Question


On January 1, 2021, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. T

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Statement No. 34 issued by Financial Accounting Standard Board in 1979, lays down principles for Capitalization of Interest cost for certain assets. Business can use specific method or weighted average method to determine portion of interest cost to be capitalized.

In light of given principles, we shall answer following questions one by one.

(Question : 1 ) Amount of Interest to be Capitalized in 2021 and 2022:

Step: 1 For year 2021, determine average accumulated expenditure.

Expenditures Months January 01, 2021 $1,280,000 X 12/12 = March 01, 2021 $720,000 X 10/12 = June 30, 2021 $920,000 X 6/12 = O

Step: 2 Calculate Interest Cost to be Capitalized:

Interest cost to be capitalized for 2021 = $2,520,000 X 15% (Using Construction Loan)

      = $378,000

Amount of interest cost to be capitalized in 2021 = $378,000

Account balance of asset at end of 2021 = ($1,280,000 + $720,000 + $920,000 + $720,000) + $378,000 = $4,018,000

Step 3: For year 2022, determine average accumulated expenditure:

Expenditures Months January 01, 2022 $4,018,000 X 09/09 = January 31, 2022 $288,000 X 08/09 = April 30, 2022 $621,000 X 05/09

It can be noticed that actual average accumulated expenditure in $4,721,000 which exceeds amount o construction loan of $3,200,000. hence it can be said that difference portion of expenditure of $1,521,000 ($4,721,000 - $3,200,000) is funded by utilization of Two long term notes.

Step 4: To calculate Interest cost to be capitalized, we need to find out Weighted average rate of Interest for long term notes:

Long term note Interest rate $3,000,000 X 11% $7,000,000 X 13% Amount $330,000 $910,000 $1,240,000

Weighted average rate of interest = $1,240,000 / ($3,000,000 + $7,000,000) X 100

= 12.4%

Interest cost to be capitalized on 2022 = [($3,200,000 X 15%) + ($1,521,000 X 12.4%)] X 9/12

   = ($480,000 + $188,604) X 9/12

   = ($480,000 X 9/12) + ($188,604 X 9/12)

   = $360,000 + $141,453

= $501,453

Amount of interest cost to be capitalized in 2022 = $501,453

Amount of Interest to be capitalized:

For Year 2021 = $378,000

For Year 2022 = $501,453

(Question 2) Total Cost of Building:

Total Cost of Building = Expenditures + Interest cost to be capitalized

=($1,280,000 + $720,000 + $920,000 + $720,000 + $288,000 + $621,000 + $918,000 ) + $378,000 + $501,453

= $6,346,453

(Question 3) Amount of Interest expense for Year 2021 and 2022:

For Year 2021: Debt Components Rate Total Interest To be Capitalized Expense Construction Loan $3,200,000 15% $480,000 $378,0

Add a comment
Know the answer?
Add Answer to:
On January 1, 2021, the Mason Manufacturing Company began construction of a building to be used...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • On January 1, 2021, the Mason Manufacturing Company began construction of a building to be used...

    On January 1, 2021, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2022. Expenditures on the project were as follows: January 1, 2021 March 1, 2021 June 30, 2021 October 1, 2021 $1,280,000 720,000 920,000 720,000 288,000 621,000 918,000 January 31, 2022 April 30, 2022 August 31, 2022 On January 1, 2021, the com 2021 and 2022. The company's other interest-bearing debt included two long-term...

  • On January 1, 2021, the Mason Manufacturing Company began construction of a building to be used...

    On January 1, 2021, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2022. Expenditures on the project were as follows: January 1, 2021 March 1, 2021 June 30, 2021 October 1, 2021 January 31, 2022 April 30, 2022 August 31, 2022 $1,740,000 1,380,000 1, 580,000 1, 380,000 387,000 720,000 1, 017, 000 On January 1, 2021, the company obtained a $4,300,000 construction loan with a...

