920,000 + $720,000 + $288,000 + $621,000 + $918,000 ) + $378,000 + $501,453
= $6,346,453
(Question 3) Amount of Interest expense for Year 2021 and 2022:
On January 1, 2021, the Mason Manufacturing Company began construction of a building to be used...
On January 1, 2021, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2022. Expenditures on the project were as follows: January 1, 2021 March 1, 2021 June 30, 2021 October 1, 2021 $1,280,000 720,000 920,000 720,000 288,000 621,000 918,000 January 31, 2022 April 30, 2022 August 31, 2022 On January 1, 2021, the com 2021 and 2022. The company's other interest-bearing debt included two long-term...
On January 1, 2021, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2022. Expenditures on the project were as follows: January 1, 2021 March 1, 2021 June 30, 2021 October 1, 2021 January 31, 2022 April 30, 2022 August 31, 2022 $1,740,000 1,380,000 1, 580,000 1, 380,000 387,000 720,000 1, 017, 000 On January 1, 2021, the company obtained a $4,300,000 construction loan with a...
On January 1, 2021, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2022. Expenditures on the project were as follows: January 1, 2021 $ 1,740,000 March 1, 2021 1,380,000 June 30, 2021 1,580,000 October 1, 2021 1,380,000 January 31, 2022 387,000 April 30, 2022 720,000 August 31, 2022 1,017,000 On January 1, 2021, the company obtained a $4,300,000 construction loan with a 12% interest rate....
On January 1, 2021, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2022. Expenditures on the project were as follows: January 1, 2021 $ 1,740,000 March 1, 2021 1,380,000 June 30, 2021 1,580,000 October 1, 2021 1,380,000 January 31, 2022 387,000 April 30, 2022 720,000 August 31, 2022 1,017,000 On January 1, 2021, the company obtained a $4,300,000 construction loan with a 12% interest rate....
On January 1, 2021, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2022. Expenditures on the project were as follows: January 1, 2021 March 1, 2021 June 30, 2021 October 1, 2021 January 31, 2022 April 30, 2022 August 31, 2022 $1,280,000 960,000 1,160,000 960,000 324,000 657,000 954,000 On January 1, 2021, the company obtained a $3,600,000 construction loan with a 15% interest rate. The...
On January 1, 2021, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2022. Expenditures on the project were as follows: January 1, 2021 $ 1,350,000 March 1, 2021 1,080,000 June 30, 2021 1,280,000 October 1, 2021 1,080,000 January 31, 2022 342,000 April 30, 2022 $675,000 August 31, 2022 $972,000 On January 1, 2021, the company obtained a $3,800,000 construction loan with a 15% interest rate....
On January 1, 2021, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2022. Expenditures on the project were as follows: January 1, 2021 $ 1,740,000 March 1, 2021 1,380,000 June 30, 2021 1,580,000 October 1, 2021 1,380,000 January 31, 2022 387,000 April 30, 2022 720,000 August 31, 2022 1,017,000 On January 1, 2021, the company obtained a $4,300,000 construction loan with a 12% interest rate....
On January 1, 2021, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2022. Expenditures on the project were as follows: January 1, 2021 $ 1,310,000 March 1, 2021 1,020,000 June 30, 2021 1,220,000 October 1, 2021 1,020,000 January 31, 2022 333,000 April 30, 2022 666,000 August 31, 2022 963,000 On January 1, 2021, the company obtained a $3,700,000 construction loan with a 12% interest rate....
On January 1, 2021, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2022. Expenditures on the project were as follows: January 1, 2021 March 1, 2021 June 30, 2021 October 1, 2021 January 31, 2022 April 30, 2022 August 31, 2022 $1,310,000 1,020,000 1,220,000 1,020,000 333,000 666,000 963,000 On January 1, 2021, the company obtained a $3,700,000 construction loan with a 12% interest rate. The...
On January 1, 2021, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2022. Expenditures on the project were as follows: January 1, 2021 March 1, 2021 June 30, 2021 October 1, 2021 January 31, 2022 April 30, 2022 August 31, 2022 $1,310,000 1,020,000 1,220,000 1,020,000 333,000 666,000 963,000 On January 1, 2021, the company obtained a $3,700,000 construction loan with a 12% interest rate. The...