Specific Interest method:
Solution 1: | |||
Year 2021: Weighted-Average accumulated expenditure and interest capitalized | |||
Date | Amount | Capitalization period | Weighted Average Accumulated Expenditures |
01 January 2021 | $10,00,000 | 12/12 | $10,00,000 |
01 March 2021 | $6,00,000 | 10/12 | $5,00,000 |
30 June 2021 | $8,00,000 | 6/12 | $4,00,000 |
01 October 2021 | $6,00,000 | 3/12 | $1,50,000 |
Total | $30,00,000 | $20,50,000 | |
*Interest rate | 10% | ||
Interest capitalized in 2021 | $2,05,000 | ||
Year 2022: Weighted-Average accumulated expenditure | |||
Date | Amount | Capitalization period | Weighted Average Accumulated Expenditures |
01 January 2022 | $32,05,000 | 9/9 | $32,05,000 |
31 January 2022 | $2,70,000 | 8/9 | $2,40,000 |
30 April 2022 | $5,85,000 | 5/9 | $3,25,000 |
31 August 2022 | $9,00,000 | 1/9 | $1,00,000 |
Total | $49,60,000 | $38,70,000 | |
Weighted average interest rate of all other debt | |||
Debt | Amount | Interest rate | Interest amount |
6% Note | $40,00,000 | 6% | $2,40,000 |
8% Note | $60,00,000 | 8% | $4,80,000 |
Totals | $1,00,00,000 | $7,20,000 | |
Weighted average rate (total interets/ total debt) | 7.20% | ||
Year 2022: Interest Capitalized | |||
Debt | Amount | ||
3000000*10%*9/12 = | $2,25,000 | ||
(3870000- 3000000)*7.20%*9/12 = | $46,980 | ||
Total interest capitalized in 2022 | $2,71,980 |
Solution 2: | |||
Computation of Cost of Building | |||
Total expenditure before capitalization(4960000-205000) | $47,55,000 | ||
Add: Interest capitalized in 2021 | $2,05,000 | ||
Add: Interest capitalized in 2021 | $2,71,980 | ||
Total cost of Building | $52,31,980 | ||
Solution 3: | |||
Computation of Interest expense | |||
Debt | Amount | Interest rate | Interest amount |
Construction Loan | $30,00,000 | 10% | $3,00,000 |
6% Note | $40,00,000 | 6% | $2,40,000 |
8% Note | $60,00,000 | 8% | $4,80,000 |
Total interest incurred | $10,20,000 | ||
2021 | 2022 | ||
Total inerest incurred | $10,20,000 | $10,20,000 | |
Less: Interest Capitalized | $2,05,000 | $2,71,980 | |
Interest Expense | $8,15,000 | $7,48,020 |
Weighted Average Method:
Solution 1: | |||
Year 2021: Weighted-Average accumulated expenditure and interest capitalized | |||
Date | Amount | Capitalization period | Weighted Average Accumulated Expenditures |
01 January 2021 | $10,00,000 | 12/12 | $10,00,000 |
01 March 2021 | $6,00,000 | 10/12 | $5,00,000 |
30 June 2021 | $8,00,000 | 6/12 | $4,00,000 |
01 October 2021 | $6,00,000 | 3/12 | $1,50,000 |
Total | $30,00,000 | $20,50,000 | |
*Interest rate | 7.85% | ||
Interest capitalized in 2021 | $1,60,925 | ||
Year 2022: Weighted-Average accumulated expenditure | |||
Date | Amount | Capitalization period | Weighted Average Accumulated Expenditures |
01 January 2022 | $31,60,925 | 9/9 | $31,60,925 |
31 January 2022 | $2,70,000 | 8/9 | $2,40,000 |
30 April 2022 | $5,85,000 | 5/9 | $3,25,000 |
31 August 2022 | $9,00,000 | 1/9 | $1,00,000 |
Total | $49,15,925 | $38,25,925 | |
*Interest rate | 7.85% | ||
Interest capitalized in 2022 | $2,25,251 | ||
Weighted average interest rate of all debt | |||
Debt | Amount | Interest rate | Interest amount |
Loan | $30,00,000 | 10% | $3,00,000 |
6% Note | $40,00,000 | 6% | $2,40,000 |
8% Note | $60,00,000 | 8% | $4,80,000 |
Totals | $1,30,00,000 | $10,20,000 | |
Weighted average rate (total interets/ total debt) | 7.85% |
Solution 2: | |||
Computation of Cost of Building | |||
Total expenditure before capitalization(4915925-160925) | $47,55,000 | ||
Add: Interest capitalized in 2021 | $1,60,925 | ||
Add: Interest capitalized in 2022 | $2,25,251 | ||
Total cost of Building | $51,41,176 | ||
Solution 3: | |||
Computation of Interest expense | |||
Debt | Amount | Interest rate | Interest amount |
Loan | $30,00,000 | 10% | $3,00,000 |
6% Note | $40,00,000 | 6% | $2,40,000 |
8% Note | $60,00,000 | 8% | $4,80,000 |
Total interest incurred | $10,20,000 | ||
2021 | 2022 | ||
Total inerest incurred | $10,20,000 | $10,20,000 | |
Less: Interest Capitalized | $1,60,925 | $2,25,251 | |
Interest Expense | $8,59,075 | $7,94,749 |
On January 1, 2018, the Mason Manufacturing Company began construction of a building to be used...
On January 1, 2018, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2019. Expenditures on the project were as follows: January 1, 2018 March 1, 2018 June 30, 2018 October 1, 2018 January 31, 2019 April 30, 2019 August 31, 2019 $1,350,000 1, 080, 000 1, 280,000 1,080,000 342, 000 675, 000 972, 000 On January 1, 2018, the company obtained a $3,800,000 construction loan...
On January 1, 2018, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2019. Expenditures on the project were as follows: January 1, 2018 March 1, 2018 June 30, 2018 October 1, 2018 January 31, 2019 April 30, 2019 August 31, 2019 $1,350,000 1, 080, 000 1, 280,000 1,080,000 342, 000 675, 000 972, 000 On January 1, 2018, the company obtained a $3,800,000 construction loan...
help please On January 1, 2018, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2019 Expenditures on the project were as follows: January 1, 2018 March 1, 2018 June 30, 2018 October 1, 2018 January 31, 2019 April 30, 2019 August 31, 2019 $1,070,e00 840,000 380, e00 Dok nt 710,000 1,170,000 1,485,000 2,700,e0e nces On January 1, 2018, the company obtained a $3 million construction...
help please On January 1, 2018, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2019 Expenditures on the project were as follows: points 8 03:03:29 January 1, 2018 March 1, 2018 June 30, 2018 October 1, 2018 January 31, 2019 April 30, 2019 August 31, 2019 $1,070,000 840,000 380,000 710,000 1,170,000 1.485.000 2,700,000 eBook Print References On January 1, 2018, the company obtained a $3...
On January 1, 2018, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2019. Expenditures on the project were as follows: January 1, 2018 $ 1,180,000 March 1, 2018 660,000 June 30, 2018 860,000 October 1, 2018 660,000 January 31, 2019 279,000 April 30, 2019 612,000 August 31, 2019 909,000 On January 1, 2018, the company obtained a $3,100,000 construction loan with a 12% interest rate....
On January 1, 2018, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2019. Expenditures on the project were as follows: January 1, 2018 March 1, 2018 June 30, 2018 October 1, 2018 January 31, 2019 April 30, 2019 August 31, 2019 $1,000.000 840,000 480.009 630.000 630,eee 945,000 1,620, DBC On January 1, 2018, the company obtained a $3 million construction loan with a 11% interest...
On January 1, 2018, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2019. Expenditures on the project were as follows: January 1, 2018 $ 2,020,000 March 1, 2018 1,740,000 June 30, 2018 1,940,000 October 1, 2018 1,740,000 January 31, 2019 441,000 April 30, 2019 774,000 August 31, 2019 1,071,000 On January 1, 2018, the company obtained a $4,900,000 construction loan with a 12% interest rate....
explain it please Check my work On January 1, 2018, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2019 Expenditures on the project were as follows: January 1, 2018 March 1, 2018 June 30, 2018 October 1, 2018 January 31, 2019 April 30, 2019 August 31, 2019 $1,000,000 600,000 800,000 600.000 270,000 585,000 900,000 On January 1, 2018, the company obtained a $3 million construction...
On January 1, 2021, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2022. Expenditures on the project were as follows: January 1, 2021 March 1, 2021 June 30, 2021 October 1, 2021 January 31, 2022 April 30, 2022 August 31, 2022 $1,280,000 960,000 1,160,000 960,000 324,000 657,000 954,000 On January 1, 2021, the company obtained a $3,600,000 construction loan with a 15% interest rate. The...
help please O t 2018, the Mason Manufacturing Company began construction of a building to be used as its office en The bug was completed on September 30, 2019 Expenditures on the project were as follows: G . January 1, 2018 March 1, 2018 June 10, 2018 October 1, 2018 January 31, 2019 April , 2019 August 31, 2019 51,070,000 340,000 380,000 710,000 1,170,000 1,485,000 2,700,000 On January 1, 2018, the company obtained a $3 million construction loan with a...