  • On January 1, 2021, the Mason Manufacturing Company began construction of a building to be used...

    On January 1, 2021, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2022. Expenditures on the project were as follows: January 1, 2021 $ 1,740,000 March 1, 2021 1,380,000 June 30, 2021 1,580,000 October 1, 2021 1,380,000 January 31, 2022 387,000 April 30, 2022 720,000 August 31, 2022 1,017,000 On January 1, 2021, the company obtained a $4,300,000 construction loan with a 12% interest rate....

  • On January 1, 2021, the Mason Manufacturing Company began construction of a building to be used...

    On January 1, 2021, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2022. Expenditures on the project were as follows: January 1, 2021 $ 1,740,000 March 1, 2021 1,380,000 June 30, 2021 1,580,000 October 1, 2021 1,380,000 January 31, 2022 387,000 April 30, 2022 720,000 August 31, 2022 1,017,000 On January 1, 2021, the company obtained a $4,300,000 construction loan with a 12% interest rate....

  • On January 1, 2021, the Mason Manufacturing Company began construction of a building to be used...

    On January 1, 2021, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2022. Expenditures on the project were as follows: January 1, 2021 March 1, 2021 June 30, 2021 October 1, 2021 January 31, 2022 April 30, 2022 August 31, 2022 $1,280,000 960,000 1,160,000 960,000 324,000 657,000 954,000 On January 1, 2021, the company obtained a $3,600,000 construction loan with a 15% interest rate. The...

  • On January 1, 2021, the Mason Manufacturing Company began construction of a building to be used...

    On January 1, 2021, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2022. Expenditures on the project were as follows: January 1, 2021 $ 1,350,000 March 1, 2021 1,080,000 June 30, 2021 1,280,000 October 1, 2021 1,080,000 January 31, 2022 342,000 April 30, 2022 $675,000 August 31, 2022 $972,000 On January 1, 2021, the company obtained a $3,800,000 construction loan with a 15% interest rate....

  • On January 1, 2021, the Mason Manufacturing Company began construction of a building to be used as its office headquarte...

    On January 1, 2021, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2022. Expenditures on the project were as follows: January 1, 2021 $ 1,740,000 March 1, 2021 1,380,000 June 30, 2021 1,580,000 October 1, 2021 1,380,000 January 31, 2022 387,000 April 30, 2022 720,000 August 31, 2022 1,017,000 On January 1, 2021, the company obtained a $4,300,000 construction loan with a 12% interest rate....

  • On January 1, 2021, the Mason Manufacturing Company began construction of a building to be used...

    On January 1, 2021, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2022. Expenditures on the project were as follows: January 1, 2021 $ 1,310,000 March 1, 2021 1,020,000 June 30, 2021 1,220,000 October 1, 2021 1,020,000 January 31, 2022 333,000 April 30, 2022 666,000 August 31, 2022 963,000 On January 1, 2021, the company obtained a $3,700,000 construction loan with a 12% interest rate....

  • On January 1, 2021, the Mason Manufacturing Company began construction of a building to be used as its office headquart...

    On January 1, 2021, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2022. Expenditures on the project were as follows: January 1, 2021 March 1, 2021 June 30, 2021 October 1, 2021 January 31, 2022 April 30, 2022 August 31, 2022 $1,310,000 1,020,000 1,220,000 1,020,000 333,000 666,000 963,000 On January 1, 2021, the company obtained a $3,700,000 construction loan with a 12% interest rate. The...

  • On January 1, 2021, the Mason Manufacturing Company began construction of a building to be used...

    On January 1, 2021, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2022. Expenditures on the project were as follows: January 1, 2021 March 1, 2021 June 30, 2021 October 1, 2021 January 31, 2022 April 30, 2022 August 31, 2022 $1,310,000 1,020,000 1,220,000 1,020,000 333,000 666,000 963,000 On January 1, 2021, the company obtained a $3,700,000 construction loan with a 12% interest rate. The...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT