Question

Tyde Company is presented with the following two mutually exclusive projects. The required return for both...

Tyde Company is presented with the following two mutually exclusive projects. The required return for both projects is 14 percent.

Year. PROJECT A. PROJECT B

0. -$140,000. -$365000

1. 64,500. 147,500

2. 82,500. 190,000

3. 73,500. 132,500

4. 59,500. 120,000

a. What is the IRR for each project? ( Do not round intermediate calculations and enter answer as a percent rounded to 2 decimal places)

b. What is the NPV for each project?

c. Which, if either, of the projects should the company accept?

0 0
Add a comment Improve this question Transcribed image text
Answer #1

U 1 Year V W Project A Project B 0 -140000 -365000 64500 147500 82500 190000 73500 132500 59500 120000 35.38% 23.65% 64899.20

V 1. W 1 Year 20 4 5 2 3 Project A Project B - 140000 -365000 64500 147500 82500 190000 73500 132500 59500 120000 =IRR(V2:16)

Part a:
IRR of project A is 35.38%
IRR of project B is 23.65%

Part b:
NPV of project A is $64899.20
NPV of project B is $71068.15

Part c:
Given that the projects are mutually exclusive, it means out of a set of projects only one project can be selected.
So, the project with higher NPV should be accepted because it will increase the shareholders' value by higher amount. Hence, project B should be accepted.

Add a comment
Know the answer?
Add Answer to:
Tyde Company is presented with the following two mutually exclusive projects. The required return for both...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Bausch Company is presented with the following two mutually exclusive projects. The required return for both...

    Bausch Company is presented with the following two mutually exclusive projects. The required return for both projects is 13 percent. Year Project M -$135,000 65,000 83.000 74,000 60,000 Project N -$370,000 145,000 195.000 130.000 125,000 2 a. What is the IRR for each project? (Do not round intermediate calculations and enter your answers as a percent rounded to 2 decimal places, e.g., 32.16.) b. What is the NPV for each project? (Do not round intermediate calculations and round your answers...

  • Bausch Company is presented with the following two mutually exclusive projects. The required return for both...

    Bausch Company is presented with the following two mutually exclusive projects. The required return for both projects is 15 percent. Year ہے 40 points Project M -$140,000 61,500 73,400 68,100 40,500 Project N -$359,000 159,300 168,400 154,800 110,400 یہ بیا هم eBook Print References a. What is the IRR for each project? (Do not round Intermediate calculations and enter your answer as a percent rounded to 2 decimal places, e.g., 32.16.) b. What is the NPV for each project? (Do...

  • Bausch Company is presented with the following two mutually exclusive projects. The required return for both projects i...

    Bausch Company is presented with the following two mutually exclusive projects. The required return for both projects is 20 percent. Year Project M. -$142,000 64,300 82,300 73,300 59,300 Project N. -$363,000 148,500 188,000 133,500 118,000 a. What is the IRR for each project? (Do not round intermediate calculations and enter your answers as a percent rounded to 2 decimal places, e.g., 32.16.) b. What is the NPV for each project? (Do not round intermediate calculations and round your answers to...

  • Bausch Company is presented with the following two mutually exclusive projects. The required return for both projects i...

    Bausch Company is presented with the following two mutually exclusive projects. The required return for both projects is 20 percent. Year Project M. -$142,000 64,300 82,300 73,300 59,300 Project N. -$363,000 148,500 188,000 133,500 118,000 a. What is the IRR for each project? (Do not round intermediate calculations and enter your answers as a percent rounded to 2 decimal places, e.g., 32.16.) b. What is the NPV for each project? (Do not round intermediate calculations and round your answers to...

  • Bausch Company is presented with the following two mutually exclusive projects. The required return for both...

    Bausch Company is presented with the following two mutually exclusive projects. The required return for both projects is 17 percent. Year O-NM Project M $138,000 64,700 82,700 73,700 59.700 Project N -$367,000 146,500 192,000 131,500 122.000 a. What is the IRR for each project? (Do not round intermediate calculations and enter your answers as a percent rounded to 2 decimal places, e.g. 32.16.) b. What is the NPV for each project? (Do not round intermediate calculations and round your answers...

  • Bausch Company is presented with the following two mutually exclusive projects. The required return for both...

    Bausch Company is presented with the following two mutually exclusive projects. The required return for both projects is 20 percent. Year Project M Project N 0 –$139,000      –$356,000      1 63,600      152,000      2 81,600      181,000      3 72,600      137,000      4 58,600      111,000      a. What is the IRR for each project? (Do not round intermediate calculations and enter your answers as a percent rounded to 2 decimal places, e.g., 32.16.) b. What is...

  • Bausch Company is presented with the following two mutually exclusive projects. The required return for both...

    Bausch Company is presented with the following two mutually exclusive projects. The required return for both projects is 17 percent. Project N Year Project M -$145,000 -$360,000 64,000 82,000 73,000 59,000 0 1 150,000 185,000 135,000 115,000 2 3 4 a. What is the IRR for each project? (Do not round intermediate calculations and enter your answers as a percent rounded to 2 decimal places, e.g., 32.16.) b. What is the NPV for each project? (Do not round intermediate calculations...

  • Bausch Company is presented with the following two mutually exclusive projects. The required return for both...

    Bausch Company is presented with the following two mutually exclusive projects. The required return for both projects is 15 percent. Project N Project M -S140,000 61,500 73,400 68,100 40,500 -$359,000 159,300 168,400 154,800 110,400 a. What is the IRR for each project? b. What is the NPV for each project? C. Which, if either, of the projects should the company accept?

  • Kerron Company is presented with the following two mutually exclusive projects. The required return for both...

    Kerron Company is presented with the following two mutually exclusive projects. The required return for both projects is 15 percent. Year Project M Project N 0 -$125,000 -$310,000 1 57,000 135,000 2 64,000 161,000 3 59,000 129,000 4 34,000 92,000 Required: (a) What is the IRR for each project? (Do not round intermediate calculations. Enter your answer as a percentage rounded to 2 decimal places (e.g., 32.16).) IRR Project M% Project N % (b) What is the NPV for each...

  • NPV and IRR. Reece Company is presented with the following two mutually exclusive projects. The required return f...

    NPV and IRR. Reece Company is presented with the following two mutually exclusive projects. The required return for both projects is 15 percent. Year Project M Project N -$150,000 -$372,000 68,600 159,300 193,200 154,800 2 76,800 71,300 110,400 &se40,500 What is the IRR for each project? a. What is the NPV for each project? b. Which, if either, of the projects should the company accept? C. O-23

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT