Question

On January 1, 2021, the Mason Manufacturing Company began construction of a building to be used...

On January 1, 2021, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2022. Expenditures on the project were as follows:

January 1, 2021 $ 1,500,000
March 1, 2021 1,200,000
June 30, 2021 1,400,000
October 1, 2021 1,200,000
January 31, 2022 360,000
April 30, 2022 693,000
August 31, 2022 990,000


On January 1, 2021, the company obtained a $4,000,000 construction loan with a 14% interest rate. The loan was outstanding all of 2021 and 2022. The company’s other interest-bearing debt included two long-term notes of $1,000,000 and $4,000,000 with interest rates of 10% and 12%, respectively. Both notes were outstanding during all of 2021 and 2022. Interest is paid annually on all debt. The company’s fiscal year-end is December 31.

Required:
1. Calculate the amount of interest that Mason should capitalize in 2021 and 2022 using the specific interest method.
2. What is the total cost of the building?
3. Calculate the amount of interest expense that will appear in the 2021 and 2022 income statements.

Calculate the amount of interest that Mason should capitalize in 2021 and 2022 using the specific interest method and interest expense that will appear in the 2021 and 2022 income statements. (Do not round intermediate calculations.)

2021 2022
Interest capitalized
Interest expense

What is the total cost of the building? (Do not round intermediate calculations.)

Total cost of building
0 0
Add a comment Improve this question Transcribed image text
Answer #1

Capitalization period C =B/12 Average Accumulated Expenditures D = (AXC) Year 2021 Months outstanding from Date of ConstructiIn Year 2022 Beginning Expenditure cost (5,300,000 + 490,000) = 5,790,000 Calculation of weighted Average Accumulated ExpendiCalculation of Interest to be capitalized for 9 Months Total Average Accumulated Expenditures 6,605,000 Interest rate Amount

2) Cost of Building 1,500,000 1,200,000 1,400,000 1,200,000 $ 5,300,000 490,000 Expenditures incurred in 2018 January 01, 202

Add a comment
Know the answer?
Add Answer to:
On January 1, 2021, the Mason Manufacturing Company began construction of a building to be used...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • On January 1, 2021, the Mason Manufacturing Company began construction of a building to be used...

    On January 1, 2021, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2022. Expenditures on the project were as follows: January 1, 2021 March 1, 2021 June 30, 2021 October 1, 2021 January 31, 2022 April 30, 2022 August 31, 2022 $1,280,000 960,000 1,160,000 960,000 324,000 657,000 954,000 On January 1, 2021, the company obtained a $3,600,000 construction loan with a 15% interest rate. The...

  • On January 1, 2021, the Mason Manufacturing Company began construction of a building to be used...

    On January 1, 2021, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2022. Expenditures on the project were as follows: January 1, 2021 $ 1,350,000 March 1, 2021 1,080,000 June 30, 2021 1,280,000 October 1, 2021 1,080,000 January 31, 2022 342,000 April 30, 2022 $675,000 August 31, 2022 $972,000 On January 1, 2021, the company obtained a $3,800,000 construction loan with a 15% interest rate....

  • On January 1, 2021, the Mason Manufacturing Company began construction of a building to be used as its office headquarte...

    On January 1, 2021, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2022. Expenditures on the project were as follows: January 1, 2021 $ 1,680,000 March 1, 2021 1,260,000 June 30, 2021 1,460,000 October 1, 2021 1,260,000 January 31, 2022 369,000 April 30, 2022 702,000 August 31, 2022 999,000 On January 1, 2021, the company obtained a $4,000,000 construction loan with a 12% interest rate....

  • On January 1, 2021, the Mason Manufacturing Company began construction of a building to be used...

    On January 1, 2021, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2022. Expenditures on the project were as follows: January 1, 2021 $ 1,310,000 March 1, 2021 1,020,000 June 30, 2021 1,220,000 October 1, 2021 1,020,000 January 31, 2022 333,000 April 30, 2022 666,000 August 31, 2022 963,000 On January 1, 2021, the company obtained a $3,700,000 construction loan with a 12% interest rate....

  • On January 1, 2021, the Mason Manufacturing Company began construction of a building to be used...

    On January 1, 2021, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2022. Expenditures on the project were as follows: January 1, 2021 $ 1,740,000 March 1, 2021 1,380,000 June 30, 2021 1,580,000 October 1, 2021 1,380,000 January 31, 2022 387,000 April 30, 2022 720,000 August 31, 2022 1,017,000 On January 1, 2021, the company obtained a $4,300,000 construction loan with a 12% interest rate....

  • On January 1, 2021, the Mason Manufacturing Company began construction of a building to be used...

    On January 1, 2021, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2022. Expenditures on the project were as follows: January 1, 2021 $ 1,740,000 March 1, 2021 1,380,000 June 30, 2021 1,580,000 October 1, 2021 1,380,000 January 31, 2022 387,000 April 30, 2022 720,000 August 31, 2022 1,017,000 On January 1, 2021, the company obtained a $4,300,000 construction loan with a 12% interest rate....

  • On January 1, 2021, the Mason Manufacturing Company began construction of a building to be used...

    On January 1, 2021, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2022. Expenditures on the project were as follows: January 1, 2021 March 1, 2021 June 30, 2021 October 1, 2021 January 31, 2022 April 30, 2022 August 31, 2022 $1,420,000 1,140,000 1,340,000 1,140,000 351,000 684,000 981,000 On January 1, 2021, the company obtained a $3,900,000 construction loan with a 12% interest rate. The...

  • On January 1, 2021, the Mason Manufacturing Company began construction of a building to be used...

    On January 1, 2021, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2022. Expenditures on the project were as follows: January 1, 2021 $ 1,000,000 March 1, 2021 600,000 June 30, 2021 800,000 October 1, 2021 600,000 January 31, 2022 270,000 April 30, 2022 585,000 August 31, 2022 900,000 On January 1, 2021, the company obtained a $3 million construction loan with a 10% interest...

  • On January 1, 2021, the Mason Manufacturing Company began construction of a building to be used...

    On January 1, 2021, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2022. Expenditures on the project were as follows: January 1, 2021 March 1, 2021 June 30, 2021 October 1, 2021 January 31, 2022 April 30, 2022 August 31, 2022 $1,310,000 1,020,000 1,220,000 1,020,000 333,000 666,000 963,000 On January 1, 2021, the company obtained a $3,700,000 construction loan with a 12% interest rate. The...

  • On January 1, 2021, the Mason Manufacturing Company began construction of a building to be used...

    On January 1, 2021, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2022. Expenditures on the project were as follows: January 1, 2021 $ 1,090,000 March 1, 2021 780,000 June 30, 2021 980,000 October 1, 2021 780,000 January 31, 2022 297,000 April 30, 2022 630,000 August 31, 2022 927,000 On January 1, 2021, the company obtained a $3,300,000 construction loan with a 16% interest rate....

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT